Title: IT Projects with CAO/FOIS
1IT Projects with CAO/FOIS
A Status Report
2Projects in Progress
- FOIS RMS and TMS
- VSAT
- Crew Management System (CMS)
- Integrated Coaching management System (ICMS)
- Control Office Application (COA)
- Radio Frequency Identification (RFID)
- Web Enabled Claims Office Application
- Integration of in-motion electronic weighbridges
- Network Upgardation
- Electronic Payment Gateway (IREPG)
3Estimate and Budget
Allotment of Funds For various Projects in the
Year 2006-07
Expenditure on FOIS project has been Rs.
367.04 Cr upto June 06
COIS estimate was enhanced to Rs 17.32 Cr
(sanctioned by Rly Bd on 12.05.06)
4FOIS RMS Module
- Successfully implemented on 233 locations on IR,
comprising Railway Board, Zonal and Divisional
HQs, Area Controls and major yards - More than 1100 PCs networked for this phase
- Daily and periodic reports being generated for
Railway Board, Divisions and station level
(around 2000 reports)
5FOIS RMS Locations
6FOIS TMS Module
- 537 locations on IR
- 214 locations on VSAT
- 324 locations online
- 126 printing RR online
- Around 1100 PCs and 400 printers supplied so far
- 668 PCs and 612 printers under supply
7FOIS TMS MODULE
8TMS VSAT locations
- 214 TMS locations have to be commissioned on
VSATs by IRPMU - Railway Boards target was June 2006. IRPMUs
revised target is Sept 2006 - 53 VSATs have been installed upto 30.06.06
- 37 of these were commissioned upto June 2006
- The target for July 2006 is for commissioning 64
locations on VSAT - Target for 118 (6453) locations is 15th Aug 2006
- 16 locations have been commissioned upto 18.07.06
- Equipment has been installed at 11 locations
- Work is in progress at 10 other locations
9Additional requirement of VSAT based connectivity
10Crew Management System (CMS)
- Detailed estimate of Rs 38.16 crores sanction by
Railway Board. - 302 lobbies to be covered, out of which 261 are
integrated lobbies. - Target for completion 7.3.2007
11CMS - Locations
Details
12CMS Locations details -
13CMS Individual Location details -
14CMS - Progress
- Application under development and testing for
- Freight module
- Coaching, shunting and pilot module
- Suburban module
- Site Preparation
- Lump sum sanctioned _at_ Rs 1,31,000 for major and
Rs 81,000 for minor lobbies - Target for readiness Aug 2006
- Terminal Equipment
- Under vetting
- Target of supply - Oct 2006
- Datacom Equipment
- Under vetting. Will be procured through CRIS
- Training
- Core group and core implementers will be trained
at CRIS - Core group identified on all 16 zonal railways
- Training labs being set up at 5 locations
15Integrated Coaching Management System
(ICMS)
- Enhanced scope
- Punctuality Module
- Implemented on IR. Migrated module will be given
for testing by the end of July 2006 - Coaching Stock Management Module
- Being implemented in three phases
- Software ready and under field trials at
Nizamuddin - Ready for roll out
- Coaching Stock Maintenance Module
- Maintenance modules scope received from Railway
Board in July 2006. - Target for implementation is 31.3.07
- Timetabling Module
- Time table simulation modules system
requirements under discussion
16ICMS Coaching Stock Management Module
- Phase I 114 terminals at 41 locations
- Target for implementation 31st Aug
2006 - Phase II - 78 terminals at 34 locations
- Target for implementation 31st Oct
2006 - Phase III - 128 terminals at58 locations
- Target for implementation 31st Dec
2006 - Training
- 186 staff from 136 locations trained so far
- Training labs being set up to take care of
additional training needs - Equipment
- Thin clients and printers supplied to all
locations - Datacom equipment- 57 LAN extenders supplied.
