SAACE Membership survey June 1998 - PowerPoint PPT Presentation

About This Presentation
Title:

SAACE Membership survey June 1998

Description:

Welcome to CESA Presentation: Best Practice Guideline - Procurement of Consulting Engineering Services THE WORLD WITHOUT ENGINEERS THE WORLD WITHOUT ENGINEERS ... – PowerPoint PPT presentation

Number of Views:207
Avg rating:3.0/5.0
Slides: 115
Provided by: bif6
Category:

less

Transcript and Presenter's Notes

Title: SAACE Membership survey June 1998


1
Welcome to CESA Presentation Best Practice
Guideline - Procurement of Consulting Engineering
Services

2
  • Introduction
  • Background
  • The seminar is a culmination of the CE
    Procurement Indaba conducted under the banner of
    CESA during Feb 2008.
  • A task team was established to draft a
    simplified step-by-step Best Practice Guideline
    Manual for Procurement Consulting Engineering
    Services.
  • To be rolled-out to all the twelve regions of
    CESA.
  • George - marks the 11th roll-out, where the
    manual is being launched.
  • The manual was drawn up in collaboration with
    the CIDB, (many thanks to CEO Programme
    Manager Procurement and Delivery).

3
  • Introduction (contd)
  • Objectives
  • To inform and capacitate clients and consulting
    engineers (trusted/ independent advisor / agent
    of client) with best practice in procurement
  • Enable CEs to appropriately respond to calls for
    consulting engineering services and to deliver
    these services in a true valueadded context
  • To assist both Client and CE to better understand
    and implement the requirements of procurement
    contracts ito CIDB Treasury legislation
  • To provide CEs and clients a platform to make
    suggestions to the best practice procurement
    guideline manual (living document), which will be
    updated regularly to reflect the challenges faced
    by our industry.
  • Manual is available on http//www.cesa.co.za/ 
    at no charge.
  • Comments to wallym_at_cesa.co.za

4
  • Introduction (contd)
  • Outline of the CESA Guide/Briefing

Chapter 1.   Project Life-cycle background of typical project life cycle
Chapter 2.   Consulting Services - typical CES provided by CEs
Chapter 3.   Procurement of Consulting Services - legislation and objectives
Chapter 4.   Scope - expanded description of elements of scope
Chapter 5.   Tender Documentation for CES - preparing tenders for CES
Chapter 6.   Value Added Services value of additional CES
Chapter 7.   Evaluation of tenders - Guidelines on evaluation of CES tenders
Chapter 8. Performance monitoring Suggested framework for CPE.
5
  • The technical briefings are geared towards
    creating a conducive sustainable procurement
    environment  to enhanced infrastructure delivery.
  • Ensure that the right firm(s) are appointed for
    the right job
  • Appointment at a reasonable level of
    compensation
  • ensure continued existence and development of
    firm(s) and industry
  • serve the best interests of public
  • Hence the theme of our Technical Briefing today
    is, Walking together towards a Sustainable
    Procurement Environment.

Introduction Re-cap
6
Right firm for the right job
Example right firm for the right job Three
relatively easy questions for a House Bridge
Consulting Engineer Question 1   How much
does a house weigh? Question 2 How much
weight can a rural two-lane bridge Hold???
7
Qualified firm for the right job
otherwise house becomes a bridge
8
Competent firm for the right job
a bridge that cannot be used
9
Appropriate Consultant for the right job
a house that cannot be used
10
Right firm for the right job
And Question 3 Would this be covered by
PI, Home insurance, car insurance, or, does
it come under the roadside accident fund
??? ----------------------------------------------
--------------------------------------------------
----------------
We can all relate to this, e.g. 40 000 defective RDP houses to be flattened and rebuilt at a cost gt R1-billion.
                             
delivers questions rather than intended
product
11
Right firm for the right job
We can relate to this R4 million bridge swallows
a taxi!
                             
delivers questions rather than intended
product
12
(No Transcript)
13
  • SESSION 1
  • 1.1 Consulting Engineers South Africa
  • 1.2 Consulting Engineering Industry
  • 1.3 The Foothold Definitions
  • 1.4 The Project Life-Cycle
  • 1.5 Overview of Consulting Services

