Enterprise Analysis and Design Method - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

Enterprise Analysis and Design Method

Description:

Chapter 6 Enterprise Analysis and Design Method Ronald E. Giachetti, Ph.D. Associate Professor Industrial and Systems Engineering, FIU * * August 18, 2006 ... – PowerPoint PPT presentation

Number of Views:264
Avg rating:3.0/5.0
Slides: 45
Provided by: bart70
Category:

less

Transcript and Presenter's Notes

Title: Enterprise Analysis and Design Method


1
Chapter 6 Enterprise Analysis and Design Method
Ronald E. Giachetti, Ph.D. Associate Professor
Industrial and Systems Engineering, FIU
2
Overview
  • Present enterprise architecture mapping to
    system life-cycle
  • System life-cycle
  • Method tools
  • Method techniques

3
(No Transcript)
4
(No Transcript)
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
Method Tools
  • Project Charter template
  • Business Case template
  • Budget spreadsheet
  • Requirements template
  • Estimation spreadsheet

12
Too much planning?
13
No planning?
14
Work Breakdown Structure (WBS)
  • The Work Breakdown Structure (WBS) is a tool that
    defines a project and groups the projects
    discrete work elements in a way that helps
    organize and define the total work scope of the
    project.
  • WBS also provides the necessary framework for
    detailed cost estimating and control along with
    providing guidance for schedule development and
    control.

15
WBS for Home Construction
? Level 1
? Level 2
Level 3 ?
16
Project Management -- WBS
Work Breakdown Schedule (WBS)
  • Each task should
  • have a well-defined start and end
  • By easy to track (schedule budget)
  • Single individual is responsible
  • Have budget allocated to it
  • Task duration should be proportional to overall
    project

17
Estimation
  • For each Work Breakdown Activity
  • Assign project team role to activity
  • Estimate person-hours
  • work measurement
  • regression analysis
  • expert
  • Determine start date and end date
  • Estimate budget for activity (Rate Hrs)


Slide 17
Ronald E. Giachetti December 17, 2013
18
Estimation Approaches
  • Expert Opinion
  • Top-down use previous similar projects to
    estimate
  • Parametric a percentage of size or other
    project characteristic
  • Three-point most likely, optimistic, pessimistic

19
Responsibility Assignment Matrix
  • Assign staff to WBS elements.

20
Responsibility Assignment Matrix
  • Can show estimated person-hours and determine
    workload of each staff member.

21
Cross Life-cycle activities
  • Project Management
  • Requirements Management
  • Quality Assurance
  • Configuration Management Control
  • Risk Management

22
Requirements Management
  • Requirements Management is the process of
    managing change to the requirements.
  • It is during the analysis phase that requirements
    are elicited, specified, and documented.
  • The project team establishes and maintains a plan
    for performing requirements management. Included
    in requirements
  • management is a plan for ensuring bi-directional
    requirements traceability.
  • Additionally, requirements are a configuration
    item to be tracked and controlled as part of the
    configuration management process.

23
Risk Management
  • The systematic process of identifying, analyzing,
    and responding to project risk.
  • Risk is the possibility of suffering diminished
    project success (scope, cost, schedule)
  • Risk management is proactive identify risk and
    take action to prevent or mitigate

24
Risk Probability
  • Often from Expert Opinion without value of
    historical data.
  • Cannot assign valid probabilities with any
    reliability.
  • Ordinal Scale

