LLRF Control System - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

LLRF Control System

Description:

... (Klystron 20-6) L0-A, a.k.a. L0-1 (Klystron 20-7) L0-B, a.k.a. L0-2 (Klystron 20-8) L0 Transverse cavity (Klystron 20-5) L1-S (Klystron 21-1) L1-X ... – PowerPoint PPT presentation

Number of Views:112
Avg rating:3.0/5.0
Slides: 34
Provided by: DayleK4
Category:

less

Transcript and Presenter's Notes

Title: LLRF Control System


1
LLRF Control System
  • Outline
  • Scope
  • Requirements
  • Design Considerations
  • Evaluation
  • System drawings
  • How this fits into beam-based longitudinal
    feedback
  • Conclusions

2
Scope
  • This document summarizes the design of the LCLS
    LLRF control system design including its
    interface with the beam-base longitudinal fast
    feedback.

3
Scope
  • The low level RF controls system consists of RF
    phase and amplitude controls at these locations
  • Laser
  • Gun (Klystron 20-6)
  • L0-A, a.k.a. L0-1 (Klystron 20-7)
  • L0-B, a.k.a. L0-2 (Klystron 20-8)
  • L0 Transverse cavity (Klystron 20-5)
  • L1-S (Klystron 21-1)
  • L1-X (Klystron 21-2)
  • L2 - (Klystrons 24-1,24-2,24-3) to control avg
    phase/ampl of L2
  • L3 Transverse cavity (Klystron 24-8)
  • L3 - 2 sectors of klystrons, S29S30

4
Requirements (1)
  • Meet phase/amp noise levels shown below
  • Table 1. RMS tolerance budget for lt12 rms
    peak-current jitter (column 3) or lt0.1 rms final
    e- energy jitter (column 4). The tighter
    tolerance is in BOLD, underlined text and both
    criteria, DI/I0 lt 12 and ?DE/E0? lt 0.1, are
    satisfied with the tighter tolerance applied.
    All tolerances are rms levels and the voltage and
    phase tolerances per klystron for L2 and L3 are
    ?Nk larger, assuming uncorrelated errors, where
    Nk is the number of klystrons per linac.

5
  • ParameterSymbol?I/I0 lt 12??E/E0? lt 0.1Unitme
    an L0 rf phase (2 klystrons)?00.100.10S-band
    degmean L1 rf phase (1 klystron)?10.100.10S-band
    degmean LX rf phase (1 klystron)?x0.50.5X-band
    degmean L2 rf phase (28 klystrons)?20.070.07S-band
    degmean L3 rf phase (48 klystrons)?30.50.15S-band
    degmean L0 rf voltage (1-2 klystrons)DV0/V00.100.
    10mean L1 rf voltage (1 klystron)DV1/V10.100.10m
    ean LX rf voltage (1 klystron)DVx/Vx0.250.25mean
    L2 rf voltage (28 klystrons)DV2/V20.100.10mean
    L3 rf voltage (48 klystrons)DV3/V30.50.08BC1
    chicaneDB1/B10.010.01BC2 chicaneDB2/B20.050.05Gu
    n timing jitter?t00.80.8psecInitial bunch
    chargeDQ/Q02.04.0

6
Requirements (2)
  • Achieve 120 Hz feedback to maintain phase/amp
    stability
  • Adhere to LCLS Controls Group standards RTEMS,
    EPICS, Channel Access protocol
  • Begin RF processing of high-powered structures
    May, 2006

7
Local feedback loop requirements
  • At each of these locations, the klystrons phase
    and amplitude will be monitored and controlled
  • When beam is present, control will be done by
    beam-based longitudinal feedback (except for
    T-cavs) when beam is absent, control will be
    done by local phase and amplitude controller (PAC)

8
Design considerations
  • Through end of January 2005, various solutions
    were evaluated, from 100 COTS modules to hybrids
    of in-house designed boards.

9
Options considered Jan/05 (2)
10
Options considered Jan/05 (3)
11
Options considered Jan/05 (4)
12
Options considered Jan/05 (5)
13
Options considered Jan/05 (6)
14
Options considered Jan/05 (7)
15
Options considered Jan/05 (8)
16
Narrowing down the options May/05
  • Later, the options were narrowed down to two an
    Off-the-shelf solution and an in-house solution.
  • This subset of options was presented at the
    Lehman Review, May 10-12, 2005. Ref Low Level RF

17
Off-the-shelf solution May/05
18
In-house solution May/05
19
Evaluation
  • The Off-the-shelf solution is
  • Expensive (25K per instance 10 instances)
  • Noisy. ADCs are up to 150 from what they
    measure so analog noise levels and ground loop
    problems would need to be dealt with
  • The in-house solution is
  • Possibly longer to develop due to board design
    and fabrication time.

20
Evaluation (2)
  • Characteristics of the Off-the-shelf solution
    were seen as requiring more effort than those of
    the in-house solution
  • Potential offered by the lower cost of the
    in-house solution to replace 250 klystron
    controllers in the remainder of the LINAC is
    attractive
  • Hardware people were available as of 22aug2005 to
    work on board design if µcontroller was decided
  • Turned to the EPICS community for ideas and chose
    a µcontroller

21
Evaluation (3)
  • Lower cost alternatives to the 15K VME chassis
    and IOC were discussed in the session on hardware
    at the EPICS Collaboration Meeting. April 27-29,
    2005
  • Of the options available, only the Coldfire
    uCdimm 5282 processor had the communication speed
    and power to meet our data requirements. Cost is
    150 per processor plus the development of the
    board it sits on

22
Evaluation (4)
  • By choosing the Coldfire processor, we are able
    to make use of the port of the operating system,
    RTEMS, which has already been done.
  • RTEMS is the standard for the real-time operating
    system chosen for LCLS by the Controls Group
  • EPICS, the standard for the control system
    software for LCLS runs on RTEMS
  • With these choices, the LLRF control system will
    be fully integrated into the rest of the LCLS
    EPICS control system and can speak to other
    devices and applications such as control panels,
    alarm handlers and data archivers, using Channel
    Access protocol, the standard communication
    protocol for this project.

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
How this fits into global feedback (Gun)
27
How this fits into global feedback (L0)
28
How this fits into global feedback (L1)
29
How this fits into global feedback (L2)
30
How this fits into global feedback (L3)
31
How this fits into global feedback
32
Conclusions
  • This solution
  • meets the spec for speed and noise
  • avoids signal noise problems
  • avoids ground loop problems
  • meets LCLS control system requirments and
    standards running EPICS on RTEMS
  • provides a low cost path for future upgrade in
    the rest of the LINAC when the rest of the
    klystron control is replaced

33
Conclusions
  • At 120 Hz, the LCLS LLRF raw signals must be
    processed, the phase and amplitude corrections
    must be sent out, applied and achieved
  • When there is beam, this system will integrate
    with the beam-based longitudinal feedback by
    accepting the latters RF phase and amplitude
    corrections and passing them on.
Write a Comment
User Comments (0)
About PowerShow.com