14
  • 1.1 Consulting Engineers South Africa

15
  • CONSULTING ENGINEERS SOUTH AFRICA (CESA)
  • History
  • SA Association of Consulting Engineers (SAACE)
    established in 1952
  • Voluntary association of independent CEs in
    private practice
  • August 2008 - SAACE transformed to CESA
  • Employing more than 22 000 people
  • Members interests
  • CESA seeks to promote interests of Members and
    Clients by
  • Regular liaison meetings
  • Publication of documents relating to profession
  • Compiling Advisory Notes for Members and
    Clients
  • Guidelines to Members on professional practice
    matters

16
  • CONSULTING ENGINEERS SOUTH AFRICA (continued)
  • Professionalism and Integrity of Members
  • 1. In general
  • ECSA registers professional individual
    engineers, technologists etc
  • CESA registersprofessional CE Firms through
    membership
  • 2. Credibility of applicants
  • In business gt 12 months
  • Nominated by an existing CESA member
  • CIPRO registered - bona fides, directors
    governance structures
  • Not fly-by night
  • 3. Ongoing requirements
  • Subject to CESA Code of Conduct gives Clients
    recourse
  • Disciplinary Committee - non-compliance 
  • Ownership/principals gt 50 Pr Engrs/Technos
    engineering focus
  • No contracting work (construction) - no
    conflict of interest

17
  • 1.2 Consulting Engineering Industry
  • Consulting Engineering Industry Overview
  • Construction Industry - Enabler Regulator

18

Consulting Engineering Industry Overview
19
  • THE CONSULTING ENGINEERING INDUSTRY
  • The birth
  • The word engineer first appeared in the 15th
    Century, in
  • reference to a particular group of
    professionals in the military
  • Associations formed to exchange experiences and
    to improve
  • the status of engineers
  • It was then legalised to safeguard the health
    and welfare of the
  • general public
  • The licensing procedures were intended to stop
    people from
  • selling engineering services when they were not
    trained or
  • qualified in the practice of engineering.

20
  • THE CONSULTING ENGINEERING INDUSTRY (continued)
  • The present
  • Take-over of engineering services by the
    un-qualified
  • (e.g. Tenderpreneurs, tender syndicate, etc)
  • Due to tendering process
  • Which disregard engineering ability/technical
    competence of CE

21
  • THE CONSULTING ENGINEERING INDUSTRY (continued)
  • The future
  • Competitive tendering is here to stay
  • it must not be used to drive professional fees
    down
  • The struggle continues professionalism,
    reservation of
  • engineering work and use of appropriate
    procurement methods
  • FIDIC Report Engineering Our Future

Change is upon us there is no future in the
status quo industry must adapt. --- Firms must
grow in capability and scope of services to meet
the client demands. We must move up the food
chain to a new set of value-added services for
our clients.
22
THE WORLD WITHOUT ENGINEERS
23
THE WORLD WITHOUT ENGINEERS
24
The Construction Industry Enabler and Regulator
25
  • The Construction Industry Development Board
    (CIDB)
  • Established by and gets its mandate from the CIDB
    Act (38 of 2000)
  • Aims
  • Promote sustainable growth of the construction
    industry and sustainable participation of the
    emerging sector in the industry
  • Promote improved performance and best practice
    of public and private sector clients, contractors
    and other participants
  • Promote procurement and delivery management,
    the uniform application of policy throughout all
    spheres of government, uniform and ethical
    standards all guided by a Code of Conduct
  • Establish registers as a tool to systematically
    regulate and monitor the performance of the
    industry and its stakeholders
  • Register of Contractors(RoC)
  • Register of Projects (RoP)
  • Register of Professional Service Providers
    (RoPSP)

26
  • CIDB (continued)
  • Register of Professional Service Providers
    (RoPSP)

27
  • CIDB (continued)
  • CIDB documentation/prescripts (www.cidb.org.za)
  • Standard of Uniformity (SFU)
  • Code of Conduct
  • Practice notes
  • Legislation
  • Code of Conduct establishes certain standards of
    behaviour
  • Behave equitably, honestly and transparently.
  • Discharge duties and obligations timeously and
    with integrity.
  • Comply with all applicable legislation and
    associated regulations
  • Satisfy all requirements established in
    procurement documents
  • Avoid conflict of interest