Very unlikely Unlikely Possible Highly likely Almost certain
0.1 0.3 0.5 0.7 0.9
0.05 0.1 0.2 0.4 0.8
25
Risk Impact (ordinal scale)
Project Objective Very Low (0.5) Low (0.1) Moderate (0.2) High (0.4) Very High (0.8)
Costs Insignificant cost increase lt5 cost increase 5-10 cost increase 10-20 cost increase gt 20 cost increase
Schedule Insignificant schedule slippage Schedule slippage lt 5 Overall project slippage 5-10 Overall project slippage 10-20 Overall project slippage gt 20
Scope Scope decrease barely noticeable Minor areas of scope are affected Major areas of scope are affected Scope reduction unacceptable to client Project end item is effectively useless
Quality Quality degradation barely noticeable Only very demanding applications are affected Quality reduction requires client approval Quality reduction unacceptable to client Project end item is effectively unusable
26
Which is more risky with numbers?
Project A
Project B
Technology depends on availability of rare earth
elements that are only sourced from China and
supply is uncertain. The likelihood of supply
disruptions is low (0.1) , but if it occurs
production of the technology could stop (expected
budget impact of 1M).
Application software for new technology is being
written by government software engineers.
Compared to those in industry, they are poorly
paid, so risk of turn-over is high (especially if
economy improves), and this would disrupt ability
to meet deadlines. The likelihood of a single
software engineer leaving is high (0.8) , but
delays on meeting deadline are minimum (expected
schedule impact of 1 week).
27
Probability Impact Matrix
High Risk/Impact
Low Risk/Impact
CAUTION do not put too much stock in actual
values.
28
Sample Probability/Impact Matrix
Taken from IT Project Mgmt, 3rd edition, Course
Technology Publishing
29
Understand Risk
Will risky new technology mature before Milestone
B? Is there a risk mitigation plan?
Probability of risk event
consequence
Showing full probability distribution provides
complete information of expected value and
variation that can enable better decision-making
with respect to risk
30
Identify potential scenarios and associated risks
31
Strategies
  • Avoidance change project plan to eliminate risk
    or to protect project objectives from risk
    impact.
  • Transference shift the consequence of the risk
    to a third party with ownership of the response.
    (usually for financial risks, use of insurance,
    warranties, and so forth).
  • Mitigation reduce the probability and/or
    consequence of the risk to an acceptable
    threshold. Earlier the better. Mitigation costs
    should be appropriate.
  • Acceptance do not change project plan. Develop
    a contingency plan if risk event should occur.

32
Quality Assurance
  • Quality Assurance (QA) is a planned and
    systematic approach necessary to provide adequate
    confidence that an item or product conforms to
    established standards, procedures and policies
  • QA is an umbrella activity that is applied at
    each step in the process of building the system
  • QA is a CMMI Level 2 Process
  • Dont equate QA with Test (although testing is
    important)

33
QA Feedback
QA
QA
QA Criteria
Objective Feedback via
Should be part of a continuous improvement plan
  • Evaluations
  • Noncompliance reports
  • Corrective actions

ERP Implementation Process
34
Famous Software errors
  • ATT Long Distance phone lines down for 9 hours in
    1990.
  • (caused by a software upgrade)
  • Patriot missile failure to track an incoming SCUD
    missile in the 1991 Gulf War. 28 soldiers
    killed.
  • (an arithmetic error accumulated over time)
  • Gemini V orbiter missed its landing site by 100
    miles. (Failure to take into account Earths
    motion around the sun)
  • Mariner I Venus probe veered off course after
    lift-off and had to be destroyed.
  • (A period in the code should have been a comma).

35
Types of Tests
  • Unit Test Test each individual component to
    ensure it is as defect free as possible
  • Integration test Occurs between unit and
    system testing to test functionally grouped
    components
  • Interface Test Test the interfaces in the
    end-to-end business process
  • Security Test Test users security access
    provides proper authority for their roles in the
    business processes
  • User Acceptance test Is an independent test
    performed by the end user prior to accepting the
    delivered system users sign off on test results
  • System Test Test the system as a whole
  • Regression Test Test that changes do not
    adversely impact already tested components

