Brief Synopsis of Project Hickahala Creek - PowerPoint PPT Presentation

About This Presentation
Title:

Brief Synopsis of Project Hickahala Creek

Description:

... Pipe Exposed on Overbank, Large Sand Splay in Farmers Field (top right) ... April 2003 Pipe is Vulnerable to Impact from the Next Large Floating Tree. – PowerPoint PPT presentation

Number of Views:292
Avg rating:3.0/5.0
Slides: 37
Provided by: deng3
Category:

less

Transcript and Presenter's Notes

Title: Brief Synopsis of Project Hickahala Creek


1
  • Brief Synopsis of ProjectHickahala Creek
  • Hickahala Creek Pipeline Protection Project at
    milepost 347.64
  • Tate County, Senatobia, MSDesigned by Submar,
    Inc and River Research and Design,
    Inc.Installed, Monitored bySubmar
    Incorporated 805 Dunn St., Houma,
    LAwww.R2D-ENG.com www.Submar.com
                                       

2

Hickahala Creek Pipeline Protection Project at
milepost 347.64 Tate County, Senatobia, MS
(Looking across and downstream in this view)
3
Looking Upstream - September 2001 - Pipeline
Exposed 10 Feet
4
Looking Upstream - September 2002 - Pipeline
Exposed 25 Feet
5
Looking Upstream - March 2003 - Pipeline Exposed
50 Feet
6
Looking Downstream - March 2003 - Pipeline
Exposed 50 FeetMain stream force thalweg of
stream aimed underneath exposed pipe note other
pipeline exposed.
7
Looking Upstream - March 2003 - Long Straight
ReachThornton Creek (tributary stream bottom
left) feeding into Hickahala Creek (top right)
8
Looking Upstream - April 2003 and the news is
not good"
9
Looking Upstream - the entire stream is trying to
flow underneath the pipeline
10
Looking Downstream (standing Upstream) - August
2003Typical Tourist on Safari in Mississippi
11
Note Pipe Tie-Down Structure
12
July 2003 After May Flood (overbank, picture
looking away from stream) Floodwaters Carry Sand
1000 Feet into Farmer's Field
13
August 2003 - Aerial Photos - Note Upstream
Straight Stretch (bottom right) Pipe Exposed on
Overbank, Large Sand Splay in Farmers Field (top
right)
14
Looking Downstream - April 2003 Pipe is
Vulnerable to Impact from the Next Large Floating
Tree. Bank is a mess (technical term)
15
September 5th, 2003 Portable Cofferdams used to
Dewater the site for Pipeline Recoating The
Green Portion of the Pipeline is New, Pipe was
Cut, and New Section Installed at a Lower
Elevation
16
Pre-tested Pipe
17
Hickahala Creek Conceptual Drawings - Total Mats
(182)
18
Looking Upstream into Tributary Widening Channel
to Accommodate LPSTP
19
The Key Trench is a Thing of Beauty!
20
From Key Looking Downstream in Tributary Toward
Hickahala Creek - September 17th, 2003 - Fresh
LPSTP
21
Looking Upstream into Tributary Longitudinal
Peaked Stone Toe Protection (LPSTP)
22
LPSTP Under Construction Looking Downstream -
September 17th, 2003
23
September 17th, 2003Mat Installation
24
September 17th, 2003Installing Mat
25
Looking Across and Upstream - September 22nd,
2003High Water Event During Construction
26
High Water Event During Construction September
22nd, 2003
27
September 26th, 2003 Note Bank Paving (left),
LPSTP (5 tons/ft middle), Key (right)
28
September 26th, 2003Note Bank Paving (left),
LPSPT (right)
29
September 27th, 2003 - Mat Installation Complete
30
Looking Upstream - September 30th
2003 Installation Complete
31
Project Completed
32
Looking Upstream - November 24th,
2003Floodwaters Crested 1 Foot Below Top of
Levee
33
Before
34
After
35
Looking Upstream - February 5th 2004 - Flood
36
February 5th, 2004 FloodFlow Left to Right
Write a Comment
User Comments (0)
About PowerShow.com