What is Stocked? - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

What is Stocked?

Description:

(MRP I) Manufacturing Resources Planning (MRP II) Manufacturing Systems History 1950 s Stock Replenishment using EBQ, ROL, ROQ, etc. 1960 s MRP - Forward planning ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 34
Provided by: Gateway2045
Category:

less

Transcript and Presenter's Notes

Title: What is Stocked?


1
Materials Requirements Planning (MRP
I) Manufacturing Resources Planning (MRP II)
2
Manufacturing Systems History
  • 1950s Stock Replenishment using EBQ, ROL, ROQ,
    etc.
  • 1960s MRP - Forward planning of dependent
    demands.
  • 1970s MRP - Rescheduling to keep order dates
    valid.
  • JIT - Manufacturing in Japan.
  • 1975s Closed loop MRP with feedback.
  • OPT scheduling of bottlenecks.
  • 1980s MRP2/RDBMS JIT linkages.
  • 1985s Simulation and Factory Management's
    Systems.
  • 1990s Computer Integrated Manufacturing
    Enterprise Integration
  • 2000 ERP, Extended Enterprise Supply Chain
    Integration

3
Dependent Demand
  • When it is directly related to, or derives from,
    the demand for another inventory item or product
  • For example Demand for a TV component is
    dependent upon the demands for TV sets
  • OR where demand is derived
  • For example The demand for TV sets at the
    factory is determined by demand from the retailer
    which is derived from ultimate demand in the
    market place

4
Independent Demand
  • When demand is unrelated to demand for other
    items.
  • Or When it is not a function of demand for other
    items.
  • In these cases we use Re-order point system OR
    Re-order cycle system

5
MRP Structure
Master Production Schedule
MRP Analysis
Stock Status
Bill of Materials
Reports
6
MPS - Purposes
  • Links production plans to day to day operations
  • Forms basis for managerial control
  • Basis for integration of activities
  • Demand management functions

7
Master Schedule for Product X
Output per week
Weeks into Future
8
Spare Parts Demand for Assembly A
Assembly A
Firm Orders
Forecast Orders
Order Quantity
1 2 3 4 5 6 7 8 9 10
11 121
Weeks into Future
9
Inputs into the MPS
Known Orders
Forecast Deamnd
Key Capacity Constraints
Sister Plant Demand
Master Production Schedule
Inventory Levels
RD Demand
Spares Demand
Exhibition/ promotion Requirements
Safety Stock Requirements
10
Master Schedule with Variable Length Time Periods
Today
Future
MASTER SCHEDULE
Days
Weeks
Months
Quarters
1 2 3 4 5
2 3 4
2 3 4 5 6
3 4 5 6
11
Product Structure for chair
Chair
Level 0 Finished Product
4
1
2
2
1
1
Level 1 Sub- assembly
Frame
Back Cushion
Seat Cushion
Wood End
Cross-piece (Chair)
0.45
1.4
0.6
0.5
3
3
0.7
2.2
0.55
Level 2 Raw Material
Webbing
Tube
Fabric
Foam
Wood
Fastener
Notes Indicates common item with settee. The
number to the left of each link shows the
number/quantity of the lower -level item needed
in the manufacture of the higher-level item.
12
Bill Of Material - BOM
  • Maintains Parts and Structures used for Product
    definition in a manufacturing company
  • Parts in a BOM, include Assemblies,
    Sub-assemblies, parts, bought out items, and
    materials
  • Each part needs a unique identification - number,
    brief description, and other reference codes
  • The structure shows the relationships of one part
    with another
  • The BOM is not a parts list, but defines how a
    product is made
  • BOM is usually the first module to be installed

13
BOM Outputs
  • SINGLE LEVEL BOM
  • Shows the structure of a BOM one level down.
  • MULTI LEVEL BOM
  • Shows the structure of a BOM through all
    levels.
  • INDENTED BOM
  • Where the part number within a multi level BOM
    is displaced by one digit for each level.
  • 0.23456 Assembly
  • 0.13247 Sub Assembly
  • 0.33457 Part
  • 0.13248 Sub Assembly
  • 0.33468 Part

14
Uses of BOM
  • Product Definition
  • Manufacturing Instructions
  • Engineering Change Control
  • Services Parts Support
  • Materials Procurement
  • Production Scheduling
  • Parts Kitting
  • Costing

15
Inventory Analysis
  • Inventory classification by part or material type
  • Annual usage by quantity and value
  • Balance on hand by quantity and value
  • Turnover ratio
  • Active inventory value (balance on hand not
    exceeding gross usage unit cost)
  • Percent active inventory
  • Inactive inventory amount value
  • Inventory valuations

16
Stock condition route for a part
On Order
Goods receiving uninspected
Goods receiving inspected
Raw Material Store
Work in Progress
Finished Parts Store Free
Final Assembly
Finished Parts Store Allocated
Dispatched
Kitting Dept
17
Work in Progress Stock Condition
Raw Material Store
Op 1 Cast
Op 2 Mill
Op 3 Grind
Finished Parts Store
Op 4 Inspect
Op 6 Inspect
Op 5 Paint
18
MRP LOGIC
  • Master Production Schedule
  • MRP explosion using BOM
  • Lower level gross requirements
  • Net requirements - netting out Inventory
    scheduled receipts
  • Applying order policies
  • Order release dates obtained by off setting lead
    times
  • Planned / confirmed orders
  • Rescheduling