28
  • CIB (continued)
  • Monitoring role - CIDB can
  • Conduct investigations
  • Sanction offenders
  • Suspend offenders from the CIDB RoC
  • Issue fines to Employers up to R100 000
  • Intergovernmental Relations Framework Act
    liaises with
  • Treasury
  • Public Protector
  • Auditor General
  • CESA/ CIDB Collaboration
  • CESA consulted extensively with CIDB in compiling
    the Manual/Guide for Procurement of CES because
    CIDB
  • Regulates public sector procurement (large CESA
    Client base)
  • Complies with applicable legislation/
    regulations
  • Authority to enforce compliance
  • Good working relationship

29
  • 1.3 The Foothold Definitions

30
  • THE FOOTHOLD DEFINITIONS
  • Conformity of Terminology
  • Terminology in Manual conforms with CIDB
    documentation and
  • ECSA Guideline Scope of Services and Tariff of
    Fees
  • Mainly aligned with CIDBs Revised SFU in
    Construction Procurement
  • Noteworthy Examples
  • Bid Tender
  • Client he/she who engages the Consulting
    Engineer (CE)
  • Construction Monitoring (administration of
    Construction Contract for
  • verification only) new term
  • Contract Agreement between Client and CE

31
  • Noteworthy Examples (contd)
  • Engineering and Construction Works contract
    includes construction,
  • repair, maintenance, alteration, demolition
    etc of building and
  • engineering infrastructures
  • Normal Services Typical services as in ECSA
    guideline tariffs
  • Quality Totality of features of a service
    that bears on its ability to
  • satisfy stated or implied needs
  • Scope of Services Services undertaken by the
    CE in relation to the
  • Scope of Work
  • Scope of Work Portion of the Works for which
    the CE is engaged
  • Tender Price Price submitted including all
    payment conditions, costs
  • and disbursements

32
  • 1.4 The Project Life Cycle

33
(No Transcript)
34
  • THE PROJECT LIFE CYCLE (contd)
  • Steps 1 to 3 Identification, Definition,
    Feasibility
  • Identifying the potential project often by
    Owner, Specialist assistance
  • And Defining the best project to meet the need
  • Reject unsuitable solutions, shortlist suitable
    alternatives
  • Select the best project, based on technical and
    financial feasibility
  • Steps 4, 5, 6 Concept Viability, Design,
    Procure
  • Developing the project through all concept and
    viability stages, confirm viability
  • Detail design of the project to procure
    construction
  • Design can be a maintenance/operation assignment
  • Procuring a contractor to construct proper
    tender/contract documents, proper evaluation of
    tenders

35
  • THE PROJECT LIFE CYCLE (contd)
  • Steps 7, 8 Construct, Operate and Maintain
  • Construction - from site handover to when Owner
    takes possession of the constructed project
  • Final handover after Defects Liability Period
    expired and defects rectified
  • Operation and Maintenance
  • Usually by Owner - According to manuals and own
    procedures
  • O M - May be contracted out
  • Note CE may be appointed for any one, or all,
    of the steps 1 to 8

36
  • 1.5 Overview of Consulting engineering
  • services

37
CONSULTING ENGINEERING SERVICES
  • Consulting engineering services include many
    Engineering Disciplines inter alia
  • Agricultural
  • Civil
  • Construction Management
  • Construction Project Management
  • Electrical
  • Geotechnical
  • Mechanical
  • Structural
  • Transportation
  • Specialist Engineering Services

38
  • CONSULTING ENGINEERING SERVICES (contd)
  • Deliver Value
  • 1. Early project stages
  • Services deliver most value
  • Functionality quality of the proposed service
    more important than Cost (Steps 1 to 3)
  • 2. After project is well defined
  • Services are easier to determine
  • Role of high level expertise reduces as project
    develops
  • Efficient more routine tasks more important
  • Correct/comprehensive contract documentation is
    vital

39
REQUIRED EXPERTISE OVER THE PROJECT CYCLE
40
(No Transcript)
41
  • SESSION 2
  • 2.1 How to Procure Engineering Services

42
HOW TO PROCURE CONSULTING SERVICES
  • Procurement Tendering

43
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Important that Government recognises
  • CEs are an important pool of expertise and
    skilled resources
  • High standard of engineering and Infrastructure
    development vital for growth
  • National Treasury policy statements
  • It is necessary that certain minimum standards
    of quality and efficiency be achieved when
    appointing consultants
  • Need to maintain a basic policy of competitive
    selection
  • Legal Environment for consulting engineering
    services
  • Constitution of South Africa
  • System is to be Fair, Equitable, Transparent,
    Competitive, Cost effective
  • Adopted by ISO in ISO 10845 series for
    construction procurement

