LNG Project Design Competitions - A contractor - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

LNG Project Design Competitions - A contractor

Description:

LNG Project Design Competitions - A contractor s viewpoint * * * Topics Contractor selection for LNG projects Design competition strategies Key issues for design ... – PowerPoint PPT presentation

Number of Views:135
Avg rating:3.0/5.0
Slides: 19
Provided by: ScottM157
Category:

less

Transcript and Presenter's Notes

Title: LNG Project Design Competitions - A contractor


1
LNG Project Design Competitions - A
contractors viewpoint
2
Topics
  • Contractor selection for LNG projects
  • Design competition strategies
  • Key issues for design competition
  • Scope and structure of design competition
  • Conducting a design competition
  • Recommended guidelines

3
LNG Project Contractor Selection Traditional
Approach
4
LNG Project Contractor Selection Design
Competition
  • Benefits overall project
  • Promotes innovative solutions and competition

Complete Pre-FEED Studies
Contractor X
Contractor A or B
Contractor A and B
9 - 12 months
3- 6 mths
Scoping phase
EPC BID
Evaluation Criteria
Generally Lump Sum
EPC Terms
5
LNG Project Contractor Selection Design
Competition
  • Benefits overall project
  • Promotes innovative solutions and competition

Complete Pre-FEED Studies
Contractor X
Contractor A or B
Contractor A and B
9 - 12 months
3- 6 mths
Scoping phase
EPC BID
Evaluation Criteria
Generally Lump Sum
EPC Terms
6
(No Transcript)
7
Strategies for Design Competition
  • Dependent on several factors
  • Project drivers, goals, ownership structure,
    liquefaction technology, type of facility
    (grassroots/expansion), etc.
  • Two primary approaches
  • Based on owner specifications
  • Owner provides detailed specifications and
    requirements
  • Less freedom for contractor to make technical
    changes
  • Based on fit-for-purpose philosophy
  • Owner specifies overall requirements and guiding
    principles
  • Contactor designs fit-for-purpose plant

8
Choosing Contractor for Design Competition
  • Contractor selection has impact on cost of
    facility
  • Demonstrated experience in developing and
    managing novel technology and execution
    innovations
  • Competition should be among peers
  • Design competition process relatively new and
    evolving
  • Past design competitions generally well managed
  • Lessons learned

9
Issues with Design Competition
  • Scope of design competition
  • What to include and what not to include? That
    is the Question!
  • Structure of design competition
  • The Fairness Factor
  • Methodology of design competition
  • Many things have worked well in past design
    competitions. However, the purpose of this paper
    was to highlight the things that could be
    improved. Hence the examples are a one sided view
    of design competitions.

10
What to include and what not to include?
  • Determination of level at which design
    competition is conducted
  • Scope restriction results in less room to
    innovate
  • Mind reading should to avoided
  • Key issues
  • Confidentiality of information
  • Rely upon items
  • Avoid a liars contest
  • Do not confuse design basis issues versus ideas
  • Protecting competitive advantage
  • Identify what is in best interest of the project

11
Common Elements of Design Scope
  • Minimum safety requirements
  • Site data
  • Feed gas compositions/contaminants
  • Product specifications
  • Definition and requirements for proven equipment
    vs. prototype

12
Common Elements of Design Scope
  • Licensed technologies selected
  • Guarantee philosophy
  • Availability of plant
  • Plant OM philosophy
  • Plant capacity
  • EPC Schedule ? (liars contest)

13
What to include in a design competition?some
examples
  • Execution strategy
  • Plant configuration
  • Compressor and driver configuration
  • Cooling medium selection
  • Equipment specifications
  • Design philosophy sparing, flaring, etc.
  • Plot plan
  • Design optimizations
  • Rotating equipment maintenance cost

14
Structuring a Design Competition
  • Similar to a tendering process
  • Set and implement guidelines
  • Decide on evaluation criteria early
  • Owners team
  • Composition, role, and behavior
  • Set procedures for handling of confidential
    information and intellectual property rights
  • Basis of design versus owner preferences
  • Explicit economic evaluation guidelines
  • Equalize scope and compensation
  • Cross pollination of ideas and impact on
    innovation

15
Recommended Guidelines for Design Competition
  • All designs must be based on a workable LNG
    process technology
  • Guideline applies to not just the technology but
    also the critical equipment and other design
    aspects
  • Whatever definition of workable is, it should
    be applied consistently with all contractors
  • All designs must use the same design basis and
    design philosophy
  • Owner shall define the level at which the design
    competition is implemented
  • Guidelines set at beginning of design competition
    should be closely followed to ensure fairness and
    integrity of competitive process

16
Recommended Guidelines for Design Competition
(continued)
  • Define evaluation criteria and terms of EPC
    contract prior to start of FEED
  • Equal treatment of competing teams in terms of
    scope, compensation, schedule and
    terms/conditions
  • All competing bids should be submitted at the
    same time (Sequential bidding should not be
    considered)
  • Owner should specify certain items, whose claims
    cannot be verified at the time of the award, e.g.
    schedule, etc.
  • All competing teams should be free to chose
    vendors, sub-contractors and partners from an
    approved list

17
What does it take to conduct a design
competition?
  • All parties working towards the benefit of the
    overall project
  • Setting uniform guidelines to ensure fair
    competition

18
Is design competition right for you?
  • Design competitions are effective but may not be
    a good solution for every project
  • The owner has to decide if this strategy is good
    for his specific project
Write a Comment
User Comments (0)
About PowerShow.com