Cost Estimation - PowerPoint PPT Presentation

About This Presentation
Title:

Cost Estimation

Description:

CHAPTER 7 Cost Estimation Review General Problem Solving Skills Moving Money through Time (Equivalence Models) Developing Estimates of Future Cash Flows Using Cash ... – PowerPoint PPT presentation

Number of Views:156
Avg rating:3.0/5.0
Slides: 35
Provided by: sarf
Learn more at: https://www.ecs.csun.edu
Category:
Tags: cost | estimation

less

Transcript and Presenter's Notes

Title: Cost Estimation


1
CHAPTER 7
  • Cost Estimation

2
Review
  • General Problem Solving Skills
  • Moving Money through Time (Equivalence Models)
  • Developing Estimates of Future Cash Flows
  • Using Cash Flows to Compute Various Measures of
    Economic Merit before and after tax
  • Chapter 2
  • Chapter 3
  • Chapter 7
  • Chapter 4, 5, and 6

3
Cost Estimation
  • What is estimating?
  • A forecast, a best guess, a projection into the
    future
  • For the most part, Engineers generally have the
    responsibility of cost estimation
  • Future costs are very critical to the analysis of
    a project
  • Revenue generation generally comes from marketing
    or sales areas

4
Applications
  • What is the purpose of estimating?
  • quoting, bidding, or evaluating bids
  • profitability analysis
  • basis for make versus buy decisions
  • investment justification
  • basis for comparing manufacturing methods
  • basis for cost reduction
  • planning new products and services
  • All these involve developing cash flows for
    feasible alternatives

5
Costs to Estimate
  • What costs are to be estimated?
  • First cost elements
  • Equipment cost
  • Delivery charges
  • Installation costs
  • Insurance costs (premiums)
  • Training of personnel for equipment use.
  • The first important cost
  • Given the interest rate and the estimated life of
    the asset
  • Calculate the Capital Recovery Costs

6
Annual Operating Cost Estimation
  • Estimate the AOC using
  • Direct Labor Costs
  • Direct materials costs
  • Periodic maintenance costs
  • Rework and rebuilt
  • Other costs could be
  • On-line testing and calibration
  • Proofing runs before actual production.

7
Work Breakdown Structure (WBS)
  • The WBS technique organizes activities into a
    hierarchical structure based on either functional
    or physical categories
  • See Figures 7-2 and 7-3
  • WBS - Organizational Schemes
  • Functional
  • Logistical Support, Project Management,
    Marketing, Engineering, System Integration
  • Physical
  • Products, Outputs, or Parts that make up the
    structure

8
WBS-Tabular Format
  • 1.0 Commercial Building Project
  • 1.1 Site Work and Foundation
  • 1.1.1 Site Grading
  • 1.1.2 Excavation
  • 1.1.3 Sidewalks/Parking
  • 1.1.4 Footing/Foundation
  • 1.1.5 Floor Slab
  • 1.2 Exterior
  • 1.2.1 Framing
  • 1.2.2 Siding
  • 1.2.3 Windows
  • 1.2.4 Entrances
  • 1.2.5 Insulation
  • 1.3 Interior
  • 1.3.1 Framing
  • 1.3.2 Flooring/Stairways
  • 1.3.3 Walls/Ceilings
  • 1.3.4 Doors
  • 1.3.5 Special Additions

9
Cost Estimation Approaches
  • Bottom-Up Approach
  • Treats the final cost as an independent (output)
    variable and the associated costs as input or
    dependent variables
  • Top-Down Approach
  • Treats the competitive cost as an input variable
    and the associated cost estimates as the output
    variables
  • Also called Design-to-Cost Approach

10
Two Cost Estimating Approaches
11
Bottom-Up Approach
  • Treats the final cost as an independent (output)
    variable and the associated costs as input or
    dependent variables.
  • Cost components are first identified
  • Cost elements are estimated
  • Price DC TIDC Profit
  • Traditional costing approach
  • Applied in industries where competition is not
    the dominant factor in pricing the product or the
    service

12
Top-Down Approach
  • Treats the competitive cost as an input variable
    and the associated cost estimates as the output
    variables.
  • Applied in the early stages of new or enhanced
    product design
  • Price estimates are conducted to set target
    values
  • Detailed design and equipment needs are not yet
    defined
  • Becoming more popular especially in high
    competition markets
  • Places greater emphasis on the accuracy of the
    estimation process
  • Common practice in Eastern cultures (Japan and
    other Asian countries)

13
Accuracy of Estimates
  • NO estimate is intended to be exact
  • But must be reasonable and accurate enough to
    provide a robust economic analysis.
  • In Preliminary Design Phase
  • Estimates are viewed as first cut estimates.
  • Serve as inputs to the project initial budget.
  • The unit method is often applied here
  • Accepted Range of Accuracy
  • Per Unit approaches should fall into the ?5 to
    ?15 range for total costs
  • Estimates outside of the ?15 range are not
    reliable!

