Title: AM-LINERII
1AM-LINERII
INSTALLATION PROCEDURE
2Introduction
- This presentation is intended to give an
overview of the procedures and techniques used to
install the AM-LINERII PVC pipeline
rehabilitation system.
3SEQUENCE OF EVENTS
- Pre-Installation closed circuit television
inspection - Pre-installation pipeline preparation
- Installation technique
- Post-installation closed circuit television
inspection - Reinstatement of service connections
4PRE-INSTALLATION CLOSED CIRCUIT TELEVISION
INSPECTION
- Identify any conditions in the pipeline that
could impede or prevent the proper installation
of the liner - Provide a record of the pre-lined condition of
the pipe - Accurately record the position of all service
connections
5PRE-INSTALLATION CLOSED CIRCUIT TELEVISION
INSPECTION
- A highly trained operator uses a remotely
controlled CCTV camera to assess the condition of
the pipeline. - As the camera passes through the pipeline, images
from the camera are monitored by the operator and
recorded either in DVD or VHS format. - The operator makes a record of the position of
all service connections and defects in the
pipeline.
6PIPELINE PREPARATION
- Typical pipeline conditions that must be
remediated prior to lining - Roots
- Large quantities of groundwater infiltration
- Collapsed pipe
- Dropped Joints or offsets of more than 12.5 of
the inside pipe diameter - Protruding taps
7PIPELINE PREPARATION
ROOTS
- Roots must be removed from the pipeline prior
to installing the liner. Roots may be removed by
using a chemical root treatment or by mechanical
means such as chain flails.
8PIPELINE PREPARATION
INFILTRATION
- Large quantities of cold ground water
flowing into the pipeline, can act as a heat sink
and prevent the PVC liner material from reaching
the temperature needed to form properly. - Infiltration may be eliminated either by
chemical grouting or installing a patch prior to
lining.
9PIPELINE PREPARATION
- Collapsed pipe, dropped or offset joints that
reduce the inside circumference of the pipeline
to less than the outside circumference of the
pipe liner will not allow the liner to form
properly. This condition is usually presented as
a longitudinal rib after the liner is installed. - To avoid ribs in the liner, sections of
pipeline containing collapsed pipe, dropped or
offset joints should be point repaired prior to
lining.
COLLAPSED PIPE
10PIPELINE PREPARATION
PROTRUDING TAPS
- Service taps that protrude into the pipeline
more than 12.5 or 1-inch should be cut off using
a chain flail or remotely controlled grinder.
11PIPELINE PREPARATION
CLEANING
- Prior to insertion of the liner, the pipeline
is cleaned using a high pressure water jet to
remove any debris in the pipeline.
12LINER INSTALLATION
- Heating the coil of liner
- Attaching the liner to the pulling cable
- Insertion of the liner into the host pipe
- Stress Relief
- Processing the liner
13LINER INSTALLATION
The coil of AM-LINERII is brought to the jobsite
and loaded into an enclosed trailer to be heated.
14LINER INSTALLATION
Preparing Pulling Nose
The pulling nose is made by folding the flat
liner in half longitudinally, drilling holes
perpendicularly through the folded liner, then
weaving a cable or chain through the holes. The
entire section is then wrapped with duct tape.
The end of the liner is heated to make it pliable.
15LINER INSTALLATION
- The coil of liner is heated by steam in the
trailer. - The liner is heated until it is as pliable as wet
leather. - Heating time will vary depending on ambient
temperature, altitude and steam quality.
16LINER INSTALLATION
A cable that has been strung from a winch at the
downstream manhole, through the pipeline to the
upstream manhole is attached to the pulling nose.
17LINER INSTALLATION
The liner is pulled into the host pipe either
directly as shown in the picture on the left or
through the patented shaping device shown on the
right.
18LINER INSTALLATION
The speed at which the liner is inserted into the
pipeline is coordinated using two way radio.
19LINER INSTALLATION
- The liner is pulled to above ground level at the
downstream manhole. - When the liner reaches the maximum above ground
length allowed by the pulley system the winch is
locked in that position.
20LINER INSTALLATION
STRESS RELIEF
- The liner is cut off above ground level at the
upstream manhole. - A flow through plug with the steam hose attached
is inserted into the end of the liner. - Steam under low pressure is forced into the
liner. - As the liner material heats induced stress is
relieved, this is indicated by movement of the
liner. - This process continues until no movement of the
liner is observed.
21LINER INSTALLATION
STRESS RELIEF
- After all movement has ceased at the upstream
end, the excess liner is trimmed and the process
plug installed. - The brake on the winch at the downstream manhole
is released. - Steam is applied to the liner through the plug at
the upstream manhole. - The stress relief process is repeated for the
downstream end of the liner until all movement
has stopped.
Upstream manhole
Downstream manhole
22LINER INSTALLATION
Processing
- After the stress relief process is complete, the
excess liner material is cut away and a
flow-through plug installed. - The hose from the plug is connected to the
downstream exhaust manifold. - The steam temperature and pressure is monitored
and controlled at this process station.
23LINER INSTALLATION
Processing
- The liner is heated using low pressure steam
supplied by a boiler at the upstream end. - Heating time is determined by the length, and SDR
of the liner. - Additional heating time may be added by the
installer if warranted by conditions within the
host pipe.
24LINER INSTALLATION
Forming and Cooling
- At the end of the heating time the process is
switched from steam to compressed air. - The operator at the downstream manifold quickly
increases the internal pressure of the liner
causing it to expand and conform tightly to the
interior of the host pipe. - Internal pressure is maintained until the exhaust
air temperature has reached a predetermined
temperature. - Water may be induced into the compressed air
during the cooling process to reduce the cooling
time.
25POST INSTALLATION CCTV INSPECTION
- After the liner has been cooled, the flow through
plugs are removed and the liner is inspected
using CCTV. - The operator inspects the liner to make sure that
the it has formed properly and that there are no
defects in the liner.
26REINSTATEMENT OF SERVICE CONNECTIONS
Services are reconnected using a remotely
controlled robotic cutter
27REINSTATEMENT OF SERVICE CONNECTIONS
CCTV Camera
Robotic Cutter
Cutter Operator
28REINSTATEMENT OF SERVICE CONNECTIONS
- In most cases the service connection is located
by means of a pronounced dimple in the liner. - When the dimple is not clearly visible, the
cutter operator refers to the pre-installation
inspection tape and the previously recorded
position of all the service connections.
29REINSTATEMENT OF SERVICE CONNECTIONS
- Service connections are reinstated using a
remotely controlled cutting device. - When reinstated the hole for the connection must
be smooth and conform to the inside shape of the
old opening. - The hole must be a maximum of 105 and a minimum
of 90 of the service pipe diameter.
30FINISHING TOUCHES
The ends of the liner are neatly trimmed leaving
one to one and one half inches of liner extending
into the manhole.
31AM-LINERII
Installation advantages
- No refrigeration required for storage and
transportation - No hazardous chemicals to mix
- No noxious odors
- The liner is manufactured in a controlled
environment not in the ground under unstable
conditions - The installation process does not change the
physical properties of the liner material - Simple installation procedure