Title: Resource Offer Commitment Parameters
1Resource Offer Commitment Parameters
- Structured Market Trials August 23, 2013
- Gay Anthony
- SPP Market Design
2Resource Offer Commitment Parameters
- What are the Parameters?
- How are they used in SMT?
- Parameter Relationships
- How the Parameters are used for Commitment
- Examples
Gay Anthony
3Resource Offer Commitment Parameters
- What are the Parameters?
- Time-Related Parameters for Resource Commitment
- Minimum Run Time
- Maximum Run Time
- Minimum Down Time
- Min-To-Off Time
- Sync-To-Min Time
- Hot-to-Cold Time
- Hot-to-Intermediate Time
Gay Anthony
4Commitment Reminders
- DA Market, DA RUC, and ID RUC processes use the
Current Operating Plan (COP) for determining if a
Resource has satisfied submitted Commitment
Parameters - Commit Times are communicated as Start or
Stop notifications - Indicates when SPP expects the resource to be at
minimum - PLEASE NOTE During SMT, the COP True-Up process
is performed after DA RUC and run every two hours
throughout an OD - DA Market will be affected by EIS Market
commitments - Example Resource with Max Run Time of 24 hours
but shows as online for a week due COP True Up - DA Market will decommit the resource
Gay Anthony
5Resource Offer Commitment Parameters
Gay Anthony
6Resource Offer Commitment Parameters
Gay Anthony
7Resource Offer Commitment Parameters
- A Resources physical min run time begins when
the resource is synchronized and is the amount of
time a resource must remain synchronized. (Sync
to Off) - The MPs submitted Min Run Time used by the
Market should be the physical min run time minus
the Sync-to-Min time and Min-to-Off time - SCUC does NOT consider Sync-to-Min and Min-to-Off
when evaluating Min Run Time for commitment
purposes
Gay Anthony
8Resource Offer Commitment Parameters
- A Resources physical max run time begins when
the resource is synchronized but has a limit for
how long it can remain synchronized. (Sync to
Off) - The MPs submitted Max Run Time used by the
market should be the physical max run time minus
the Sync-to-Min time and Min-to-Off time - SCUC does NOT consider Sync-to-Min and Min-to-Off
when evaluating Max Run Time for commitment
purposes
Gay Anthony
9Resource Offer Commitment Parameters
- A resources physical min down time begins when
the resource is de-synchronized and ends when
the resource is physically able to synchronize
again. - The MPs submitted Min Down Time used by the
market should be the physical - min down time of the resource.
(completely offline) - SCUC automatically adds Sync-to-Min and
Min-to-Off time to the value entered for Min
Down Time - This sum represents the effective Min Down
Time, which isevaluated by SCUC for commitment
purposes
Gay Anthony
10Resource Offer Commitment Parameters
Resource A physical min run time 5
hours physical max run time 10 hours physical
min down time 3 hours Sync-to-Min Time 1
hour Min-to-Off Time 15 minutes
Gay Anthony
11Resource Offer Commitment Parameters
Resource A physical min run time 5
hours physical max run time 10 hours physical
min down time 3 hours Sync-to-Min Time 1
hour Min-to-Off Time 15 minutes
Markets UI Resource A (MP-submitted) Min Run
Time - 345 Max Run Time - 845 Min Down Time -
145 Sync-to-Min Time - 100 Min-to-Off Time - 15
Gay Anthony
12Resource Offer Commitment Parameters
- Start-Up Parameters
- In the Start-Up Offer, MPs submit a hot,
intermediate and cold start-up price - In the Resource Offer, MPs submit two
time-related parameters - Hot-to-Cold Time
- Hot-to-Intermediate Time
- These parameters are used to determine which
start-up price is applied
Gay Anthony
13Resource Offer Commitment Parameters
- Hot-to-Cold Time
- A resources physical hot-to-cold Time begins
when the resource is de-synchronized and
represents the amount of time required before the
next synchronization after which a cold start-up
offer will apply. - The MP-submitted Hot-to-Cold Time should be equal
to the sum of the physical hot-to-cold time, the
Sync-To-Min Time and the Min-To-Off Time - No programmatic summing of parameters is
performed in determining start-up times for
applying start-up price
Gay Anthony
14Resource Offer Commitment Parameters
- Hot-to-Intermediate Time
- A resources physical hot-to-intermediate Time
begins when the resource is de-synchronized and
represents the amount of time required before the
next synchronization after which an intermediate
start-up offer will apply. - The MP-submitted Hot-to-Intermediate Time should
be equal to the sum of the physical
Hot-To-Intermediate time, the Sync-To-Min Time
and the Min-To-Off Time - No programmatic summing of parameters is
performed in determining start-up times for
applying start-up price
Gay Anthony
15Resource Offer Commitment Parameters
- Hot-To-Cold Time Example
-
-
- If the Resources De-Commit Time is 1000 AM, the
Cold Start-Up Offer price would apply for
Resource commitments after 800 PM.
Resource A physical hot-to-cold time 8
hours Sync-to-Min Time 1 hour Min-to-Off Time 1
hour
Markets UI Resource A (MP-submitted) Hot-to-Cold
Start-Up Time 10 hours
Gay Anthony
16Resource Offer Commitment Parameters
- Hot-To-Intermediate Time Example
-
- If the Resources De-Commit Time is 1000 AM, the
Intermediate Start-Up Offer price would apply for
Resource commitments between 400 PM and 800 PM.
The Hot Start-Up Offer price would apply for
Resource commitments prior to 400PM.
Resource A physical hot-to-intermediate time 4
hours Sync-to-Min Time 1 hour Min-to-Off Time 1
hour
Markets UI Resource A (MP-submitted) Hot-to-Inte
rmediate Time 6 hours
Gay Anthony
17Resource Offer Commitment Parameters
- Summary
- The MPs submitted Min Run Time should be the
Resources physical min run time minus the
Sync-to-Min time and Min-to-Off time - The MPs submitted Max Run Time should be the
Resources physical max run time minus the
Sync-to-Min time and Min-to-Off time - The MPs submitted Min Down Time should be equal
to the physical min down time. - The MPs submitted time-related start-up
parameters should be equal to the physical
start-up time plus Sync-to-Min and Min-to-Off
Time. - These parameters are used to determine which
Start-Up price to use
Gay Anthony