Title: PROJECT MANAGEMENT
1PROJECT MANAGEMENT
- Outline
- What is project mean?
- Examples of projects
- Project Planning and Control
- Project Life Cycle
- Gantt Chart
- PERT/CPM
2What is Project?
- What is the different between normal business
activities and Project? - Project
- Unique, one time operations design to
accomplish a specific set of objectives in a
limited time frame.
3Examples of project
- Building a house
- Building a factory
- Add assembly line in the factory
- Merging to companies
- Managing political campaign
- Designing a new product
- Soft ware development
4In project a lot of problem arise? Why?
- a lot of activities should be handles
- Limited time
- Restricted resources
5Project Planning and Control
- Definition of Project Management
- Work Breakdown Structure
- Project Control
- Organizational Structures
- Critical Path Scheduling
- CPM with a Single Time
- CPM with Three Activity Time Estimates
6Project Management
- Project
- Lengthy network of activities needed to complete
a major output. - Project Management
- Planning, execution, and controlling resources to
needed to complete the project. -
7Project Life Cycle
- Definition
- Why we need to start new project
- Feasibility Analysis (Cost, Benefit , risk of
under taking a project) - Planning
- Details of the work, estimates time, Human
resource and cost - Execution
- During which a project itself is done
- Termination
- During which closer is achieved
8Project Planning, Controlling and Scheduling
- Project Planning
- 1. Setting goals.
- 2. Defining the project.
- 3. Tying needs into timed project activities.
- 4. Organizing the team.
Before Project
9Project Planning, Controlling and Scheduling
- Project Scheduling
- 1. Tying resources to specific activities.
- 2. Relating activities to each other.
- 3. Updating and revising on regular basis.
10Project Planning, Controlling and Scheduling
- Project Controlling
- 1. Monitoring resources, costs, quality and
budgets. - 2. Revising and changing plans.
- 3. Shifting resources to meet demands.
During Project
11Work Breakdown Structure
12Project Control Gantt Chart
- The Gantt chart is a popular tool for planning
and scheduling simple project. - It enables a manager to initially schedule
project activities and then to monitor progress
over time by comparing planned progress to actual
progress
13Project Control Gantt Chart
a
b
a
c
b
d
c
d
d
14PERT and CPM
- PERT (program evaluation and review technique)
- U.S. Navy Special Projects Office (1958)
- Polaris missile project
- CPM (critical path method)
- J. E. Kelly of Remington-Rand and M. R. Walker of
Du Pont (1957) - Scheduling maintenance shutdowns of chemical
processing plants
15Questions answered by PERT/CPM
- When will the entire project be completed?
- What are the critical activities or tasks in the
project, that is, the ones that will delay the
entire project if they are late? - Which are the non-critical activities, that is,
the ones that can run late without delaying the
entire projects completion? - What is the probability that the project will be
completed by a specific date?
16Questions answered by PERT/CPM
- At any particular date, is the project on
schedule, behind schedule, or ahead of schedule? - On any given date, is the money spent equal to,
less than, or greater than the budgeted amount? - Are there enough resources available to finish
the project on time? - If the project is to be finished in a shorter
amount of time, what is the best way to
accomplish this at the least cost?
17To Find Critical Path ???
- To find the critical path, need to determine the
following quantities for each activity in the
network - 1. Earliest start time (ES) the earliest time an
activity can begin without violation of immediate
predecessor requirements. - 2. Earliest finish time (EF) the earliest time
at which an activity can end. - 3. Latest start time (LS) the latest time an
activity can begin without delaying the entire
project. - 4. Latest finish time (LF) the latest time an
activity can end without delaying the entire
project.
18CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities
19First draw the network
C, 1
20Determine early start and early finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
?
C, 1
ES4 EF9
21When I can start depends on when predecessors
finish.
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
C, 1
ES4 EF9
22Determine late starts and late finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
?
LS4 LF9
23Dont delay the project
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
24Critical Path Slack
ES4 EF6
D, 2
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
E, 5
LS4 LF9
Duration 15 weeks
25(No Transcript)
26Activity Times
- To find the expected activity time (t), the beta
distribution weights the estimates as follows
27Activity Times
- The time estimates in PERT are
Optimistic time (a) time an activity will take
if everything goes as well as possible. There
should be only a small probability (say, 1/100)
of this occurring. Pessimistic time (b) time
an activity would take assuming very unfavorable
conditions. There should also be only a small
probability that the activity will really take
this long. Most likely time (m) most realistic
time estimate to complete the activity
28Activity Times
- The time estimates in PERT are
Optimistic time (a) time an activity will take
if everything goes as well as possible. There
should be only a small probability (say, 1/100)
of this occurring. Pessimistic time (b) time
an activity would take assuming very unfavorable
conditions. There should also be only a small
probability that the activity will really take
this long. Most likely time (m) most realistic
time estimate to complete the activity
29- Consider the following project
- Immed. Optimistic Most
Likely Pessimistic - Activity Predec. Time (Hr.) Time
(Hr.) Time (Hr.) - A -- 4
6 8 - B -- 1
4.5 5 - C A 3
3 3 - D A 4
5 6 - E A 0.5
1 1.5 - F B,C 3
4 5 - G B,C 1
1.5 5 - H E,F 5
6 7 - I E,F 2
5 8 - J D,H 2.5
2.75 4.5 - K G,I 3
5 7
30PERT/ CPM
- CPM uses two sets of time and cost estimates for
activities - A normal time and cost and
- A crash time and cost
- The normal cost is an estimate of cost to
complete an activity in normal time. - The crash time is the shortest possible activity
time. - Crash cost is the cost of completing the activity
on a crash or deadline basis.
31Project Crashing with PERT/CPM Four Steps
- Find the normal critical path and identify the
critical activities. - Compute the crash cost per week (or other time
period) for all activities in the network. - This process uses the following formula
32Project Crashing with PERT/CPM Four Steps
- 3. Select the activity on the critical path with
the smallest crash cost per week. - Crash this activity to the maximum extent
possible or to the point at which your desired
deadline has been reached - 4. Check to be sure that the critical path you
were crashing is still critical. - Often, a reduction in activity time along the
critical path causes a non-critical path or paths
to become critical. - If the critical path is still the longest path
through the network, return to step 3. - If not, find the new critical path and return to
step 2.
33Subproject
- For extremely large projects, an activity may be
made of several smaller sub-activities. - Each activity might be viewed as a smaller
project or a subproject of the original project. - The person in charge of the activity might wish
to create a PERT/CPM chart for managing this
subproject. - Many software packages have the ability to
include several levels of subprojects
34In class assignment
- Immediate Completion
- Activity Description
Predecessors Time (days) - A Initial Paperwork
--- 3 - B Build Body
A 3 - C Build Frame
A 2 - D Finish Body
B 3 - E Finish Frame
C 7 - F Final Paperwork B,C
3 - G Mount Body to Frame D,E
6 - H Install Skirt on Frame C
2