Status of PHENIX and Run-12 Prep RPC Installation complete 11/23 RPC Commissioning Ongoing 12/16 VTX/FVTX Installation 12/1-12/6 VTX/FVTX Survey, cabling ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 4
Provided by: Brookhave7
Learn more at: https://www.c-ad.bnl.gov
Category:
Tags: phenix | prep | run | status

less

Transcript and Presenter's Notes

Title: Status of PHENIX and Run-12 Prep


1
Status of PHENIX and Run-12 Prep
  • RPC Installation complete 11/23
  • RPC Commissioning Ongoing 12/16
  • VTX/FVTX Installation 12/1-12/6
  • VTX/FVTX Survey, cabling, plumbing 12/7-12/16
  • East Carriage Roll In Week of 12/12
  • Safety system checkout pink/blue/white
    sheets 12/12-12/23
  • Cool down start 1/17

2
Highlights
VTXFVTX assembly complete. Next pre-installation
tests, pre-survey
RPC1-S installed in Central Magnet
3
Summary
  • PHENIX is on schedule to be fully installed and
    ready for final commissioning at RHIC cryo
    start Jan 17
  • Major 2011 projects are nearing completion (
    VTXFVTX fab and installation, RPC1 fab and
    installation, MuTracker St1 maintenance)
  • The schedule relies on availability of various
    support groups Survey, carpenters, riggers,
    PASS, CAS ..
  • As usual this is well coordinated between Don
    Lynch and Dave Phillips