19
Definition of MRP
Master Production Schedule (MPS)
MRP Analysis
Inventory Status Data
Bill of Materials (BOM)
Release Orders
Planned Orders
Reschedule Orders
20
MRP
  • Basic MRP handles material aspects of production
    control
  • Simple MRP systems based on MPS, BOM, inventory
    records and material requirements
  • A number of software companies have developed
    inter-related files to provide a more complete
    picture
  • MRP I assumes that resources available are
    constant

21
MRP II
  • called a closed loop system
  • a push system
  • Forecasts are generated at the outset and
    manufacturing plan developed to meet these
    demands
  • The plan then drives the manufacture through the
    issue of work orders

22
MRP II
  • Essentially a computerized database of parts,
    components, finished goods, WIP and requirements
  • Lead time and relationships between parts are
    held in a database
  • The computer then calculates the best way to meet
    the MPS (which is based on forecasts firm
    orders etc.)

23
MRP2 - Manufacturing Modules
Production Planning
Forecasts
Resource Requirement Planning
Rough Cut Capacity Planning
Master Production Scheduling
Customer Orders
Material Requirement Planning
Capacity Requirement Planning
Production Activity Control
Purchasing
Dispatching
Input/Output Control
24
MRP
  • best suited to companies making discrete
    multi-component items
  • it provides mgt with an accurate record of
    inventory related activities
  • it enables mgt to make accurate predications and
    highlight problems
  • it enables optimisation of resources
  • inventory levels or lead times generally reduced
  • mgt commitment essential to make a positive impact

25
MRP II system works as follows
  • MPS is drawn up (based on forecasts, orders etc.)
  • MPS is checked for feasibility in gross capacity
    terms (rough cut capacity planning).Once a
    feasible plan is agreed it is input into the
    materials requirements planning module
  • Material requirements are calculated and schedule
    of quantity and time determined
  • These requirements are then exploded in the BOM
    file (which provides a breakdown of a product
    into its constituent parts)

26
MRP II system works as follows contd..
  • Net requirements are then calculated by deducting
    available inventory from gross requirements.
  • In a closed loop system their capacity
    requirements would be checked against resource
    availability. (estimated capacity planning) with
    user able to decide on different variables such
    as lot sizes and start dates.
  • Finally works orders are fed into the live system
    where a schedule is calculated to take account of
    the day-to-day situation on the shop floor.

27
Materials Requirement Planning (MRP)
  • Assume currently week 1
  • Orders are
  • Wk 8 200 settees
  • Wk 9 350 chairs
  • Wk 7 100 replacement seat cushions
  • GR Gross requirements
  • NR Net requirements
  • OH On-hand stock
  • OD Orders Due
  • SS Safety Stock
  • PO Planned Orders/start

28
MRP example
  • For chair
  • GR 350 (wk 9)
  • NR GR - OH - OD SS
  • 350 - 25 - 0 20 345 (wk 9)
  • Since lead time 1 wk, PO 345 (wk 8)
  • For settees
  • GR 200 (wk 8)
  • NR GR - OH - OD SS
  • 200 - 30 -0 20 190 (wk 8)
  • Since lead time 1 wk, PO 190 (wk 7)

29
MRP example
  • Cascading down to level 1 items, all items should
    be considered, but for the purposes of this
    illustration only cushions will be considered.
  • For back Cushions
  • GR 190 x 2 380 (wk 7)
  • (PO for 190 settees in wk 7, 2 back
    cushions/settee)
  • NR 380 - 45 - 0 0 335 (wk 7)
  • Since lead time 2 weeks, PO 335 (wk 5)
  • GR 345 (wk 8)
  • (PO for 345 chairs in wk 8)
  • NR 345 - 0 - 0 0 345 (wk 8)
  • Since Lead Time 2 wks, PO 345 (wk 6)

30
MRP example
  • For seat cushions
  • GR 190 x 2 100 (wk 7)
  • (PO for 190 settees in wk 7, 2 seat
    cushions/settee
  • 100 replacement cushions)
  • NR 480 - 45 - 0 0 435 (wk 7)
  • Since lead time 2 weeks, PO 435 (wk 5)
  • GR 345 (wk 8)
  • (PO for 345 chairs in wk 8)
  • NR 345 - 0 - 0 0 345 (wk 8)
  • Since Lead Time 2 wks, PO 345 (wk 6)

31
MRP 2 Modules
  • MANUFACTURING
  • Bill of Materials - BOM
  • Master Production Scheduling - MPS
  • Inventory - INV
  • Material Requirements Planning - MRP
  • Capacity Requirements Planning - CRP
  • Production Activity Control - PAC
  • Purchasing - PUR
  • System Control - SYS
  • BUSINESS/FINANCE
  • Order Processing - ORD
  • Costing Cost Control - COST
  • Sales Ledger - SL
  • Purchase Ledger - PL
  • General/Nominal Ledger - NL
  • Financial Statements -FIN
  • Asset Management - AM
  • Payroll/Salaries- PAY

32
Advantages of MRP2
  • Reduced lead times
  • Inventory turnover increased, value of inventory
    reduced
  • Improved scheduling of purchased made in items
  • On time deliveries improved
  • Greater throughput
  • Costs reduced

33
Summary
  • A tool enables managers to plan control a
    manufacturing business
  • A formal system for scheduling the needs of
    marketing, production and materials
  • A means of integrating management functions and
    their goals
  • The integrated planning tool for more advanced
    manufacturing technologies and CIM
  • A means of getting better results in business
Write a Comment
User Comments (0)
About PowerShow.com