Title: Placing and Finishing Concrete
1Placing and Finishing Concrete
2Basic Requirements for Placing Concrete (1)
- Preserve concrete quality
- Water-cement ratio
- Slump
- Air-content
- Homogeneity
- Avoid separation of aggregate and mortar
3Basic Requirements for Placing Concrete (2)
- Avoid excessive horizontal movement
- Consolidate adequately
- Maintain sufficient placement capacity
- Choose the right equipment for the concrete
4Preparation Before Placing Includes
5Preparation Before Placing Includes
6Preparation Before Placing Includes
7Depositing Concrete
- DO NOT
- (a) disturb saturated subgrades so bearing
capacity is maintained - (b) deposit on frozen subgrade
- Deposit continuously and as near as possible to
its final position - Rate of placement should be such that previously
placed concrete has not set when the next layer
is placed upon it
8Depositing Concrete
Slab Construction
- Start placing along perimeter at one end with
each batch discharged against previously placed
concrete - Do not
- (a) dump in separate piles then level and
work together - (b) deposit in large piles then move
horizontally into position - These practices result in segregation
- (mortar flows ahead of coarser material)
9Depositing Concrete
Effective use of wheelbarrows
Discharging into previously placed concrete
10Incorrect Placement with Conveyor Belt
Baffle
Mortar
Mortar
Rock
Shallow hopper
Rock
Mortar
11Placement with Conveyor Belt
12Depositing Concrete
- Pavement Slab
- Concrete deposited in front of slip form paver by
dump trucks - Concrete spread evenly across the subgrade by the
paver before consolidation and finishing
13Depositing Concrete
Curb/Curb and Gutter
- Concrete deposited into hopper of slip form curb
and gutter machine which then extrudes the
concrete into the desired shape
14Depositing Concrete
Walls
- Deposit in horizontal layers of uniform thickness
- Reinforced 150 mm to 500 mm
- Mass 375 mm to 500 mm
- Consolidate each layer before next is placed
- Timely placement consolidation prevents flow
lines and cold joints
15Horizontal Construction Joint
16Horizontal Construction Joints
17Underwater Placement Methods
- Tremie
- Pump
- Bottom dump buckets
- Grouted preplaced aggregate (specialized)
- Toggle bags
- Bagwork
- Diving bell
18Placing Concrete Under Water
Basic Recommendations
- Water velocity ? 3 m (10 ft) / min.
- Water temperature ? 5C(if below test for
strength gain) - w/c ? 0.45
- Cementing materials content ? 390 kg/m3 (600
lb/yd3) - Slump range 150 to 225 mm (6 to 10 in.)
19Placing Concrete Underwater
- Used Tremie
- Advantages Can be used to funnel concrete down
through the water into the structure. - Watch for Discharge end always has to be buried
in fresh concrete to ensure seal between water
and concrete mass.
20Consolidating Concrete
- Internal Vibration
- External Vibration
21Internal Vibration
Radius of Action
22Internal Vibrators
Diameter of head, mm (in.) Recommended frequency, vibrations per minute Approximate radius of action, mm (in.) Rate of placement,m3/h (yd3/h) Application
20-40 (3/4-1½) 9000-15,000 80-150 (3-6) 0.8-4 (1-5) Plastic and flowing concrete in thin members. Also used for lab test specimens.
30-60 (1¼-2½) 8500-12,500 130-250 (5-10) 2.3-8 (3-10) Plastic concrete in thin walls, columns, beams, precast piles, thin slabs, and along construction joints.
50-90 (2-3½) 8000-12,000 180-360 (7-14) 4.6-15 (6-20) Stiff plastic concrete (less than 80-mm 3-in. slump) in general construction .
Adapted from ACI 309
23Systematic Vibration of Each New Lift
CORRECT Vertical penetration a few inches into
previous lift (which should not yet be rigid) of
systematic regular intervals will give adequate
consolidation
INCORRECT Haphazard random penetration of the
vibrator at all angles and spacings without
sufficient depth will not assure intimate
combination of the two layers
24Placing Concrete in a Sloping Lift
CORRECT Start placing at bottom of slope so that
compaction is increased by weight of newly added
concrete. Vibration consolidates the concrete.
INCORRECT When placing is begun at top of slope
the upper concrete tends to pull apart especially
when vibrated below as this starts flow and
removes from concrete above.
