AM-LINERII - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

AM-LINERII

Description:

AM-LINERII INSTALLATION PROCEDURE Charles A. Munson Introduction This presentation is intended to give an overview of the procedures and techniques used to install ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 32
Provided by: ampipeCom
Category:
Tags: linerii | pulley | system

less

Transcript and Presenter's Notes

Title: AM-LINERII


1
AM-LINERII
INSTALLATION PROCEDURE
  • Charles A. Munson

2
Introduction
  • This presentation is intended to give an
    overview of the procedures and techniques used to
    install the AM-LINERII PVC pipeline
    rehabilitation system.

3
SEQUENCE OF EVENTS
  • Pre-Installation closed circuit television
    inspection
  • Pre-installation pipeline preparation
  • Installation technique
  • Post-installation closed circuit television
    inspection
  • Reinstatement of service connections

4
PRE-INSTALLATION CLOSED CIRCUIT TELEVISION
INSPECTION
  • Identify any conditions in the pipeline that
    could impede or prevent the proper installation
    of the liner
  • Provide a record of the pre-lined condition of
    the pipe
  • Accurately record the position of all service
    connections

5
PRE-INSTALLATION CLOSED CIRCUIT TELEVISION
INSPECTION
  • A highly trained operator uses a remotely
    controlled CCTV camera to assess the condition of
    the pipeline.
  • As the camera passes through the pipeline, images
    from the camera are monitored by the operator and
    recorded either in DVD or VHS format.
  • The operator makes a record of the position of
    all service connections and defects in the
    pipeline.

6
PIPELINE PREPARATION
  • Typical pipeline conditions that must be
    remediated prior to lining
  • Roots
  • Large quantities of groundwater infiltration
  • Collapsed pipe
  • Dropped Joints or offsets of more than 12.5 of
    the inside pipe diameter
  • Protruding taps

7
PIPELINE PREPARATION
ROOTS
  • Roots must be removed from the pipeline prior
    to installing the liner. Roots may be removed by
    using a chemical root treatment or by mechanical
    means such as chain flails.

8
PIPELINE PREPARATION
INFILTRATION
  • Large quantities of cold ground water
    flowing into the pipeline, can act as a heat sink
    and prevent the PVC liner material from reaching
    the temperature needed to form properly.
  • Infiltration may be eliminated either by
    chemical grouting or installing a patch prior to
    lining.

9
PIPELINE PREPARATION
  • Collapsed pipe, dropped or offset joints that
    reduce the inside circumference of the pipeline
    to less than the outside circumference of the
    pipe liner will not allow the liner to form
    properly. This condition is usually presented as
    a longitudinal rib after the liner is installed.
  • To avoid ribs in the liner, sections of
    pipeline containing collapsed pipe, dropped or
    offset joints should be point repaired prior to
    lining.

COLLAPSED PIPE
10
PIPELINE PREPARATION
PROTRUDING TAPS
  • Service taps that protrude into the pipeline
    more than 12.5 or 1-inch should be cut off using
    a chain flail or remotely controlled grinder.

11
PIPELINE PREPARATION
CLEANING
  • Prior to insertion of the liner, the pipeline
    is cleaned using a high pressure water jet to
    remove any debris in the pipeline.

12
LINER INSTALLATION
  • Heating the coil of liner
  • Attaching the liner to the pulling cable
  • Insertion of the liner into the host pipe
  • Stress Relief
  • Processing the liner

13
LINER INSTALLATION
The coil of AM-LINERII is brought to the jobsite
and loaded into an enclosed trailer to be heated.
14
LINER INSTALLATION
Preparing Pulling Nose
The pulling nose is made by folding the flat
liner in half longitudinally, drilling holes
perpendicularly through the folded liner, then
weaving a cable or chain through the holes. The
entire section is then wrapped with duct tape.
The end of the liner is heated to make it pliable.
15
LINER INSTALLATION
  • The coil of liner is heated by steam in the
    trailer.
  • The liner is heated until it is as pliable as wet
    leather.
  • Heating time will vary depending on ambient
    temperature, altitude and steam quality.

