Retro-Commissioning - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Retro-Commissioning

Description:

Retro-Commissioning An SNL Experience Chris Evans, CEM Miguel Atencio Sandia Energy Management Program A Lessons Learned Activity Sandia is a multiprogram laboratory ... – PowerPoint PPT presentation

Number of Views:201
Avg rating:3.0/5.0
Slides: 24
Provided by: efcogOrg7
Category:

less

Transcript and Presenter's Notes

Title: Retro-Commissioning


1
Retro-Commissioning
An SNL Experience Chris Evans, CEM Miguel
Atencio Sandia Energy Management Program A
Lessons Learned Activity
Sandia is a multiprogram laboratory operated by
Sandia Corporation, a Lockheed Martin
Company,for the United States Department of
Energys National Nuclear Security
Administration under contract DE-AC04-94AL85000.
2
Retro-Commissioning at SNLIntroduction
  • The Sandia Energy Management Team has developed a
    program to Retro-commission buildings at the
    laboratory. To date two buildings have been
    partially completed. The following presentation
    will explain the process and lessons we have
    learned.

3
What is Retro?
  • Retro-commissioning is a process to identify and
    resolve operating problems, improve comfort and
    optimize energy use in existing buildings to meet
    current building requirements. Typically the
    focus is on HVAC systems, controls and lighting.
    Most fixes tend to be low cost in nature.

4
Why even do retro?
  • Space complaints (temp, IAQ, etc)
  • Rooms changed from original design intent
  • System modifications
  • Building not operating efficiently
  • Energy costs ()
  • Changes in building mission
  • Building was not commissioned during construction
  • More than 5 years have passed since the last
    retro-commissioning

5
Benefits of Retro
  • Excellent ROI/ Payback (lt1 year typical)
  • Excellent energy savings (5 to 15 typical)
  • Cost of lost productivity/ comfort is much higher!

6
Top 10 Retro Measures
  • 10.) Improve Boiler Efficiency, Controls
  • 9.) Reset supply static pressure set point
  • 8.) Review terminal unit operation
  • Reheat is a major energy consumer and problem at
    Sandia
  • 7.) Return VFDs to variable speed operation
  • 6.) Lower condenser water temperature
  • 5.) Improve chiller sequencing
  • 4.) System level test and balance
  • 3.) Optimize economizer
  • 2.) Eliminate simultaneous heating and cooling
  • 1.) Turn off equipment when not needed!!

7
Retro Process
  • 1.) Planning Phase
  • 2.) Investigation Phase
  • 3.) Implementation Phase
  • 4.) Operating Phase

8
Planning Phase
  • Identify key players
  • Building Owner/ Manager, Building Systems
    Engineer, Building Operators/ Mechanics,
    Building, Environmental Safety Health (ESH),
    buildings controls representative
  • The team members are necessary to make the
    process a success. Everyone needs to be
    continuously informed and in agreement or the
    project will fail.
  • For laboratory facilities industrial hygiene
    representatives

9
Planning Phase
  • Kick off meeting
  • The kickoff meeting is important so everyone
    understands the goals, why we are
    retro-commissioning, what systems will be looked
    at and what systems are off limits. The kickoff
    meeting is where all members agree that
    retro-commissioning is the right process to
    proceed with.

10
Planning Phase
  • Benchmark past performance
  • Past performance data is necessary to track
    improvements made during the retro-commissioning
    process. Data is often not available. For this
    reason, it is important to see what data is
    available as early as possible. It may be
    necessary to install portable meters to collect
    baseline data. Typical baseline data would
    include building electrical usage, natural gas
    use, average outputs of VFD drives on large fans
    and pumps, average airflow readings on air
    handlers and exhaust fans and run time profiles
    of air handlers, chillers and boilers.

11
Planning Phase
  • Discuss building operational issues
  • Discuss operational issues with occupants and the
    key team members. This can provide some insight
    into whether components such outside air dampers,
    air washers or sensors are actually operating
    correctly.
  • Identify problem areas
  • Information from the previous planning steps can
    lead to identifying problem areas.
  • Develop Retro plan
  • Develop an initial plan identifying systems to
    investigate.

12
Investigation Phase
  • Determine how the system is supposed to
    operate?
  • Look for design documents from the original
    construction. The building may have never
    operated according to the original design.
  • The building management team, ESH coordinator
    and the building mechanic determine how the
    systems are supposed to operate. Determine
    operating schedule requirements, air flow
    requirements, special temperature requirements
    and lighting requirements.