25External Vibration
- Form vibrators
- Vibrating tables
- Surface vibrators
- Vibratory screeds
- Plate vibrators
- Vibratory roller screeds
- Vibratory hand floats or trowels
26Consolidating Concrete
- Inadequate consolidation can result in
- Honeycomb
- Excessive amount of entrapped air voids
(bugholes) - Sand streaks
- Cold joints
- Placement lines
- Subsidence cracking
27Nuclear Gauges to Determine Subbase Compaction
28Screeding (Strikeoff)
- The process of cutting off excess concrete to
bring the top surface of a slab to proper grade
29Vibratory Screeds
30Bullfloating
31Darbying
32Edging
Edging densifies and compacts concrete next to
forms where floating is less effective
- Required along all edge forms,isolation and
construction jointsin floors and exterior slabs - Cut concrete away from formsto a depth of 25 mm
with apointed mason or margin trowel - Edging may be required aftereach subsequent
finishing operation for interior slabs
33Highway Straightedges
34Floating (Power or Hand)
- To embed aggregate particles just beneath the
surface - To remove slight imperfections, humps, and voids
- To compact the mortar at the surface in
preparation for additional finishing operations.
35Troweling
- Creates smooth, hard,dense surface
- Exterior concrete should not be troweled because
- it can lead to a loss of entrained air caused by
overworking the surface - troweled surfaces can be slippery when wet.
36Brooming
37Tining
38Curing and Protection
39Placing on Hardened Concrete
Preparing Hardened Concrete
40Bonding New to Previously Hardened Concrete
- Cement-sand grout
- Latex
- Epoxy
41Isolation Joints
42Contraction Joints
43Spacing of Contraction Joints in Meters
Slab thickness, mm Maximum-size aggregate less than 19 mm Maximum-size aggregate 19 mm and larger
100 2.4 3.0
125 3.0 3.75
150 3.75 4.5
175 4.25 5.25
200 5.0 6.0
225 5.5 6.75
250 6.0 7.5
Metric
44Spacing of Contraction Joints in Feet
Slab thickness, in. Maximum-size aggregate less than ¾ in. Maximum-size aggregate ¾ in. and larger
4 8 10
5 10 13
6 12 15
7 14 18
8 16 20
9 18 23
10 20 25
Inch-Pound
45Making Contraction Joints
Grooving tool on bull-float
Dry-cut sawing concrete
46Construction Joints
47Joint Layout for Slabs
Basic Factors to Remember
- Panels created by contraction joints should be
approximately square - Panel aspect ratio max. 1½ to 1
- Contraction (control) joints should only
terminate at a free edge or at an isolation joint - When joint spacing exceeds 4.5 m (15 ft), load
transfer by aggregate interlock decreases
significantly
48Typical Joint Layout
49 Finishing Operations
Single Course Floors
- Consolidation
- Strike-off
- Edging
- Darbying or Bull Floating
- Lapse of Time
- Edging
- Grooving (if desired)
- Floating (power or hand)
- Troweling (power or hand)
- Lapse of Time
- Second Troweling (power or hand)
- Final Troweling (hand)
- Curing
50 Finishing Operations - Exterior Slabs
Sidewalks, Driveways etc.
- Consolidation
- Strike-off
- Depress aggregate with metal/wood strip at joint
location if hand tooled - Darbying or Bull floating
- Lapse of time
- Edging
- Jointing (optional if hand tooled)
- Floating
- Lapse of time
- Texturing (brooming/swirl float finish)
- Curing
51Patching
52Curing Patches
53Cleaning Concrete Surfaces
- Cleaning methods
- Water
- Chemical
- Mechanical
54Finishing Formed Surfaces
- Rough-form finishes
- Smooth off-the-form finish
- Smooth, rubbed finish
- Sand-floated finish
- Grout cleandown
- (sack-rubbed finish)
55Special Surface Finishes
- Pattern and Textures
- Exposed Aggregate Concrete
- Colored Finishes
- Stains, Paints and Clear Coatings
56(No Transcript)
57Working Safely with Concrete
- Protect
- Your Eyes
- Your Back
- Your Skin
58Precautions
WARNING Contact with wet (unhardened) concrete,
mortar, cement, or cement mixtures can cause SKIN
IRRITATION, SEVERE CHEMICAL BURNS (THIRD-DEGREE),
or SERIOUS EYE DAMAGE. Frequent exposure may be
associated with irritant and/or allergic contact
dermatitis. Wear water-proof gloves, a
long-sleeved shirt, full-length trousers, and
proper eye protection when working with these
materials. If you have to stand in wet concrete,
use waterproof boots that are high enough to keep
concrete from flowing into them. Wash wet
concrete, mortar, cement, or cement mixtures from
your skin immediately. Flush eyes with clean
water immediately after contact. In-direct
contact through clothing can be as serious as
direct contact, so promptly rinse out wet
concrete, mortar, cement, or cement mixtures from
clothing. Seek immediate medical attention if you
have persistent or severe discomfort.
http//www.cement.org/pdf_files/ms271.pdf
59Videos 1/4
Placing and Consolidating
Vibration
60Videos 2/4
Finishing I
Finishing II
61Videos 3/4
Contraction Joints
Jointing
62Videos 4/4
Improper Finishing