Title: Design for Efficiency Scheme
1Design for Efficiency Scheme
Ang Chye Peng, Engineer Resource Conservation
Department
2Objective
- To encourage investors in new facilities in
Singapore to integrate energy and resource
efficiency improvements into manufacturing
development plans early in the design stage - This scheme is targeted at large consumers of
energy
3Design Workshop
- Energy efficient facilities are most effectively
developed through design workshops (also known as
design charrettes) - Design workshop
- An intensive, highly integrative and
multi-disciplinary 2-3 day session that brings
together multiple internal experts (home team)
and external experts (visiting team) at the
design stage
VISITING TEAM
Expert facilitation and process support Technical expertise
HOME TEAM HOME TEAM
Building owner Building users Building operator Project Manager Facility directors Facility operators Architect Interior designer Electrical engineer Mechanical engineer Contractors Etc.
4Design Workshop
- By fostering cross-disciplinary interaction,
design workshops encourage the exchange of ideas
and information, allowing truly integrated design
solutions to take form and generating solutions
that would otherwise remain obscured by
conventional thinking. - Requires 3-4 months preparation for maximum
success - Most effective very early in design phase
5Design Workshop Outcomes
- Opportunities in
- Resource efficiency reduced demand (energy,
water, gases) - Waste reduction and reuse
- Cost-effective supply (energy, water, etc.)
- Conceptual design for high-efficiency plant and
systems - Preliminary estimates of net cost and
payback/return
6Design Workshop Success Stories
- In 2008, a design workshop was conducted by Rocky
Mountain Institute (RMI) to think through EDSs
plan for a new data center and identify
opportunities for breakthrough energy efficiency.
- The design workshop identified advanced design
measures that will substantially reduce energy
use and likely lead to increased revenue. - The capital cost savings are estimated at
US28.2mil and the annual energy savings are
US1.8mil.
7Design Workshop Success Stories
- In Texas, Texas Instruments (TI) broke ground on
a state-of-the-art, 100,000 m2 chip fab (with
20,000 m2 of clean room), designed with ideas
generated at a design workshop conducted by Rocky
Mountain Institute (RMI). - The new facility cut energy use by 20 and water
use by 35, compared with TI's previous wafer
fab. - At least US750,000 in operating costs in first
year, more than US3mil per year at full build. - Savings come about half each from better tools
and their direct support equipment and from
smaller, more efficient utilities and building
systems.
8Form of Assistance
- Grant quantum
- 80 of the qualifying costs or S600,000,
whichever is lower - Qualifying costs
- Qualifying costs would include the design
workshop fees - Consultancy fees, comprising manpower and
overheads - Transportation and accommodation for consultants
- Venue and other logistical costs for workshop
9Eligibility Criteria
- Company
- Owner or operator of new industrial facility in
Singapore - Consultants
- Experienced external consultants with good track
record in carrying out design workshops of a
comparable scale and scope -
- Consultants should be external experts
providing facilitation and technical expertise to
the design workshop. They should not be design
consultants directly involved in design
development.
10Process
Company submits application with copy of proposed
contract with consultant
Approval granted
Within 4 months
Company signs contract with consultant
40 reimbursed
Within 6 months
Consultant conducts design workshop
Within 14 months
Within 2 months
Company submits design workshop report
40 reimbursed
Company submits assessment report
20 reimbursed
END
11More Information
- Application form and more information are
available at http//www.e2singapore.gov.sg/design
-for-efficiency.html
12Thank you
13Design Workshop Results EDS
- Key design recommendations included
- Replacing entry level servers with
best-in-energy-class equipment - Consolidating entry level servers by removing
unused equipment, rationalizing applications and
virtualizing - Reducing electrical system uninterruptible power
supply (UPS) redundancy - Replacing static UPS system with a rotary hybrid
system - Eliminating chillers by using an outside air
economizer system with backup direct evaporative
cooling - Replacing the raised floor with a mezzanine deck
as the supporting structure for the IT equipment,
providing flexibility increased floor space and
potential for a future liquid cooling system - Using supply and return air plenums instead of
ducts - Pursuing a BREEAM-certified green building
- Using a 10-15,000 SF pod system to populate the
data center a fully-utilized pod at a time - Implementing hardware and software for measuring,
monitoring, and displaying energy use,
environmental variables, and server performance - Developing pricing systems based on client value,
and financially rewarding both EDS and the client
for efficiency and elimination of waste - Creating an EDS-internal incentive structure
(including metrics, measurement and incentives)
to drive positive economic change
14Design Workshop Results Texas Instruments
- Design concepts include
- Internally cooled tools with heat exchangers
designed to lose less pressure and temperature -
3,000-gallon-per-minute reduction in the size of
the central process cooling water system. - Nearly doubled-efficiency vacuum pumps, cut to
idle speed when waiting for wafers, saved 300
tons of chiller capacity (vacuum-pump vendors
have to design and supply new pumps) - saved a
fifth of internally cooled tools' cooling-water
flow. - Split chiller plant that cools water to two
different temperatures for different purposes
(further innovation might even eliminate one of
the two sections in the next fab). - Highly efficient fan filter units for air
recirculation prechilling incoming hot air with
outgoing cool air big pipes and small pumps to
cut friction and capital cost natural
daylighting and highly efficient lighting
fixtures in the office area solar water heating
a reflective roof and extensive water recycling
and reuse - Recovering heat and using high-pressure water
spray rather than steam for humidification,
reduced six boilers to just one plus a backup --
both of which will be off most of the year --
cutting emissions of nitrogen oxides by 60