Title: Brief Synopsis of Project Hickahala Creek
1 - Brief Synopsis of ProjectHickahala Creek
- Hickahala Creek Pipeline Protection Project at
milepost 347.64 - Tate County, Senatobia, MSDesigned by Submar,
Inc and River Research and Design,
Inc.Installed, Monitored bySubmar
Incorporated 805 Dunn St., Houma,
LAwww.R2D-ENG.com www.Submar.com
2 Hickahala Creek Pipeline Protection Project at
milepost 347.64 Tate County, Senatobia, MS
(Looking across and downstream in this view)
3Looking Upstream - September 2001 - Pipeline
Exposed 10 Feet
4Looking Upstream - September 2002 - Pipeline
Exposed 25 Feet
5Looking Upstream - March 2003 - Pipeline Exposed
50 Feet
6Looking Downstream - March 2003 - Pipeline
Exposed 50 FeetMain stream force thalweg of
stream aimed underneath exposed pipe note other
pipeline exposed.
7Looking Upstream - March 2003 - Long Straight
ReachThornton Creek (tributary stream bottom
left) feeding into Hickahala Creek (top right)
8Looking Upstream - April 2003 and the news is
not good"
9Looking Upstream - the entire stream is trying to
flow underneath the pipeline
10Looking Downstream (standing Upstream) - August
2003Typical Tourist on Safari in Mississippi
11Note Pipe Tie-Down Structure
12July 2003 After May Flood (overbank, picture
looking away from stream) Floodwaters Carry Sand
1000 Feet into Farmer's Field
13August 2003 - Aerial Photos - Note Upstream
Straight Stretch (bottom right) Pipe Exposed on
Overbank, Large Sand Splay in Farmers Field (top
right)
14Looking Downstream - April 2003 Pipe is
Vulnerable to Impact from the Next Large Floating
Tree. Bank is a mess (technical term)
15September 5th, 2003 Portable Cofferdams used to
Dewater the site for Pipeline Recoating The
Green Portion of the Pipeline is New, Pipe was
Cut, and New Section Installed at a Lower
Elevation
16Pre-tested Pipe
17Hickahala Creek Conceptual Drawings - Total Mats
(182)
18Looking Upstream into Tributary Widening Channel
to Accommodate LPSTP
19The Key Trench is a Thing of Beauty!
20From Key Looking Downstream in Tributary Toward
Hickahala Creek - September 17th, 2003 - Fresh
LPSTP
21Looking Upstream into Tributary Longitudinal
Peaked Stone Toe Protection (LPSTP)
22LPSTP Under Construction Looking Downstream -
September 17th, 2003
23September 17th, 2003Mat Installation
24September 17th, 2003Installing Mat
25Looking Across and Upstream - September 22nd,
2003High Water Event During Construction
26High Water Event During Construction September
22nd, 2003
27September 26th, 2003 Note Bank Paving (left),
LPSTP (5 tons/ft middle), Key (right)
28September 26th, 2003Note Bank Paving (left),
LPSPT (right)
29September 27th, 2003 - Mat Installation Complete
30Looking Upstream - September 30th
2003 Installation Complete
31Project Completed
32Looking Upstream - November 24th,
2003Floodwaters Crested 1 Foot Below Top of
Levee
33Before
34After
35Looking Upstream - February 5th 2004 - Flood
36February 5th, 2004 FloodFlow Left to Right