Transcript and Presenter's Notes

Title: A Design-Build Success Story


1
Landfill Gas Migration Control
  • A Design-Build Success Story
  • Dick Sprague
  • HDR, Inc.

2
Purpose Background
  • Design-Build Project Delivery
  • Emerging delivery system in public sector
  • Single source of responsibility
  • Faster, less contentious delivery
  • Not necessarily cheaper
  • Landfill
  • Historic landfill cell began in early 1950s
  • New, lined landfill cell began in late 1990s
  • Landfill gas migration discovered in 2001

3
Landfill Site
4
Landfill Gas Migration
  • Anaerobic decomposition
  • Predominantly methane and carbon dioxide
  • March 2001 monitoring
  • High concentrations of Lfg at property boundary
  • gt1,000 feet beyond property boundary
  • May 2001
  • Issued engineering RFP
  • Informed state agency neighbors

5
Extent of Contamination
6

7
Design-Build Project
  • Too little time for traditional design-bid-build
  • 2-part contract
  • Several form contracts
  • AGC, AIA, EJCDC
  • DBIA is fairest to all parties
  • 2-Part form contract includes
  • Terms Conditions
  • Scope
  • Price Schedule

8
Design-Build Project (cont.)
  • Part I - Concept Design Proposal
  • 30 Design
  • Proposal for Part II
  • Firm, fixed price based on bids
  • Drilling subcontractor
  • Equipment supplier
  • Balance of construction contractor
  • Documents Belong to Owner
  • Negotiate with Part I contractor
  • Bid the work
  • Cancel the project

9
Design-Build Project (cont.)
  • Part II
  • Final Design
  • Construction, Start-up Warantee
  • Firm schedule based on WES commitments
  • Contract (part II) signed on September 27
  • Completion planned for December 14
  • Best Value Selection

10
Design-Build Project (cont.)

11
Design-Build Project (cont.)
  • Performance
  • Drilling subcontractor failed to perform
  • Primarily his lower tier subs
  • Third lower tier sub required to complete project
  • Flare station operational December 14, accepted
    December 18
  • 60 percent of wells operational on December 18
    met commitment to state agency
  • Final completion January 18

12
Design-Build Project (cont.)

13
Design-Build Project (cont.)

14
Design-Build Project (cont.)

15
Design-Build Project (cont.)

16
Design-Build Project (cont.)
Event Planned Actual
Engineering Contract June 18 July 20
Construction Contract October 1 September 27
Begin Construction October 15 October 2
System Startup December 18
System Complete December 15 January 18

17
Design-Build Project (cont.)
  • Lump Sum Price
  • Change Orders
  • Net Price

18
Design-Build Project (cont.)
  • Lump Sum Price
  • Change Orders
  • Net Price
  • 929,367
  • ( 25,129)
  • _________
  • 904,238

19
Questions?
20
Design-Build Project (cont.)