Title: TOP-DOWN CONSTRUCTION METHOD


1
TOP-DOWN CONSTRUCTION METHOD
  • Use of diaphragm wall as the side support for
    the earth
  • Construction progress upwards and downwards at
    the same time
  • Savings in construction time
  • Schematics and pictures give ideas on ongoing
    activities during construction

2
Diaphragm Wall Installation
3
Conventional Open-cut Bottom-up Construction
Method (For comparison with Top-Down Method)
4
Conventional Open-cut Bottom-up Construction
Method (For comparison with Top-Down Method)
5
Top-Down Construction Method
6
Top-Down Construction Method
7
Main Advantage of Top-Down Construction
8
Details of Top-Down Construction Method
9
Excavation to Level -1
10
Excavate to Level -2
11
Compaction and leveling of basement slab for
reinforcement and concrete works
12
Circular ramp beam and wall supported on bored
column
13
Excavation work of Level -3 in progress, use of
clamp-shell for exc.
14
Excavation of Ramp Level -3 to - 4 in progress
15
More excavation work in progress
16
More excavation work of lower levels inprogress
17
Above ground, structure works in progress
18
Typical basement reinforcement slab ready for
concreting
19
Concreting of basement slab for top-down
construction method
20
Top-down construction work in progress
21
Complete construction of project
22
Another example of top-down construction
23
Another example of top-down construction
24
Conclusion
  • Need careful consideration for use in HCMC since
    method is new here
  • Ideal for 5 basements or more
  • May need some soil improvement techniques and
    good dewatering system
  • Equipment for these works may not be readily
    available in HCMC
  • Handling of excavated soil material require
    planning, keeping in mind marine clay at upper
    level and silty sand at lower level