14
Cost Estimation Techniques
  • Expert Opinion
  • Past experience in the field
  • Cost Indexes where available
  • Cost Estimating Relationships (forms of
    regression analysis based upon historical data)
  • Combinations of the above.

15
Cost Index
  • Cost Index is a ratio of a cost NOW to some cost
    back in time.
  • The index is a dimensionless number.
  • Example The Consumer Price Index (CPI)
  • Cost Index Notation
  • IN Index for some current year, N
  • Ik Index for some base year, k
  • Ck cost of some item during base year
  • CN Ck ( IN / Ik )
  • CN cost of the item during the current year

16
Sources
  • Chemical Engineering plant cost index
  • Engineering News Record
  • Marshall Swift equipment cost index
  • Many others
  • Most are web-based but require a subscription
    fee to access detailed values

17
Index Example
  • Need to estimate skilled labor for a construction
    project
  • 5 years ago the cost was documented to be
    360,000.
  • Skilled labor index then was 3,496.27.
  • Today the index is 4,038.44.
  • What is the estimated labor cost today based upon
    this information?
  • CN Ck ( IN / Ik )

18
Warnings to Heed
  • For manufacturing and servicing industries
    tabulated cost indexes are not readily available
  • Cost indexes may vary with the region of the
    country
  • Cost indexes are very sensitive over time to
    technological changes.

19
Development of Cost Index-Example
  • A manufacturing engineer with Hughes Industries
    is interested in estimating the cost of plant
    expansion. Two items used in the manufacturing
    process are A and 2. Consulting through
    Purchasing Department, he found the following
    historical data. Make the first quarter of 2001
    the base period, and determine the cost indexes
    using a basis of 100.
  • Year 1999 2000 2001 2002
  • Quarter Q1 Q2 Q1 Q2 Q1 Q2 Q1
  • --------------------------------------------------
    ------------------------------------------------
  • Item A, /unit 57.00 56.90 56.90 56.70 56.60 56.40
    56.25
  • Item B, /Unit 446 450 455 575 610 625 635

20
Solution
  • For each item, the index (IN/Ik) is calculated
    with the firs-quarter 2001 cost used for the Ik
    value
  • Year 1999 2000 2001 2002
  • Quarter Q1 Q2 Q1 Q2 Q1 Q2 Q1
  • --------------------------------------------------
    ------------------------------------------------
  • Item A cost index 100.71 100.53 100.53 100.17 100.
    00 99.65 99.38
  • Item B cost index 73.11 73.77 74.59 94.26 100.00 1
    02.46 104.10
  • ((56.60-56.60)/56.60 )100100

21
The Unit Technique
  • Unit Method
  • Popular, Very preliminary in nature, Multiply the
    number of units times a per unit cost factor.
  • Examples
  • Cost per operating mile (autos, trucks, etc.),
    Cost of construction (per sq. foot), Cost per
    mile (highways, cable, etc.)

22
The Factor Technique
  • An extension of the unit method
  • Originally developed for estimating total plant
    costs
  • Identify the major equipment items, then multiply
    by certain factors
  • Sum of products of component quantities and
    corresponding unit costs plus component costs
    estimated directly
  • C S dCd S mfmUm
  • C cost being estimated
  • Cd cost of d estimated directly
  • fm cost per unit of m
  • Um number of units of m

23
Example
  • Estimate the cost of a house consisting of 2,000
    sq, two porches, and a garage. Using unit factor
    of 50 per sq, and 5,000 per porch and 8,000
    per garage.
  • C S dCd S mfmUm
  • C(5,0002)8000(502000)118,000