44
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • TABLE PILLARS OF PROCUREMENT

45
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Procurement - Need to maintain a reasonable
    Balance between Competition Compensation

46
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Primary Legislation Regulating Procurement

Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective
Fair, Transparent, Competitive, Cost Effective Fair, Transparent, Competitive, Cost Effective Fair, Transparent, Competitive, Cost Effective Equitable Equitable
Public Finance Management Act (Act No. 1 of 1999) Municipal Finance Management Act (Act No. 56 of 2003) Construction Industry Development Board Act (Act No. 38 of 2000) Preferential Procurement Policy Framework Act (Act No. 5 of 2000) Broad Based Black Economic Empowerment Act (Act No. 53 of 2004)
PFMA MFMA CIDB PPPFA BBBEE
Public Sector Clients Public Sector Clients Public and Private Sector Clients Public Sector Clients Public and Private Sector Clients
Point to Note Compliance with CIDBs Standard
for Uniformity in Construction
Procurement (SFU) compulsory for organs of
state
Refer to Table 3.2 (pg 11-12) in Manual - 10 Acts)
47
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Objectives of Procurement
  • Procurement is engaging skilled professionals
    not purchase of a
  • commodity
  • Purpose of competitiveness is to ensure long
    term value for money not
  • short term low cost design
  • Transparency must encourage professionals to
    develop maintain
  • their skills and expertise
  • CIDB Guidelines can provide the necessary
    results
  • Methods of Procurement
  • 1. Financial Offer
  • 2. Financial Offer plus
    Preference
  • 3. Financial Offer plus Quality
    (Functionality)
  • 4. Financial Offer plus Quality
    plus Preference
  • Prescribed by CIDB Standard for Uniformity
    (SFU)
  • Services must provide cost-effective
    value-added performance

48
 
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • CESA Recommends - Method 4
  • Quality and Cost-based Selection (QCBS)
  • Accords with CIDBs SFU (Standard for Uniformity)
  • Based on CIDBs Best Practice Guidelines for
    Competitive Selection
  • CIDB states - Method 4 applies in all but small
    minority of cases
  • Method 4 is MANDATORY for public bodies
  • However,
  • the KwaZulu Natal High Court, Pietermaritzburg,
    case no 10878/2009 relegates functionality/
    Quality to a pre-qualification criteria(using a
    minimum threshold). Thus rendering Method 4 to
    be invalid.

49
HOW TO PROCURE CONSULTING SERVICES (Contd)
Competitive Selection Procedures
50
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Points to Note
  • 1. Quoting from CIDB Best Practice Guideline A7 -
    Procurement of professional services should be
    undertaken on
  • demonstrated competence qualifications (for
    type of services required)
  • capacity capability (to provide the quality
    of the service)
  • fair reasonable Financial Offers (not only
    least cost)
  • 2. Constitution requires procurement to be cost
    effective have best value outcomes in terms of
  • quality,
  • downstream life cycle costs,
  • timing
  • Financial Offer
  • least resources to effectively manage control
    the procurement process.
  • 3. Selection on basis of quality does not
    necessarily mean the best quality available but
    quality appropriate for the assignment.

51
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • Points to Note (contd)
  • 4. Calling for/ preparation of Tenders
  • Scope of Work and Services (SOWS)
  • fully describe SOWS - comparable tenders are
    received
  • fully describe SOWS - reduce time effort for
    tender preparation
  • Total Input Cost
  • can be considerable - small projects can be gt
    potential fee jeopardise
  • finances of the service provider
  • overall economy of the project.
  • Guideline
  • CEs potential fee should be 20 times gt cost of
    preparing tender
  • alternatively, cost to prepare tender should
    not gt 5 of potential CE fee
  • potential CE fee has to cover - Staff costs,
    overheads, expenses and profit
  • hence tenders should not be solicited for small
    projects,

52
HOW TO PROCURE CONSULTING SERVICES (Contd)
  • 4. Calling for/ preparation of Tenders (contd)
  • The following procedure should preferably adopted
    by client or CE (as agent of client)
  • Consider grouping small projects together
  • Request proposals for term contracts - where
    consulting engineer can support the client on a
    partnership basis for all small to medium
    projects over a longer period
  • Listing manuals and procedures as requirements
    so lengthy technical proposals are not required
    (only proposed staffing track record)

