Title: Construction Site Best Management Practices
1Construction Site Best Management Practices
and the Project Design Process
2Why are you here
- As Caltrans staff from Design (or other
divisions) you need to know how to - Assess your project for implementation of
appropriate Construction Site BMPs - Incorporate selected Construction Site BMPs as
separate bid items (lump sum is not an option) - Develop the engineers estimate of separate
Construction Site BMPs - Incorporate a Construction Site BMP strategy into
the Storm Water Data Report
- To complete these tasks, you also need to know
- About the Standard Special Provisions
2
3Agenda
Module Topic Time
0 Overview 60 Minutes
I Introduction 45 Minutes
II Soil Stabilization (SS) and Sediment Control (SC) BMPs 60 Minutes
III Tracking, Wind Erosion, and Construction Site Management BMPs 60 Minutes
IV Incorporation of Construction Site BMPs into the Design Process 90 Minutes
V Final Wrap-Up 45 Minutes
3
4Course Administration
- Sign-in and attendance forms
- Breaks
- Restrooms
- Emergency exits
- Classroom etiquette
4
5Course Administration
- Expenditure Authorization (EA) 910076
- Special Designation G100695 2059
5
6Introduction Your Facilitators
- Who am I?
- What is my background?
- What is my storm water background?
6
7Introduction About You
- Who are you?
- What is your storm water background?
- What do you want to learn from this class?
7
8The Pre-Test
- Evaluates your current level of knowledge
- Covers course topics
- Time limit 15 minutes
- Same test will be given at the end of the course
to evaluate what you learned - Answers will be reviewed at the end of the course
- Results will be used to evaluate the
effectiveness of this training
8
9Pre-Test
9
10Module Topic
0 Overview
I Introduction
II Soil Stabilization (SS) and Sediment Control (SC) BMPs
III Tracking, Wind Erosion, and Construction Site Management BMPs
IV Incorporation of Construction Site BMPs into the Design Process
V Final Wrap-Up
Module I
Introduction
10
11Module I Objectives
- The student will learn about
- The regulatory background
- Department policy and goals
- NPDES definitions
- The Caltrans manuals available to designers
11
12Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Regulatory Background
Clean Water Act Enforced by USEPA
12
13 Caltrans Statewide NPDES Permit California
General Construction Permit Caltrans Storm
Water Management Plan
Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Implementing the Caltrans Storm Water Quality
Program
13
14Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Caltrans StatewideNPDES Permit
- Issued in 1999 by the State Water Resources
Control Board (SWRCB) - Implements year-round program throughout state to
control storm water and nonstorm water
discharges from all Caltrans properties - Caltrans must comply with the California General
Construction Permit - Appropriate best management practices (BMPs) must
be installed
14
15Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
General Construction Permit
- Applies to projects that disturb gt 1 acre (0.4
ha) of soil - Disturbance means any construction activity that
creates exposed soils - Applies to smaller areas if part of a larger
common plan of development - Requires development of a storm water pollution
prevention plan (SWPPP) - Enforced by the RWQCBs
15
16Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Caltrans SWMP
- The Storm Water Management Plan (SWMP) was
adopted in May 2003 and includes the following - How Caltrans is organized
- The responsible people
- The process to disseminate information to staff,
contractors, and public - A self-audit program
16
17Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Department Policy
- The storm water data report should describe the
strategy for incorporating construction site BMPs
into the contract documents. - Designers are required to consider the BMPs as
separate bid line items for all projects. - Preferred types of BMPs may vary from district to
district therefore, Design and Construction
Divisions should be in concurrence with the
strategy.
17
18Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Department Goals
- Better projects can be achieved by
- Helping contractors develop more accurate,
competitive bids for all Caltrans construction
projects - Reducing construction costs arising from contract
change orders (CCOs) and claims - Facilitating implementation of preferred
temporary BMPs during construction of the project
18
19Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
NPDES Definitions
- What is a best management practice (BMP)
- A measure implemented to protect water quality
and reduce potential pollutants associated with
storm water runoff - Any program, technology, process, siting
criteria, operating method, or device that
controls, prevents, removes, or reduces pollution
19
20Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Caltrans-Approved Best Management Practices (BMPs)
- There are several Caltrans-approved BMPs
- Design Pollution Prevention (DPP) BMPs
- Treatment BMPs
- Maintenance BMPs
- Construction Site BMPs
20
21Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Design Pollution Prevention BMPs
DPP BMPs are permanent water quality controls
used to reduce pollutant discharges by preventing
erosion.
