COMPACT 200 RAPID REACTION BRIDGE SYSTEM

Description:

COMPACT 200 RAPID REACTION BRIDGE SYSTEM COMPACT 200 RAPID REACTION BRIDGE SYSTEM The design of the Mabey Compact 200 bridge allows the system to be used in a ... – PowerPoint PPT presentation

Number of Views:76
Avg rating:3.0/5.0
Slides: 10
Provided by: ValuedGate972
Learn more at: https://web.mst.edu
Category:

less

Transcript and Presenter's Notes

Title: COMPACT 200 RAPID REACTION BRIDGE SYSTEM


1
COMPACT 200 RAPID REACTION BRIDGE SYSTEM
2
(No Transcript)
3
COMPACT 200 RAPID REACTION BRIDGE SYSTEM The
design of the Mabey Compact 200 bridge allows the
system to be used in a logistic role throughout
the support area. As a Line of Communication
bridge it can carry loads of up to Class 110 over
gaps of up to 60m (200ft). The bridge is ideally
suited for areas where speed of deployment is
vital.
4
Rapid Construction The bridge is designed to be
built by hand. A 30m bridge can be assembled and
conventionally launched by 29 men in two or three
hours, depending on site conditions. Where cranes
or materials handling equipment is available, the
total number of man hours to assemble a bridge is
substantially reduced.
5
Launching Nose
Load Testing
6
(No Transcript)
7
B Co, 23rd Engr Bn replacing the Brcko Bridge
with the Compact 200 (MAR 96)
8
M2 Bailey Mabey Compact 200
MLC MLC 80(T) 70 (W) MLC 80 (T) 110 (W)
of Bays 13 13
Construction DT DS
of Panels 156 -- 2 ½ Sets of Bailey 52
of Transoms 66 14
Roadway Width 12 ft. 6 in (3.8m) 13 ft. 9 in. (4.2m)
Type of Deck Timber Steel
Total Weight 87 t 55 t
Based on the launch and erection of a 130ft
(39.62m) clear span, single lane bridge.
9
M2 Bailey Mabey Compact 200
of Bridging Sets Required 2 ½ Sets 1
Men Required 90 29
of Trucks Required At Least 15 PLS (7 PLS per Set) 11 PLS
of Crane Picks Required 222 66
HOURS REQUIRED 12-14 hours 8-9 hours
Based on the launch and erection of a 130ft
(39.62m) clear span, single lane bridge to carry
MLC80 (T). Note, the M2 Bailey is unable to
accommodate MLC 96 (W) Traffic.