Rest under supply - UPSs to be procured by zonal railways
implementation held up for want of UPSs - 14 locations commissioned NR-1, WR-9, SECR-3
SR-1
17ICMS Coaching Stock Management Module
18Control Office Application (COA)
- Pilot project under trial at Madurai and
Trivandrum divisions of SR - Functionalities tested response time issues
application being tuned - Tender for customization for IR being being
awarded (76 divisional/area controls and zonal
HQs) - Strategy for roll out In three phases
- Phase I SR, SCR, SWR, CR, ECOR, SECR
- Phase II WR, WCR, NCR, NR, NWR
- Phase III SER, ER, ECR, NER. NFR
19Radio-frequency ID (RFID)
- Board has sanctioned a Pilot project on ECOR at
the cost of Rs 1.92 Cr. - Approach paper invited by CRIS from System
Integrators - Requirement to have seamless integration with
existing FOIS application - A technology group constituted in CRIS for
in-depth review of technological options and
their suitability in Indian conditions -
20Web-enabled Claims Office Application
- Phase I
- All modules of Claims, Court, Accident, NR cell.
- Completed. Data entry being done by the Railways
since 1.04.05 - Phase II
- Computerization of Subsidiary Claims Office
- Software development completed.
- Varanasi subsidiary claims office computerized.
- 15 offices on other railways awaiting hardware
and network infrastructure. - Tender under evaluation in CRIS
- Refund Goods Application
- Software developed and deployed on all 16 zonal
railways - Railway Claims Tribunal
- Software under development
- Training
- Staff of 15 subsidiary Offices (_at_ 2 each) have
been imparted framing of Web-enabled claims
application software at CRIS. - Staff of Refund Goods offices of 16 Zonal
Railways (_at_ 5 each) have also imparted training
on Refund Goods office application software. - Target - Oct 2006
21IR Electronic Payment Gateway
- Sanctioned as a separate work for Rs. 2.5 Cr in
2004-05 - Now being implemented along with TMS
- Working for coal coming from 14 locations on ECR
to Badarpur Thermal Power House (BTPP) - Payment of 90 of freight on coal to BTPP is now
through e-payment - Board reviewing extending to other major
customers like FCI - Issues regarding to-pay transactions raised by
FACAO
22Integration of in-motion electronic weighbridges
- Objective to capture 100 weighment details of
all consignments booked through TMS - Connectivity being planned between the
weighbridge and TMS locations - Interface through exchange of data by means of
flat files demonstrated to weighbridge companies
by CRIS - One location each on Nagpur division and
Secunderabad division identified to do test runs - Feedback awaited
23Training All Applications
- Five training labs to be set up for all IT
training needs
24Datacom Equipment
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29Organizational setup
- Estimates of FOIS, ICMS, CMS, COA
Web-enabled Claims Central setup - Gazetted
30Organizational setup
- Estimates of FOIS, ICMS, CMS, COA
Web-enabled Claims Central setup (non-gazetted)
31Organizational Setup
Estimates of FOIS, ICMS, CMS, COA Web-enabled
Claims Zonal setup
32Growth of IT projects in IR
- IRs capital budget for IT is Rs. 273 crore in
2006-07 - It is projected to increase to about Rs. 900
crore to Rs. 1200 crore by 2010 2011 - To make this scale of operation possible,
requirement of space and other facilities for
CRIS and FOIS organization needs to be
significantly increased
33Increase in strength of FOIS and space requirement
Year Approx IT budget (Rs. Crore) Approx IT budget (Rs. Crore) FOIS manpower (total) Manpower based in HQ Bare seating space (sq m) Support space Training areas, central control room etc. Total space requirement (sq m)
2006-07 2006-07 300 264 140 420 420 210 1050
2007-08 2007-08 360 317 160 480 480 240 1200
2008-09 2008-09 450 396 200 600 600 300 1500
2009-10 2009-10 540 475 240 720 720 360 1800
2010-11 2010-11 650 572 290 870 870 435 2175
2011-12 2011-12 800 704 360 1080 1080 540 2700
34(No Transcript)
35 CRIS location
36 CRIS premises
37Required facilities for expansion
Secure areas in red
Restricted areas in orange
Open access in green
38THANK YOU