Title: LLRF Control System
1LLRF Control System
- Outline
- Scope
- Requirements
- Design Considerations
- Evaluation
- System drawings
- How this fits into beam-based longitudinal
feedback - Conclusions
2Scope
- This document summarizes the design of the LCLS
LLRF control system design including its
interface with the beam-base longitudinal fast
feedback.
3Scope
- The low level RF controls system consists of RF
phase and amplitude controls at these locations - Laser
- Gun (Klystron 20-6)
- L0-A, a.k.a. L0-1 (Klystron 20-7)
- L0-B, a.k.a. L0-2 (Klystron 20-8)
- L0 Transverse cavity (Klystron 20-5)
- L1-S (Klystron 21-1)
- L1-X (Klystron 21-2)
- L2 - (Klystrons 24-1,24-2,24-3) to control avg
phase/ampl of L2 - L3 Transverse cavity (Klystron 24-8)
- L3 - 2 sectors of klystrons, S29S30
4Requirements (1)
- Meet phase/amp noise levels shown below
- Table 1. RMS tolerance budget for lt12 rms
peak-current jitter (column 3) or lt0.1 rms final
e- energy jitter (column 4). The tighter
tolerance is in BOLD, underlined text and both
criteria, DI/I0 lt 12 and ?DE/E0? lt 0.1, are
satisfied with the tighter tolerance applied.
All tolerances are rms levels and the voltage and
phase tolerances per klystron for L2 and L3 are
?Nk larger, assuming uncorrelated errors, where
Nk is the number of klystrons per linac.
5- ParameterSymbol?I/I0 lt 12??E/E0? lt 0.1Unitme
an L0 rf phase (2 klystrons)?00.100.10S-band
degmean L1 rf phase (1 klystron)?10.100.10S-band
degmean LX rf phase (1 klystron)?x0.50.5X-band
degmean L2 rf phase (28 klystrons)?20.070.07S-band
degmean L3 rf phase (48 klystrons)?30.50.15S-band
degmean L0 rf voltage (1-2 klystrons)DV0/V00.100.
10mean L1 rf voltage (1 klystron)DV1/V10.100.10m
ean LX rf voltage (1 klystron)DVx/Vx0.250.25mean
L2 rf voltage (28 klystrons)DV2/V20.100.10mean
L3 rf voltage (48 klystrons)DV3/V30.50.08BC1
chicaneDB1/B10.010.01BC2 chicaneDB2/B20.050.05Gu
n timing jitter?t00.80.8psecInitial bunch
chargeDQ/Q02.04.0
6Requirements (2)
- Achieve 120 Hz feedback to maintain phase/amp
stability - Adhere to LCLS Controls Group standards RTEMS,
EPICS, Channel Access protocol - Begin RF processing of high-powered structures
May, 2006
7Local feedback loop requirements
- At each of these locations, the klystrons phase
and amplitude will be monitored and controlled - When beam is present, control will be done by
beam-based longitudinal feedback (except for
T-cavs) when beam is absent, control will be
done by local phase and amplitude controller (PAC)
8Design considerations
- Through end of January 2005, various solutions
were evaluated, from 100 COTS modules to hybrids
of in-house designed boards.
9Options considered Jan/05 (2)
10Options considered Jan/05 (3)
11Options considered Jan/05 (4)
12Options considered Jan/05 (5)
13Options considered Jan/05 (6)
14Options considered Jan/05 (7)
15Options considered Jan/05 (8)
16Narrowing down the options May/05
- Later, the options were narrowed down to two an
Off-the-shelf solution and an in-house solution. - This subset of options was presented at the
Lehman Review, May 10-12, 2005. Ref Low Level RF
17Off-the-shelf solution May/05
18In-house solution May/05
19Evaluation
- The Off-the-shelf solution is
- Expensive (25K per instance 10 instances)
- Noisy. ADCs are up to 150 from what they
measure so analog noise levels and ground loop
problems would need to be dealt with - The in-house solution is
- Possibly longer to develop due to board design
and fabrication time.
20Evaluation (2)
- Characteristics of the Off-the-shelf solution
were seen as requiring more effort than those of
the in-house solution - Potential offered by the lower cost of the
in-house solution to replace 250 klystron
controllers in the remainder of the LINAC is
attractive - Hardware people were available as of 22aug2005 to
work on board design if µcontroller was decided - Turned to the EPICS community for ideas and chose
a µcontroller
21Evaluation (3)
- Lower cost alternatives to the 15K VME chassis
and IOC were discussed in the session on hardware
at the EPICS Collaboration Meeting. April 27-29,
2005 - Of the options available, only the Coldfire
uCdimm 5282 processor had the communication speed
and power to meet our data requirements. Cost is
150 per processor plus the development of the
board it sits on
22Evaluation (4)
- By choosing the Coldfire processor, we are able
to make use of the port of the operating system,
RTEMS, which has already been done. - RTEMS is the standard for the real-time operating
system chosen for LCLS by the Controls Group - EPICS, the standard for the control system
software for LCLS runs on RTEMS - With these choices, the LLRF control system will
be fully integrated into the rest of the LCLS
EPICS control system and can speak to other
devices and applications such as control panels,
alarm handlers and data archivers, using Channel
Access protocol, the standard communication
protocol for this project.
23(No Transcript)
24(No Transcript)
25(No Transcript)
26How this fits into global feedback (Gun)
27How this fits into global feedback (L0)
28How this fits into global feedback (L1)
29How this fits into global feedback (L2)
30How this fits into global feedback (L3)
31How this fits into global feedback
32Conclusions
- This solution
- meets the spec for speed and noise
- avoids signal noise problems
- avoids ground loop problems
- meets LCLS control system requirments and
standards running EPICS on RTEMS - provides a low cost path for future upgrade in
the rest of the LINAC when the rest of the
klystron control is replaced
33Conclusions
- At 120 Hz, the LCLS LLRF raw signals must be
processed, the phase and amplitude corrections
must be sent out, applied and achieved - When there is beam, this system will integrate
with the beam-based longitudinal feedback by
accepting the latters RF phase and amplitude
corrections and passing them on.