53
(No Transcript)
54
  • SESSION 3
  • 3.1 Scope of Services
  • 3.2 Tender Documentation for Consulting
  • Services

55
  • 3.1 Scope of Services

56
SCOPE OF SERVICES
  • Definition
  • Scope of Services Services which a CE must
    provide in relation to scope of Work
  • MUST be clearly defined to ensure proper pricing
    and clear and unambiguous understanding by
    tenderer
  • In many instances this is lacking uncertainty
    and unrealistic pricing result
  • Recommended listing DELIVERABLES to be produced
    by the CE, i.e. products of his work (studies,
    reports, designs, drawings, documents etc)

57
SCOPE OF SERVICES (contd)
  • Planning Studies, Investigations and Assessments
  • (i) Consultation with the client or clients
    authorized representative.
  • (ii) Inspection of the site of the project.
  • (iii) Preliminary investigation, route location,
    planning and a level of design
  • appropriate to allow decisions on
    feasibility.
  • (iv) Consultation with authorities having rights
    or powers of sanction as well
  • as consultation with the public and
    stakeholder groups.
  • (v) Advice to the client as to regulatory and
    statutory requirements, including
  • environmental management and the need for
    surveys, analyses, tests and
  • site or other investigations, as well as
    approvals, where such are required
  • for the completion of the report, and
    arranging for these to be carried out
  • at the clients expense.
  • (vi) Searching for, obtaining, investigating and
    collating available data,
  • drawings and plans relating to the works.
  • (vii) Investigating financial and economic
    implications relating to the
  • proposals or feasibility studies.

58
SCOPE OF SERVICES (contd)
  • Scope of Services Stages for a Typical Project

59
SCOPE OF SERVICES (contd)
  • Detailed examples (Appendix A)
  • Refer to Appendix A, Numerous Normal Services
    tasks under Stages 1 to 6
  • Includes Activities/Deliverables
  • Recommended as a reference or checklist per stage
  • Principal Consultant
  • Refer to Appendix A, Additional Services to
    Normal Services
  • Includes Activities/Deliverables
  • Recommended as a reference or checklist per stage

60
SCOPE OF SERVICES (contd)
  • Key Factors common to every scope, in Developing
    the Scope of Services
  • Obligations of the Parties
  • Health and Safety
  • Sustainability
  • Information Available
  • Scope MUST reflect Clients intentions to enable
    tenderers to identify tasks and estimate times to
    be spent by personnel, and hence to quantify and
    price the tender
  • Failure to prepare Scope of Services in
    sufficient detail
  • Tenderer has to make assumptions
  • Misinterpret Clients requirements
  • Price unnecessarily for Risks
  • Resultant prices too low or too high
  • Fails the interests of Client, Consulting
    Engineer and Project

61
SCOPE OF SERVICES (contd)
Key Factors in Developing Scope Services - TABLE
62
THE SCOPE OF WORK
  • Definition
  • Not the same as Scope of Services of the
    Consulting Engineer
  • Scope of Work portion of the Works for which
    the Consulting Engineer is engaged or the
    document which specifies and describes the
    supplies, services engineering and construction
    works to be provided (by the Contractor)
    including special requirements, constraints etc.
  • Example
  • A client wishing to construct a Casino complex
    consisting of three distinct components being the
    Building, a Parking Area and an access road, may
    appoint a consulting engineer to undertake Stages
    3-6 of the normal engineering services for the
    Parking Area. In this case the scope of services
    can be defined as set out in Appendix A while the
    scope of work may only involve the Parking Area.
    Some thought will have to go into preparing the
    scope of work as it interfaces with other works
    such as stormwater runoff from the building and
    the interface with the access road and gate
    house.

63
THE SCOPE OF WORK (contd)
  • Points to Note
  • The scope of work for each service provider
    should be carefully
  • determined to ensure that no overlaps and
    duplication in terms of scope of work exist.
  • In some cases the consulting engineer will be
    required to
  • appoint specialist sub-consultants in which case
    the consulting engineer will ensure that no
    duplication in terms of scope occurs.