Flared End Sections
21
22Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Treatment BMPs
Treatment BMPs are water quality controls used to
remove pollutants from storm water runoff prior
to its being discharged from the Caltrans right
of way.
Gross Solid Removal Devices
22
23Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Maintenance BMPs
Maintenance BMPs are water quality controls used
to reduce pollutant discharges during highway
maintenance activities and during the operation
of the facility.
Storm Drain Stenciling
Sweeping Operations
23
24Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Construction Site BMPs
Construction Site BMPs are temporary controls
used to control pollutant discharges during
construction.
Temporary Hydraulic Mulch (Polymer Stabilized
Fiber Matrix)
24
25Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Construction Site BMP Categories
Construction Site BMPs are separated into six BMP
categories as follows
- Soil Stabilization Practices
- Sediment Control Practices
- Tracking Control Practices
- Wind Erosion Controls
- Non-Storm Water Controls
- Waste Management and Materials Pollution Controls
25
26Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Temporary vs. Permanent BMPs
- Temporary
- Implemented only for the duration of the contract
- Will be removed
- Permanent
- Installed as part of the construction work
- Will not be removed
26
27Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Active vs. Non-Active Areas
Active Areas are construction areas where soil
disturbing activities have already occurred and
continue to occur or will occur during the
ensuing 21 days.
Non-Active Areas are construction areas (formerly
active areas) that will be idle for at least 21
days.
27
28Caltrans Storm WaterQuality Handbooks
Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
- Project Planning and Design Guide
- Construction Site BMPs Manual
- SWPPP and WPCP Preparation Manual
28
29Project Planning and Design Guide (PPDG)
Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
- Provides guidance on the following
- BMP selection and design process
- Incorporation of BMPs into PID, PA/ED, and PSE
- Storm water data report (SWDR)
- BMP cost information
Recent version (revised May 2007) can be found at
http//www.dot.ca.gov/hq/oppd/stormwtr/
29
30Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
Construction Site Best Management Practices Manual
- Provides detailed information on Construction
Site BMPs, including the following - Instructions for selection and implementation of
Construction Site BMPs - Working details forConstruction Site BMPs
Recent version (dated March 2003) can be found
at http//www.dot.ca.gov/hq/construc/stormwater/ma
nuals.htm
30
31Regulatory background
Department policy and goals
NPDES definitions
Caltrans manuals
SWPPP WPCP Preparation Manual
- Guides contractors and Caltrans staff through the
process of preparing the following - Storm Water Pollution Prevention Plan (SWPPP)
- Water Pollution Control Program (WPCP)
Recent version (dated March 2007) can be found
at http//www.dot.ca.gov/hq/construc/stormwater/ma
nuals.htm
31
32Construction Site BMPs and the Design Process
33Include Construction Site BMP Strategy in the
Storm Water Data Report
- At each design phase (PID, PA/ED, PSE), include
the following - Temporary BMP information
- Quantity and cost information
- Construction Division concurrence information
33
34BMP Strategy and Cost Estimate
- PID
- General BMP Strategy
- Cost Allocation
- PA/ED
- Refined BMP Strategy
- Refined Cost estimate
- PSE
- Detailed BMP Strategy
- Select Construction Site BMPs
- Select SSPs for Line Items
- Prepare Water Pollution Control Summary Sheets
- Estimate BMPs for Line Items and Lump Sum
35Module I Summary
- These are the topics that we have just covered
- The regulatory background
- Department policy and goals
- NPDES definitions
- The Caltrans manuals available to designers
35
36Questions
36
San Mateo 1, Culvert Replacement Project
37Okay, I have a couple of questions
What are the benefits of identifying Construction
Site BMPs during the project design process?
What is Department policy concerning Construction
Site BMPs and the project design process?
37