Title: Waste Code of Practice
1Waste Code of Practice one year on
2Outline of presentation
- Waste Code of Practice interpretation, lessons
learnt, feedback, evolution, next steps - Landowner perspective
- Background to Code of Practice (how, why)
- Principles and scope of Code
- Benefits
- Progress
- Lessons learnt one year one
- Implications for Cluster
- Next steps (including Direct Transfer and Fixed
Soil Treatment facilities)
3Youll know us by one name or another!
4National Grid Perspective - Landowner
- Manages environmental risks associated with its
gasworks portfolio (both surplus and operational
land) and electricity-related sites. - Operates both in UK and US
- Historical use of sites
- Remediation programme sustained for c.15 years
- Sale of surplus property and significant
contribution to UK Brownfield regeneration - High materials re-use in remediation programme
- Leading user of remediation technologies
5What I am talking about
6Who When - Where?
- CLAIRE (chair)
- Environment Agency
- English Partnerships
- Industry representative
- SAGTA
- EIC
- HBF
- Launched in Sept 2008
- England Wales only
- Represents the further work cited in 2006
Environment Agency document The Definition of
Waste Developing greenfield and brownfield Sites
April 2006 - Field-tested on Cluster pilot project in England
7Why did we need the Code?
8First two Cluster sites
9Scope of CoP Principle Considerations
- Excavated soils both contaminated and
uncontaminated - Risk-based
- Does not undermine Waste Framework Directive
- Definitive point at which Waste ceases to be
waste - Lines of evidence
- Suitability
- Quantity
- Certainty
- Materials Management Plan
- Review and Declaration by Qualified Person (QP)
- Reality recorded via Verification Report on
completion - Aligns with CLR11 process
10Existing scope of Code of Practice
Re-used on site of origin with out treatment.
- Site of origin
- (CLUSTER Donor site)
On site Treatment (EP)
Re-used on site of origin following treatment
CLUSTER Hub site
Cluster receiver site
11Future scope of Code of Practice
Re-used on site of origin with out treatment.
- Site of origin
- (CLUSTER Donor site)
On site Treatment (EP)
Re-used on site of origin following treatment
CLUSTER Hub site
Fixed soil treatment facility
Direct transfer and use on another site
Cluster receiver site
Receiver Site
12Benefits
- Increased re-use of excavated soils with
consequential savings on transport miles and
natural resources - Waste ceases to be waste before backfilling as
opposed after backfilling. - Important when backfilling at another site (e.g.
Cluster) - Helps to reduce the blighting factor associated
with waste licensing - Direct Transfer opportunities have the potential
to- - allow greater flexibility in material reuse
- create a step-change in best practice and
value-solutions
13Step Change
Step-change in Improvement e.g. Code of Practice
Value
Continuous improvement e.g. better remediation
techniques Quicker analytical methods etc.
Time
14Progress one year on
- Training and registration
- No. of trained individuals 220
- No. of registered qualified persons 70
- Applications
- No. of declarations with Environment Agency 17
15Reasons for rate of uptake
- Lower levels of Construction activity
- Exemptions remain as alternative (for the moment)
- Waiting for trained individuals to provide
services - Others waiting for process to mature before using
16Lessons learnt one year on
- Improvement to format of Materials Management
Plan - Number of Frequency Asked Questions (51 no.)
- Qualified Person
- Cluster
- Verification reports
- Relevant factors
- Aggregates protocol
17What it means for Cluster?
Site A
Landfill
- A to B. 4000 m3 for treatment
- From A. 2000 m3 to landfill
- B to A. Return 4000 m3 treated for backfill
- B to A. 2000 m3 of surplus stockpile for backfill
- C to B. 3000m3 for treatment
- B. to C. 3000 m3 surplus stockpile for backfill
- From D. 3000m3 to landfill
- B to D. 3000 m3 of treated soils (originally from
C)
Site B
Site D
Site C
Landfill
18Constraints to Cluster
- Used to be Definition of Waste
- Now waste issue largely unlocked
- Exchange of materials remains important variation
- Direct transfer
- Main constraints now
- Planning regulations
- Perceptions of waste management centres
- Inclusion of sites that are not part of a
pre-defined Cluster - Multi-landowner contractual arrangements
19Complexities of Cluster
20Direct Transfer
- Proposals drafted by steering group for
consideration by Environment Agency - Similar to re-use at site of origin
- Materials meet relevant criteria
- Holder of material to be satisfied
- Signed declaration from Qualified Person
- Either Donor or Receiver site can own process
21Fixed Soil Treatment Facilities
- Could operate as a Cluster site under current CoP
but commercially inefficient - Role for operator as holder of the waste
- Cease to be waste prior to dispatch
- Most efficient if can be producing
specification-grade materials - Use Direct Transfer approach in short-term
22Next steps and concluding thoughts
- Direct Transfer and Fixed Soil Treatment
Facilities - Use following changes to how exemptions are used
- Greater use of Code across sector
- Market-development in provision of Qualified
Person services - Evolution and integration of material management
plans and site waste management plans - Overlaps with other Construction sector
activities - Celebrate and build on success
- Better regulation. EA engagement. Cross-sector
support - Delivering sustainability. Solution not a problem
23Accessing Code of Practise
- CoP is freely available on CLAIRE website
www.claire.co.uk - QP training is offered by CLAIRE. Contact
Kirstie McCulloch cop_at_claire.co.uk - CLAIRE maintain register of attendance on QP
training. - CLAIRE is the recognised registration body for
QP. - Example of Materials Management Plan to be on
www.claire.co.uk - FAQs - EA web site (about code and regulatory
position) - FAQs - CLAIRE web site (generated from training
events and steering group re practical aspects
of use of code) - Thank you for your attention