Title: NADB RGVSG Project Review
1NADB RGVSG Project Review
- Summary Presentation
- San Antonio, Texas
- January 27, 2003
2Introducing Pollutechs Team
- Richard Laughton
- Project Director
- NADB Compliance
- BECC Step 2
- Compliance Issues
- Risk Assessment
- Reporting
- Greg Brown
- Project Manager
- Technical Analysis
- Financial Review
- Regulatory Permits
- Project Feasibility
- Reporting
3Project Description
- The project is a clean energy and air quality
improvement project as defined under the
BECC/NADB mandate expansion. - The project sponsor is the sugar cooperative
identified as the Rio Grande Valley Sugar
Growers, Inc. (RGVSG).
FOR MORE INFO...
http//www.pollutechinternational.com/jobs/nadb/
4RGVSG Facility
The project is located 2½ miles west of Santa
Rosa, Texas (Hidalgo County) in the Lower Rio
Grande Valley on Highway 107.
5Project Goals
- Review proposed system improvements in terms of
capacity and operative compatibility with
existing facility and expected performance,
primarily focussing on equipment related to the
co-generation from bagasse, air quality
improvements, water and energy savings, and
potential waste reduction. - Review and validate proposed technical,
financial, operational, and environmental claims,
costs associated with system improvements, and
electricity sales.
6Technical Viability
- basic systems processes and technologies
- OM experience and requirements
- technical specifications and design
- energy production and sales estimates
- proposed environmental efficiencies
- cost savings, emissions credits, and
- environmental improvement-related credits
7Project Technology
- Upgrades to bagasse handling system
- New higher efficiency boiler and
- New (rebuilt) turbine generator.
8Project Resources
- NADB Project Manager
- RGVSG Management Team
- TCEQ Industry and Approvals Staff
- Schaffer Associates, LLP
- Turner Collie Braden Inc.
- Pollutech International Limited
9Review Procedures
- Background document review
- Site inspection and interviews
- Consultants reports and inquires
- Regulatory analysis and
- Technical and financial analysis.
FOR MORE INFO...
1) Pollutech Technical Review Report 2)
Executive Summary Report
10Project Timeline
- Pollutech Report January 23, 2003
- TCB BECC Step 2 February 3, 2003
- BECC Approval March 20, 2003
- NADB Approval June 2003
- Bagasse upgrade September 2004
- Boiler and GenSet April 2005
11Key Concerns
- Reduction in air emissions
- Change to net power exporter
- Compliance with BECC Step II
- Technically viable and sustainable
- Fits in with RGVSG long term plans
12The Detailed Analysis
- Review Existing Process
- Analyze Proposed Upgrade
- Projected Power Capacities
- Project Air Emissions
- The Financial Analysis
13Key Factors
- Sugar Policy (WTO and Farm Bill)
- Weather Conditions
- Supply of Irrigation Water
- Environmental Limits (air permits)
- Grower co-operation and education
- Plant Production Capabilities
14Process Flowsheet
15Proposed Plant Upgrades
- Schaffer Stage 1
- Production plant upgrades
- Plant increase to 20,000 tcd
- Schaffer Stage 2
- Bagasse handling upgrades
- Power plant upgrade (boiler turbine)
16Proposed Plant Upgrades
- As a result of other restrictions on the plant
capacity increase (i.e. production quotas,
growers capabilities, financing capabilities)
there is no immediate plan to increase the
production capabilities through the Phase 1
expansion. - However, the positive economic and environmental
benefits of the proposed Phase 2 expansion do
warrant those tasks being undertaken at this time.
17Proposed Stage 2 Plant Upgrades
- Bagasse Handling Upgrades
- conversion of all bagasse conveyors to fully
automated (PLC controlled) belt conveyors (for an
increased capacity to handle 20,000 tcd) - expansion and upgrade of the bagasse storage
building - conversion of the boiler building (height and
length) to handle the modified bagasse conveyor
system and to allow for the new boiler 5
18Proposed Stage 2 Plant Upgrades
- Power Plant Upgrade (Boiler Turbine)
- installation of a new high efficiency boiler (5)
with corresponding reduction in the use of the
existing boilers (s 1,2,3,4) - new condensate storage tank
- rebuilt 6,000 KW turbine generator to replace one
of existing 2,500 KW turbine generators
19Power Production
20Proposed Operation
Plant Operation Old Boilers ( capacity) New Boilers ( capacity)
10,000 tcd 34 90
13,500 tcd 67 90
15,000 tcd 85 90
21Proposed Power Capacities
Power Analysis MW Produced MW Purchased MW Sold MW Used
Current 4.3 1.7 0.0 6.0
10,000 tcd 9.6 0.0 5.0 4.6
13,500 tcd 11.8 0.0 4.2 7.6
15,000 tcd 14.0 0.0 9.0 5.0
22Air Emissions
23Projected Air Emissions
Emission Analysis CO tons/year NOx tons/year PM tons/year VOC tons/year
Current 2,458 482 385 157
10,000 tcd 1,320 439 198 79
13,000 tcd 2,191 609 335 134
15,000 tcd 2,564 682 393 158
24Allowable v. Actual Emissions
25Projected Air Emissions
26Financial Analysis - Project Costs
Financial Analysis Bagasse Handling Boiler Turbine Generator TOTAL PROJECT
Project Cost (10 contingency) 6,422,532 13,986,117 3,986,117 23,826,937
27Financial Analysis - Cost Savings
Component Bagasse Handling Boiler Turbine
Conveyor Operation 112,478
Bagasse Storage 135,000
Boiler Maintenance 841,000
Electricity 312,120
Natural Gas 250,000
Excess Power ________ 450,000
TOTAL 247,478 1,853,120
28Financial Analysis - Payback Period
Cost Component Bagasse Handling Boiler Turbine Total Project
Total Cost 6,422,532 17,384,405 23,826,937
Annual Cost Savings 247,478 1,853,120 2,100,598
Payback Period 26.0 Years 9.4 Years 11.3 Years
29Plant Environmental Programs
- TCEQ Site Assistance Visit (P2SAV)
- Emerald Consultants Compliance Audit
- EPA Pilot EMS Program
- Routine Regulatory Compliance
30Air Quality Improvements
- - 42 at 10,000 tcd
- - 0.6 at 13,500 tcd
- 9.0 at 15,000 tcd
31Water Quality Issues
- 100 Recycle
- High Evaporation
- Stormwater Plan
- On-Site WWTP
32Other Environmental Issues
- Solid Waste
- Chemical Waste
- TRI (no reports)
- EMS (in process)
33Emission Reduction Credits
34General Project Validation
- Is the plant proposing to use production and
power generation technology that would be used by
a prudent owner of a similar facility? - Is the pollution abatement equipment that is
proposed BACT-EA?
