Title: City of uMhlathuze Strategic Budget Planning Tool


1
City of uMhlathuzeStrategic Budget Planning Tool
Project Background Presentation
  • November 2004

2
Presentation Contents
  • Introduction
  • Dirk Pretorius City of uMhlathuze
  • Project Background
  • Dirk Pretorius City of uMhlathuze
  • Implementation Process
  • Craig Perritt Intermap
  • Project Milestones and Budget
  • Craig Perritt Intermap
  • Beta Software Demonstration
  • Craig Perritt Intermap
  • Ongoing Developments
  • Craig Perritt Intermap, Joy Ndwandwe - ASALGP
  • Questions Answers
  • All

3
Introduction City of uMhlathuze
  • Councils mission is to develop uMhlathuze as
    the industrial, commercial and administrative
    centre within the natural beauty of the region,
    providing a range of efficient municipal services
    thereby ensuring economic development, dynamic
    growth and the improvement of the quality of life
    for all
  • City of uMhlathuze situated on north-east coast
    of KwaZulu-Natal
  • Consist of amalgamation of Empangeni, Richards
    Bay, Esikhawini, Ngwelezane, Nseleni, Vulindlela
    and Felixton as well as the rural areas under
    Amakhosi Dube, Khoza, Mkhwanazi, Mbuyazi and Zungu

4
Introduction City of uMhlathuze (cont)
  • Considered the economic powerhouse of Zululand,
    comprising of a population of close to 300,000
    and a total municipal land area of 796 km2
  • Demarcation code KZ282 included with six other
    local municipalities to represent the DC28 area
    (uThungulu region)

5
Introduction IDP Review Process
  • In accordance with section 34 of the Municipal
    Systems Act
  • Budget and IDP alignment
  • Public participation process through community
    and ward information meetings October 2004
  • IDP Forum meetings Oct/Nov 2004
  • Various task team meetings November 2004
  • Draft IDP to Exco/Council
  • Provincial multi-sector IDP forum
  • Community consultation process
  • Approval of final IDP/Budget to Exco and Council

6
Introduction Budgeting Process
  • 2005/2006 Budget timetable submitted to Council
    August 2004
  • Issuing of 2005/2006 multi-year budget guidelines
    September 2004
  • Submission of 2005/2006 multi-year draft Capital
    projects November 2004
  • Submission of 2005/2006 multi-year draft
    Operating estimates December 2004
  • Draft 2005/2006 multi-year budget and IDP
    submitted to Exco/Council and PG/NT March 2005

7
Introduction Budgeting Process (cont)
  • Community consultation process April 2005
  • Tabling of revised 2005/2006 multi-year budget
    and IDP, incorporating inputs from
    community/PG/NT to Council for approval - May
    2005
  • 2005/2006 multi-year budget and IDP submitted to
    PG/NT and publication of thereof
  • Establish and complete performance evaluations on
    functional outcomes identified in IDP/operational
    plans

8
Introduction Strategic Planning
  • Formalisation of Councils objectives and
    strategies
  • Prioritising of strategies for developing
    2005/2006 multi-year budget
  • Alignment of the draft capital and operating
    estimates with the reviewed IDP
  • Submission of draft 2005/2006 multi-year budget
    in STRATEGIC format (Capex and Opex linked to
    Councils strategic objectives) to Finance
    committee/Exco/Council

9
Project Status
  • Need was identified to develop a user-friendly
    system
  • Outcomes Based Budgeting Tool (OBBT)
  • OBBT will be utilised during the discussions and
    finalisation of the 2005/2006 multi-year budget
  • Demonstration of the system to follow

10
Beta Demonstration
  • System demonstration
  • Live demo or screenshots depends on internet
    connectivity available

11
Ongoing Developments
  • Enhancements to the Planning Model with ASALGP
    funding
  • Integration / Communication with Municipal
    Financial System (ProMIS)
  • Presentation of Actual Expenditure against Budget
  • Ongoing monitoring tool as well as the planning
    tool it now is
  • Strategic level approach (IDP Strategy level and
    not lowest level approach)
  • Enhancement Project
  • Anticipated programme completion in January 2005

12
Questions Answers