Project Scheduling Tools - PowerPoint PPT Presentation

About This Presentation
Title:

Project Scheduling Tools

Description:

Project Scheduling Tools There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start Start B after A is completed SS: Start ... – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 15
Provided by: richardg48
Learn more at: http://www.csun.edu
Category:

less

Transcript and Presenter's Notes

Title: Project Scheduling Tools


1
Project Scheduling Tools
2
1. Sequencing
  • There are four possible sequencing modes in MS
    Project. Suppose B follows A.
  • FS Finish Start Start B after A is completed
  • SS Start Start Start A and B at same time
  • FF Finish Finish Finish A and B at same time
  • SF Start Finish Start A after B is completed
  • Lags are delays between work on activities

3
FS Sequence - Traditional
A
  • B

E.g. Sand and Paint
A
B
Lag
E.g. Sprinklers and Landscape
4
SS Sequence
A
E.g. Plant Lawn and Flowers
  • B

A
E.g. Drywall Hang and Tape
B
Lag
5
FF Sequence
A
E.g. Olympics
  • B

A
Lag
E.g. Olympics
B
6
SF Sequence
A
E.g. Not Practical
  • B

A
B
E.g. Ocean Cruise
Lag
7
2. Activity Uncertainty
  • PERT assumptions (Richard Schonberger and Ken Mac
    Crimmon
  • Beta distribution assumption
  • PERT approximation formula for mean and variance
  • Estimates of a, m, and b
  • Errors of above up to 30, but tend to cancel
  • Worse problem is merge event bias (probability
    near-critical path becomes critical) estimates
    consistently optimistic

8
Example 2.1
B,2
A,1
D,1
C,3
Critical path is ACD but ABD is near critical.
Criticality index probability path critical.
9
Use Simulation or Monte Carlo Analysis
  • Generate random numbers (electronic, formulas,
    tables, books) i.e. 28
  • Convert to random probabilities i.e. .28 What
    is probability of probability?
  • Convert random probability to random variate.
    Follows distribution of say actual activity time.

10
Finding Random Variates, Problem 2.1
  • B C PMF CDF
  • Mean 1 1 2 .3 .3
  • Mean 2 3 .4 .7
  • Mean 1 3 4 .2 .9
  • Mean 2 4 5 .1 1.0
  • Random probability of .28 gives B random variate
    of 1 .46 gives C value of 3.

11
Simulation of Problem 2.1
  • RN B(2) RN C(3) Length Path
  • .28 1 .46 3 5 ACD
  • .97 4 .09 2 6 ABD
  • .63 2 .33 3 5 ACD
  • .53 2 .76 4 6 ACD
  • .73 3 .00 5 7 ACD
  • Expected length 5.8 gt 5 (merge event bias)
  • Criticality index of ACD 0.8 or 80

12
Project Simulation
  • Simulation includes
  • GERT Graphical Evaluation and Review Technique
  • Crystal Ball Copy comes with text
  • Simulation includes
  • Probabilistic branching from node B may follow
    A
  • Probabilistic times for activities various
    distributions
  • Flexibility in node realization activity time
    can 0
  • Looping permitted rework
  • Critique of Simulation R. Schonberger
    recommends intensive critical path scrutiny

13
3. Limited Resource Scheduling
  • Resources include labor, material, equipment,
    space, and money
  • Money versus time tradeoffs
  • Methods
  • Crashing How to shorten activities cost
    penalties
  • Resource loading amount of resource needed per
    period.
  • Resource leveling or balancing evening out
    resource use, reacting to limited resources
  • Simulation programs can help level

14
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com