36
Configuration Management Control
  • The purpose of Software Configuration Management
    is to establish and maintain the integrity of the
    products of the software project? throughout the
    project's software life cycle.
  • Software Configuration Management involves
    identifying the configuration of the software
    (i.e., selected software works products and their
    descriptions) at given points in time,
    systematically controlling changes to the
    configuration, and maintaining the integrity and
    traceability of the configuration throughout the
    software lifecycle.
  • Standards (approved by ANSI)
  • IEEE 828 Software Configuration Management Plans
  • IEEE 1042 Guide to Software Configuration
    Management

37
Configuration Items
  • A configuration item (CI) is any part of the
    development and/or deliverable system which needs
    to be independently identified, stored, tested,
    reviewed, used, changed, delivered and/or
    maintained
  • CIs can differ widely in complexity and may
    contain other CIs in a hierarchy
  • Includes code, modules, and documentation
  • all type of code files
  • drivers for tests
  • analysis or design documents
  • user or developer manuals
  • system configurations (e.g. version of compiler
    used)

38
Finding Configuration Items
  • Large projects typically produce thousands of
    entities (files, documents, data ...) which must
    be uniquely identified
  • Any entity managed in the software engineering
    process can potentially be brought under
    configuration management control
  • But not every entity needs to be under
    configuration management control all the time
  • Two Issues
  • What Selection of Configuration Items to be
    under configuration control
  • When When do you start to place entities under
    configuration control?

39
Finding Configuration Items (continued)
  • Some items must be maintained for the lifetime of
    the software
  • An entity naming scheme should be defined so that
    related documents have related names
  • Selecting the right configuration items is a
    skill that takes practice
  • Very similar to object modeling in
    object-oriented design
  • Use techniques similar to object modeling for
    finding CIs!
  • Find the CIs
  • Find relationships between CIs

40
Which of these Entities should be Configuration
Items?
  • Problem Statement
  • Software Project Management Plan (SPMP)
  • Requirements Analysis Document (RAD)
  • System Design Document (SDD)
  • Project Agreement
  • Object Design Document (ODD)
  • Dynamic model
  • Object model
  • Functional model
  • Unit tests
  • Integration test strategy
  • Source code
  • API Specification
  • Input data and data bases
  • Test plan
  • Test data
  • Support software that is part of the final system
  • Support software that is not part of the product
  • User manual
  • Administrator manual

41
Possible Selection of Configuration Items
  • Problem Statement
  • Software Project Management Plan (SPMP)
  • Requirements Analysis Document (RAD)
  • System Design Document (SDD)
  • Project Agreement
  • Dynamic Model
  • Object model
  • Functional Model
  • Unit tests
  • Integration test strategy
  • Source code
  • API Specification
  • Input data and data bases
  • Test plan
  • Test data
  • Support software (part of the product)
  • Support software (not part of the product)
  • User manual
  • Administrator manual

Once the Configuration Items are selected, they
are usually organized in a tree
42
Baseline
  • A specification or product that has been formally
    reviewed and agreed upon, that serves as the
    basis for further development, and that can be
    changed only through formal change control
    procedures
  • Examples
  • Baseline A All the APIs have completely been
    defined the bodies of the methods are empty
  • Baseline B All data access methods are
    implemented and tested
  • Baseline C The GUI is implemented

43
Change Management
  • Change management is the handling of change
    requests
  • A change request leads to the creation of a new
    release
  • General change process
  • The change is requested (this can be done by
    anyone including users and developers)
  • The change request is assessed against project
    goals
  • Following the assessment, the change is accepted
    or rejected
  • If it is accepted, the change is assigned to a
    developer and implemented
  • The implemented change is audited
  • The complexity of the change management process
    varies with the project. Small projects can
    perform change requests informally and fast while
    complex projects require detailed change request
    forms and the official approval by one more
    managers

44
Summary
  • This chapter establishes the overall architecture
    and methodology to do an enterprise project
  • Understand life-cycle phases, their inputs,
    outputs, and activities
  • Cross life-cycle activities
  • Project initiation and project charter to start
    project
Write a Comment
User Comments (0)
About PowerShow.com