16
LINER INSTALLATION
A cable that has been strung from a winch at the
downstream manhole, through the pipeline to the
upstream manhole is attached to the pulling nose.
17
LINER INSTALLATION
The liner is pulled into the host pipe either
directly as shown in the picture on the left or
through the patented shaping device shown on the
right.
18
LINER INSTALLATION
The speed at which the liner is inserted into the
pipeline is coordinated using two way radio.
19
LINER INSTALLATION
  • The liner is pulled to above ground level at the
    downstream manhole.
  • When the liner reaches the maximum above ground
    length allowed by the pulley system the winch is
    locked in that position.

20
LINER INSTALLATION
STRESS RELIEF
  • The liner is cut off above ground level at the
    upstream manhole.
  • A flow through plug with the steam hose attached
    is inserted into the end of the liner.
  • Steam under low pressure is forced into the
    liner.
  • As the liner material heats induced stress is
    relieved, this is indicated by movement of the
    liner.
  • This process continues until no movement of the
    liner is observed.

21
LINER INSTALLATION
STRESS RELIEF
  • After all movement has ceased at the upstream
    end, the excess liner is trimmed and the process
    plug installed.
  • The brake on the winch at the downstream manhole
    is released.
  • Steam is applied to the liner through the plug at
    the upstream manhole.
  • The stress relief process is repeated for the
    downstream end of the liner until all movement
    has stopped.

Upstream manhole
Downstream manhole
22
LINER INSTALLATION
Processing
  • After the stress relief process is complete, the
    excess liner material is cut away and a
    flow-through plug installed.
  • The hose from the plug is connected to the
    downstream exhaust manifold.
  • The steam temperature and pressure is monitored
    and controlled at this process station.

23
LINER INSTALLATION
Processing
  • The liner is heated using low pressure steam
    supplied by a boiler at the upstream end.
  • Heating time is determined by the length, and SDR
    of the liner.
  • Additional heating time may be added by the
    installer if warranted by conditions within the
    host pipe.

24
LINER INSTALLATION
Forming and Cooling
  • At the end of the heating time the process is
    switched from steam to compressed air.
  • The operator at the downstream manifold quickly
    increases the internal pressure of the liner
    causing it to expand and conform tightly to the
    interior of the host pipe.
  • Internal pressure is maintained until the exhaust
    air temperature has reached a predetermined
    temperature.
  • Water may be induced into the compressed air
    during the cooling process to reduce the cooling
    time.

25
POST INSTALLATION CCTV INSPECTION
  • After the liner has been cooled, the flow through
    plugs are removed and the liner is inspected
    using CCTV.
  • The operator inspects the liner to make sure that
    the it has formed properly and that there are no
    defects in the liner.

26
REINSTATEMENT OF SERVICE CONNECTIONS
Services are reconnected using a remotely
controlled robotic cutter
27
REINSTATEMENT OF SERVICE CONNECTIONS
CCTV Camera
Robotic Cutter
Cutter Operator
28
REINSTATEMENT OF SERVICE CONNECTIONS
  • In most cases the service connection is located
    by means of a pronounced dimple in the liner.
  • When the dimple is not clearly visible, the
    cutter operator refers to the pre-installation
    inspection tape and the previously recorded
    position of all the service connections.

29
REINSTATEMENT OF SERVICE CONNECTIONS
  • Service connections are reinstated using a
    remotely controlled cutting device.
  • When reinstated the hole for the connection must
    be smooth and conform to the inside shape of the
    old opening.
  • The hole must be a maximum of 105 and a minimum
    of 90 of the service pipe diameter.

30
FINISHING TOUCHES
The ends of the liner are neatly trimmed leaving
one to one and one half inches of liner extending
into the manhole.
31
AM-LINERII
Installation advantages
  • No refrigeration required for storage and
    transportation
  • No hazardous chemicals to mix
  • No noxious odors
  • The liner is manufactured in a controlled
    environment not in the ground under unstable
    conditions
  • The installation process does not change the
    physical properties of the liner material
  • Simple installation procedure
Write a Comment
User Comments (0)
About PowerShow.com