35General Project Validation
- Will the upgraded facility be able to produce
more power? - Will the total air emissions from the upgraded
facility be significantly less than the existing?
36General Project Validation
- Will the project result in a reduction in the
environmental impacts related to water supply and
discharge? - Has it been demonstrated that there are no
adverse environmental impacts on the neighbouring
community?
37Air Emission Summary
- Immediate and significant 42 decrease in
component and total air emissions at 10,000 tcd. - Reduced air emissions from outside power
producers.
38Power Production Summary
- Currently a net importer of power at
approximately 1.7 MW - Will become a net exporter of power at 5 MW (plus
1.7 MW benefit)
39Compliance with BECC Step 2
- general
- human health and environment
- technical feasibility
- financial feasibility
- project management
- community participation and
- sustainable development.
40BECC Guiding Principles
- Principle 1. The project is centered on energy
conservation and the economic needs of the
region. - Principle 2. The rights of the cooperative
members and surrounding communities to adequately
raise their standard of living and develop their
properties are recognized and underlie the
reasons for undertaking the project.
41BECC Guiding Principles
- Principle 3. Environmental protection is integral
to the project with the promotion of renewable
energy sources and the significant reduction in
air pollutant loadings during operation. - Principle 4. Stakeholders have been involved and
have had the opportunity to participate in the
decision-making process. This not only includes
the cooperative members and surrounding
residents, but also local, regional, state and
federal agencies with statutory interest and
standing in the issues at hand.
42BECC II Community Impact
- Air emissions from the RGVSG will be reduced
while allowing the mill to continue to compete in
an aggressive international market, while at the
same time allowing for increased energy
production (electricity) from the waste biomass
(bagasse).
43BECC II Project Alternatives
- The do nothing alternative means no improvement
in air quality and a less competitive industrial
operation. - More advanced alternatives might provide
additional environmental improvement (i.e. better
emissions control technology, more efficient
energy production methods) but are deemed not to
be economically viable at this time.
44BECC II Financial Feasibility
- The annual cost savings associated with reduced
operating costs, reduced natural gas costs, and
excess power sales are calculated to be
approximately 2,100,000 per year. These cost
savings account for 8.8 of the total project
costs.
45Risk Analysis
- Can this project achieve what is projected in
terms of current and future plant operation, or
are there some undermining limitations that may
increase the risk? - If the plant can go ahead with the upgrade to the
operation with a manageable level of risk in
operations, are we sure that the project they are
proposing is technically sound?
46Risk Analysis
- Can we confirm that all the local, state and
federal environmental regulations will be met?
What are the risks and impacts of occasional
infractions? - Does the plant have the capability to operate and
maintain the upgraded facility, so as to minimize
or eliminate any risk of plant upsets that could
affect either plant profitability or
environmental emissions?
47Risk Analysis
- Does the project result in long term
sustainability for the local area, giving due
consideration to all of the issues required in
the BECC Step II evaluation? - RISK Likelihood x Impact
- Likelihood could it happen?
- Impact what if it happens?
48Cane Production
- 43,000 acres in production
- Yields of 45 tons cane per acre
- Peak generation of 2,000,000 tons cane per year
- Weather and irrigation are critical
- MODERATE RISK
49Sugar Policies
- Current quota of 144,000 tons sugar
- Storage of shortfalls
- Current pricing in the 0.21 range
- Farm Bill expires in 2007-2008
- Mexican and Canadian Issues
- MODERATE RISK
50Production Expansion
- Satisfactory for the next 5 years
- Anticipate 10,000 tcd over 150 days
- Immediate cost savings in operation
- Future growth in Stage 2 upgrades
- LOW RISK
51Plant Profitability
- Reduction in power costs
- Reduction in labour equipment costs
- Payback period of 11.3 years
- EXTEMELY POSITIVE
52Technology Evaluation
- Experience of Schaffer Associates
- Relying on proven technologies
- Manufacturer guarantees
- Proven operation and maintenance
- LIMITED RISK
53Regulatory Issues
- Immediate reduction in air emissions
- Ongoing program for cane burning
- No concerns with water discharge
- Moving to EMS in 2003
- LIMITED RISK
54Environmental Sustainability
- Direct benefit to the local community
- Plant can remain competitive
- Truly a win win situation
55For Further Information
- Pollutech International Limited
- 768 Westgate Road
- Oakville, Ontario CANADA
- Tel 1-905-847-0065
- E-mail laughton_at_pollutech.com
- Web http//www.pollutech.com