24
Cost Estimating Relationships ( CER )
  • CERs use design variables to predict costs.
  • CERs are more quantitative in nature than cost
    indexes.
  • Developed from statistical approaches
  • Usually linear or non-linear regression models.
  • A common model Cost-Capacity Model
  • A model that relates the cost of an asset or
    activity to its capacity
  • Called also power-sizing

25
The Power-Sizing Technique
  • Also referred to as exponential model
  • Used for costing plants and equipment
  • Recognizes that cost varies as some power of the
    change in capacity or size
  • Example
  • (CA / CB) (SA / SB)X
  • CA CB(SA / SB)X
  • CA Cost of plant A CB Cost of plant B
  • SA Size of plant A SB Size of plant B
  • X cost-capacity factor (reflects economies of
    scale)

26
The Exponent in the CCE - x
  • Normally 0 ltxlt1
  • For x lt 1 the economies of scale are applied.
  • For x 1, the model is linear.
  • For x gt 1, a larger size is expected to be more
    costly than a linear model.
  • If x is unknown, common to assume x 0.6
  • The Chemical Engineering area has well documented
    CCE parameters.
  • Other sources
  • Plant Design and Economics for Chemical
    Engineers
  • Chemical Engineers Handbook
  • EPA publications
  • Equipment companies.

27
The Learning and Experience Technique
  • Learning curve is a mathematical model that
    explains increased worker efficiency and improved
    performance from repetitive production
  • Most learning curves are based on the assumption
    that the number of input resources needed
    decreases by a constant percentage each time the
    number of units produced doubles.
  • Zu Kun
  • u the output unit number
  • Zu resource units to produce output unit u
  • K resource units to produce 1st output unit
  • s learning-curve slope parameter (decimal)
  • n log s / log 2

28
Example
  • It has been determined that a 90 learning curve
    applies to a particular assembly operation. It
    takes 30 minutes to assemble the first unit. How
    many minutes are required to produce the 5th
    unit? the 30th unit?
  • n log (0.9) / log (2) -0.152
  • Z 5 30(5) -0.152 23.49 minutes
  • Z 30 30(30) -0.152 17.89 minutes

29
Other Computations
  • Tu cumulative time to produce u units K?un
  • Cu cumulative average for u units Tu/u
  • Continuing our example,
  • T5 301 -0.152 2 -0.152 3 -0.152 4 -0.152
    5 -0.152 130.18 minutes
  • C5 T5/5 130.18/5 26.04 minutes per unit

30
Another Example
  • A construction Company designs and builds
    residential family homes. The company is ready to
    construct, in sequence, 16 new homes of 2400
    square feet each. The same basic design, with
    minor changes, will be used for each home. The
    successful bid for the construction materials in
    the first home is 64,800, or 27/square foot.
    The manger believes, based on past experience,
    that several actions can be taken to reduce
    material cost by 8 each time the number of homes
    constructed doubled. Based on this information,
    (a) what is the estimated cumulative average
    material cost per square foot for the first
    homes, and (b) what is the estimated material
    cost per square foot for the last 16th home?

31
Manufacturing Cost Estimating
  • Objective
  • To make a product that can be sold at a
    competitive price yet yields a reasonable profit.
  • Determining Selling Price
  • To estimate the cost of a manufactured product,
    you need a product design and process plan to
    compute direct labor hours and material costs
  • A cost estimating worksheet or spreadsheet (e.g.,
    Figure 8-5) is a useful tool for this.

32
Cost Accounting Overview
  • Costs incurred within a system are tracked by the
    cost accounting system
  • Cost accounting system accumulates
  • Material costs, Labor costs, and Indirect costs
    (overhead or factory expense)
  • And allocates these cost to defined cost centers.
  • A difficult problem, when required, is to
    properly allocate the IDCs to the various cost
    centers, departments, processes, and product
    lines.
  • Cost centers do utilize a portion of the total
    indirect costs
  • Thus, some allocation scheme needs to be applied
    to the cost centers

33
Traditional IDC Allocations
34
Summary
  • Cost estimation is not an exact science
  • Estimates should be accurate enough to support
    robust engineering economy cost analysis
  • Two Approaches (Treat costs differently)
  • Bottom-Up and Top-Down
  • Cost Indexes are used to estimate and update
    costs
  • Cost Estimating
  • Cost-Capacity Equations,
  • Cost estimation from design variables for
    material, equipment, and construction.
  • Factor Method
  • Used to estimate total plant costs.
Write a Comment
User Comments (0)
About PowerShow.com