Target Rebuild
  • Two sets of actuator coils failed in the off-line
    demonstrator target during February
  • Permission being sought for limited run of
    on-line target during imminent machine physics
    period other than that we are effectively
    stopped
  • We need to
  • Understand problems with coils
  • Re-manufacture and test
  • Re-make affected mechanical parts (flanges, tubes
    and shafts)
  • Re-assemble targets 1 2
  • Carry out pre-test run
  • Re-install in ISIS and R78 respectively

2
Target Rebuild
  • Jobs Dates
  • Steve York (mechanical) and Steve Griffiths
    (electrical) will oversee technical management
  • Talk to Deritend about coil re-design 7thMarch
  • Ditto Tesla Engineering, or similar - mid March
  • Get help from Steve Griffiths at DL done
  • Coil re-design and test programme defined end
    March?
  • Delivery of new permanent magnets Mid April?
  • Delivery of new coils Mid April
  • Delivery of new flanges and tubes 6th April
  • Delivery of new shafts 1st April?
  • DLC coating of shafts bearings 5th April?
  • Re-assembly of both targets complete 10th May?
  • Pre-testing at Sheffield or R78 10th-15th May?
  • Install Target 1 in ISIS 15th May?
  • Dates in Blue are real
  • So, target not operational until end of Summer
    shutdown