13
Investigation Phase
  • How is the system actually operating?
  • Fully automated control systems dont necessarily
    mean better control
  • Decisions are often made without ever stepping
    foot into the building space
  • The screen says the space temp is fine, why are
    they complaining?
  • The reheat valve is 100 open, why are they
    still cold?
  • The damper is 100 open, why are they still
    hot?
  • They must be low on CFM, let me increase the
    static pressure set point
  • The occupancy schedule shows that the fans shut
    off at 600 pm, why is the building base load so
    high?
  • Do not trust everything the control system tells
    you
  • There is no substitute for a good old fashioned
    field verification
  • The results may surprise you!

14
Investigation Phase
  • Without performing a site visit, how certain are
    you?
  • Is the valve actually closed?
  • Is the damper actually open?
  • Is the space temp being skewed by a false
    thermostat load?
  • Is the room facing north with lots of window
    area?
  • Are there obstructions near the room diffuser
    preventing proper air circulation?
  • Are the fans really shutting off at 600 pm?
  • Decisions made without proper verification result
    in systems that eventually run out of control
  • Unwarranted set point changes
  • Points placed in operator mode
  • Control slowly shifts from automatic DDC control
    to manual operation
  • System performance suffers resulting in increased
    occupant discomfort and increased whole building
    energy consumption
  • This snowball effect can be avoided!

15
Investigation Phase
  • DDC control is only as good as the information it
    has available (garbage in garbage out). Typical
    DDC sensor issues that should be investigated
    include
  • What inputs are used for control?
  • Have these inputs been measured/ calibrated/
    maintained?
  • What is the life expectancy of these inputs
    (sensors)?
  • Are they on a PM or replacement schedule?
  • What happens to system performance when they
    begin to lose accuracy (drift)?
  • What happens to system performance when they
    fail?
  • Prioritize those that are more critical

16
Investigation Phase
  • Control Strategy
  • Many times, it pays to follow the keep it simple
    principle
  • The more complicated the strategy
  • The less likely operational staff will understand
    it
  • The more likely the code will be by-passed and
    operated manually (operator pts)
  • The more inputs are required (More possibilities
    for failure)
  • The harder it is to update when changes are made
    to the system

17
Investigation Phase
  • Document all findings in a Retro-Investigative
    report
  • As found conditions.
  • Results of initial evaluation
  • Make a list of recommended opportunities and
    deficiencies.
  • Implementation costs and estimated savings or
    savings to investment ratio (SIR).

18
Implementation Phase
  • Implement recommended opportunities and correct
    any operational deficiencies
  • Verify that changes/ modifications are working
    correctly
  • Monitor building performance to verify energy
    savings

19
Operating Phase
  • Operational staff MUST be trained in order to
    sustain efficient operation.
  • Document/ update the new sequence of operations
  • Track monthly building energy use
  • Compare historical energy data (similar months,
    different years)
  • Compare energy usage vs. outside air temperature
    (OAT)
  • If possible, sub-meter major HVAC systems
  • Verify correct operation of all energy
    conservation control strategies
  • Track equipment schedules
  • Track systems to see if set points are being met
  • Track DDC control operations

20
SNL Retro Challenges
  • Building owners are focused on meeting
    mission/programmatic needs
  • Outside of the fence, building owners are focused
    on lowering utility bills/ over head
  • Space chargeback is not necessarily set up to
    charge users for direct energy usage
  • Everyone believes that energy is free
  • These projects are great...As long as they are
    done in someone else's building
  • Please dont touch my system, you might break it

21
Things to Consider
  • Do not assume a building with very few too hot/
    too cold calls is operating efficiently
  • Many occupants simply adapt and no longer
    complain
  • Many complaints are not submitted through proper
    channels and are never documented
  • Occupants are very creative and find ways of
    making their space temperatures acceptable
  • Space heaters
  • Taped up diffusers
  • Removing diffusers completely
  • Fans
  • Cardboard box air deflectors
  • Heat source next to thermostat
  • Cold source next to thermostat

22
Things to Consider
  • Many space temperature problems are unknowingly
    caused by occupants

23
Things to Consider
Write a Comment
User Comments (0)
About PowerShow.com