Title: Oberlin City School Facilities


1
Oberlin City School Facilities
  • Major Facility Maintenance Projects

2
Oberlin High School
  • Built in 1960
  • Classroom addition in 1964
  • Classroom and Auditorium addition in 1988
  • 86,150 sq.ft.

3
High School HVAC
  • Four gas fired hot water boilers, 1964, 1987 (2),
    2005.
  • 1964 unit is out of service
  • Cost for replacement, 640,000.
  • Cost of entire heating system replacement
    2,030,800

4
High School Systems
  • Roofs All roofs are over 14 years old, except
    for choir room area. Expected replacement cost
    490,200
  • Electrical Transformer Replacement 15,000
  • Lighting Upgrade classroom lighting, 338,480
  • Masonry 124,050

5
High School Door/Windows
  • Replacement of all window units 500,500
  • Replacement of all exterior doors 62,500

6
High School Hazardous Material
  • Removal of all hazardous building materials
    281,600

7
Oberlin High School
  • Boilers 510,000 to 2,030,800
  • Roofs 490,200
  • Electrical 15,000
  • Lighting 338,480
  • Windows and Doors 563,000
  • Hazardous material 281,600
  • Masonry 124,050
  • Total 2,322,250 to 3,843,050

8
Langston Middle School
  • Built in 1923
  • Addition in 1945
  • Renovation and addition in 1982
  • 84,240 sq. ft.

9
Langston HVAC
  • Two gas fired hot water boilers, 1958
  • Cost of boiler replacement 340,000
  • Cost of entire heating system replacement
    2,021,760

10
Langston Systems
  • Roof Single ply roof system installed in 1996,
    out of warranty in 2011. Cost to replace
    254,700
  • Electrical transformer replacement 15,000
  • Lighting 336,960
  • Doors 44,000

11
Langston Foundation and Masonry
  • Foundation sealing 10,000
  • Masonry repairs 109,175

12
Langston Hazardous Material
  • Removal of all hazardous building material
    130,672

13
Langston Middle School
  • Boilers 340,000 to 2,021,760
  • Roofs 254,700
  • Electrical 15,000
  • Lighting 336,960
  • Doors 44,000
  • Masonry 119,175
  • Hazardous material 130,672
  • Total 1,240,570 to 2,922,267

14
Prospect Elementary School
  • Built in 1960
  • Classroom addition in 1970
  • Classroom addition in 1980
  • 45,290 sq.ft.

15
Prospect HVAC
  • Two gas fired steam boilers and three hot water
    boilers.
  • Cost of boiler replacement 510,00
  • Cost of heating system replacement 1,086,960

16
Prospect Systems
  • Roof Many different roof surfaces, shingles and
    Garland section under warranty. Cost for
    replacement 221,200
  • Electrical transformer replacement 15,000
  • Lighting 181,160
  • Doors/windows 303,300

17
Langston Foundation and Masonry
  • Foundation sealing 10,000
  • Masonry repairs 100,500

18
Prospect Hazardous Material
  • Removal of all hazardous building material
    102,200

19
Prospect School
  • Boilers 510,000 to 1,086,960
  • Roofs 221,200
  • Electrical 15,000
  • Lighting 181,160
  • Doors/windows 303,300
  • Masonry 110,500
  • Hazardous material 102,200
  • Total 1,443,360 to 2,020,320

20
Eastwood Elementary School
  • Built in 1955
  • Addition in 1960
  • Addition in 1960
  • 38,660 sq.ft.

21
Eastwood HVAC
  • Two gas fired hot water boilers, 1995
  • Expected replacement in 2015 340,000.
  • Total cost of heating system replacement
    927,840.

22
Eastwood Systems
  • Roof Built up roof system, much over 15 yrs.
    old. Preschool wing 2006. Total roof replacement
    198,425
  • Electrical transformer replacement 15,000
  • Doors/windows 355,250
  • Masonry repairs 54,275

23
Eastwood Hazardous Material
  • Removal of all hazardous building material
    113,700

24
Eastwood Elementary School
  • Boilers 340,000 to 927,840
  • Roofs 198,425
  • Electrical 15,000
  • Doors/windows 355,250
  • Masonry 54,275
  • Hazardous material 113,700
  • Total 1,076,650 to 1,723,915

25
Oberlin City School District Totals
  • High School 2,322,250 to 3,843,050
  • Langston 1,240,570 to 2,922,267
  • Prospect 1,443,360 to 2,020,320
  • Eastwood 1,076,650 to 1,723,915
  • District 6,082,830 to 10,509,552