Title: Selected Topics of Software Engineering - Distributed Software Development
1Distributed software development
11-10-09
2ColdWatch
Project Plan Ante Ivankovic Usman Alam
11-10-09
3Overview
- Project Overview
- Development methodology
- Deliverables
- Communication
- Milestones
- Activity plan
- Financial plan
- Project risks
-
11-10-09
4Project overview
- Sub-zero temperatures in facilities cause pipe
bursts - Possible solution Passive heating system
-
5Development methodology (1)
- Scrum framework
- Product owner
- Product backlog
- Scrum master
- Servent leader
- Team
- Self-organizing, self-lead
- Meetings
- Sprint planning
- Daily scrum
- Sprint review and retrospective
6Development methodology (2)
7Deliverables (1)
To Output Planned date
Supervisor / Customer Project plan document 2011-10-21
Supervisor / Customer Requirement definition document 2011-10-21
Supervisor / Customer Design description document 2011-10-28
Supervisor SW Integration Alpha Version 2011-11-22
Supervisor SW Integration Beta Version 2011-12-13
Supervisor / Customer Acceptance test plan 2011-12-16
Supervisor / Customer Test report 2012-01-09
Supervisor / Customer Final project peport 2012-01-13
Supervisor / Customer Final product 2012-01-13
8Deliverables (2)
To Output Planned date
Supervisor Summary week report Every monday
Supervisor Minutes of meeting During project
Team members Technical standards documents During project
Supervisor / Customer Revisions of existing documents When needed
9Communication
10Milestones
11Activity Plan
12Financial Plan
- Costs are based on provisional activity plan
13Graphical Representation
14Project risks
Risk Level Prevention
Data loss High Regular bacups
Missing the internal scheduld deliverables Medium Flagging the issue in time
Improper estimation of resources High Scope of the project has to be estimated appropriately
Lack of communication within team Medium A clear-cut transparency required
Incompatible platforms High Proper selection of platforms
Unavailability of a member Meddium Proper hand-over has to be done