Title: New Bangkok International Airport
1New Bangkok International Airport
Progress Information Schedule Analysis
FOR Air traffic Control Tower
2003. 6. 18
KOICA(NESDB)
2INFORMATION OF NBIAS CONTROL TOWER NAVAIDS
? IMPLEMENTING AGENCY Aeronautical Radio of
Thailand Ltd. ( other government agencies) ?
INVESTMENT BUDGET 2,307 Million Baht ? SCOPE
OF WORK ( including Design, Manufacture,
Installation, Test Commissioning Duration )
1. Construction of ATC Complex 2003. 4
2005. 2 2. Provision of surveillance system
2003. 6 2005. 6 3. Provision of
navigation aids 2003.12 2005. 6 4.
Provision of aeronautical radio system 5.
Provision of communications network 2003. 5
2005.5 6. Provision of flight data
7. Provision of airline services equipment
8. Air traffic operation and communications
? PROGRESS STATUS Under bidding process
as of Jun.
2003
3ATCT
LLZ/DME
Air Navigation System of IIA
GP
TVOR/DME
ASR/MSSR
TDWR
TRACON
LLWAS
4In case of NBIA Implementation by Aeronautical
Radio of Thailand Ltd. Design Construction
Test Jun.2003Jun.2005
In case of NBIA Implementation by Department of
Meteorology Design Construction Test
Jan.2003Jun.2005
5Control Tower of IIA
1997.07 1999.10( 28 MONTHS)
1999.11 2000.06( 8 MONTHS)
H 100.4 M
- Structural Stability for Strong Earthquake
install. Of HMD
- Perfect Stormproof Test for Violent Breeze at
60m/s
6Incheon International Airport Control Tower
Outcome
Opening Date
42 MONTHS
100
AIRPORT OPERATION READINESS 6 MONTHS
Progress
EQUIP INSTALL. TEST 8 MONTHS
CONSTRUCTION 28 MONTHS
DESIGN BIDDING 16 MONTHS
0
Duration
7Incheon International Airport Control Tower
Outcome
8Incheon International Airport Control Tower
Outcome
9Incheon International Airport Control Tower
Outcome
10Incheon International Airport Control Tower
Outcome
Opening Date
42 MONTHS
100
AIRPORT OPERATION READINESS 6 MONTHS
Progress
EQUIP INSTALL. TEST 8 MONTHS
CONSTRUCTION 28 MONTHS
DESIGN BIDDING 16 MONTHS
0
Duration
11COMPARISON BETWEEN NBIA AND OTHERS
AIR TRAFFIC CONTROL (ATC) TOWER
12AIR TRAFFIC CONTROL TOWER SCHEDULE COMPARISION
BETWEEN NBIA AND IIA
100
NBIA OPEN AIRPORT 29 SEP. 2005
90
AIRPORT OPERATION READINESS
3 MONTHS
80
70
6 MONTHS
(NOV. 02 SEP 05)
60
EQP. INSTALL. TEST
50
20 MONTHS
40
26 MONTHS
30
DESIGN CONSTR.
20
6 MONTHS
10
TENDER AWARD
0
1997 1998 1999 2000 2001
2002 2003 2004 2005
100
6 MONTHS
90
IIA OPEN AIRPORT 29 MAR. 2001
AIRPORT OPERATION READINESS
80
70
8 MONTHS
60
EQP. INSTALL. TEST
50
28 MONTHS
40
30
36 MONTHS
CONSTRUCTION
20
16 MONTHS
10
0
DESIGN AWARD
1992 1993 1994 1995 1996
1997 1998 1999 2000
13THE ROLE OF CONTROL TOWER
? The control tower as the most important
facility for air control is equipped with
communication intelligence systems. ? All
sorts of facilities such as control facilities
play the most significant role for the safety of
aircraft and passengers ? Without ATCT
functions, we cant do start up and commissioning
the whole NBIA integrated system as airport
operational readiness ? ATCT progress delay
impacts directly opening date of NBIA