64
THE SCOPE OF WORK (contd)
  • Examples of Scope of Work

65
THE SCOPE OF WORK (contd)
  • Examples of Scope of Work (contd)

66
  • 3.2 Tender Documentation for Consulting
  • Services

67
TENDER DOCUMENTATION
  • Purpose
  • In line with principles and documentation of the
    CIDB
  • To achieve uniformity, in interests of a more
    efficient industry
  • Model for Uniformity
  • CIDBs Construction Procurement Toolbox
  • Process of Offer and Acceptance
  • Tenderers provide inputs to complete their
    submissions (offers)
  • These inputs to the contract to be concluded
    after acceptance of offer
  • Separation of component documents
  • Complete enquiry documentation critical to
    projects success
  • CIDB tables to assist compiling documentation
    See Appendix B

68
TENDER DOCUMENTATION contd
  • Documents relating to the Tender

69
TENDER DOCUMENTATION contd
  • Documents relating to the Form of Agreement

70
  • TENDER DOCUMENTATION (contd)
  • Standard Coloured Pages/Dividers
  • T1.1 Tender Notice and Invitation to
    Tender White
  • T1.2 Tender Data Pink
  • T2.1 List of Returnable Documents Yellow
  • T2.2 Returnable Schedules Yellow
  • C1.1 Form of Offer and Acceptance Yellow
  • C1.2 Contract Data Yellow
  • C1.3 Form of Guarantee/Securities White
  • C1.4 Adjudicators contract White

71
  • TENDER DOCUMENTATION (contd)
  • References
  • Revised Standard for Uniformity in Construction
    Procurement (SFU)
  • CIDB Construction Procurement Best Practice
    Guideline C3 Adjudication
  • CIDB Professional Services Contract
  • PROCSA Form of Agreement
  • FIDIC Client/ Consultant Model Services Agreement
  • Standard Professional Services Contract by NEC

72
(No Transcript)
73
  • SESSION 4
  • 4.1 Value-added Services

74
  • VALUE ADDED SERVICES
  • Value, Financial Offer, Quality
  • Acceptance of lowest price denies opportunity to
    assess value
  • Consulting Engineers are accustomed to tendering
    competitively
  • Professional services, unlike products, are not
    well defined
  • Requires careful descriptions in Scope of
    Services, Scope of Work
  • Still a tendency to rely on price, ignore quality
    (Treasury Functionality)
  • Remuneration should reward desirable performance
  • What performance is achieved from the lowest
    price? (examples..)
  • Life-cycle costs Eng. 2, Constr. 18, OM 80
    (2 dictates 98 !)
  • Financial offers should reflect effort to
    optimise costs of project
  •  Relationship between Financial Offer Quality
    (Effort) is not linear

75
VALUE ADDED SERVICES
76
VALUE ADDED SERVICES contd
  • Life-Cycle Cost and impact on Project Success
  • The procurement of consulting engineering
    services has the greatest impact on the
    life-cycle cost of the project, yet it is the
    least costly component
  • Life-Cycle Cost
  • Impact on Project Success
  • Engineering
    Construction Operations
    Maintenance

10
50
40
60
20
20
77
VALUE ADDED SERVICES contd
  • The Concept of Value
  • Value should
  • secure for the client value-for-money services
  • achieve minimum life-cycle costs (long term value
    for money)
  • Ensure the project will fulfill its intended
    purpose
  • The tender process must allow the tenderer to
    show that
  • value-for-money services are offered
  • minimum life-cycle costs are critical to the
    projects success
  • The Financial Offer will demonstrate the value of
    inputs offered
  • Take Clients quality evaluation criteria into
    account
  • Quantifying Value
  • Needs to be a factor in considering tenders
  • Include in determination of tender score
  • Assess Preference, Quality, and Financial Offer
    (Price) individually
  • Consulting Engineer to tender accordingly

78
VALUE ADDED SERVICES contd
  • Guidelines for Pricing of Tenders the Golden
    Rules
  • Project success relies on acceptance by client
    of the Consulting Engineers financial offer and
    conditions
  • Consulting Engineer needs to have his interests
    protected
  • Client needs to be comfortable with contract
    financial arrangements
  • Golden Rules apply to preparation of the
    financial offer
  • Golden Rule No. 1 Know the project requirements
  • No two projects the same offer
  • Must be a clear and unambiguous Scope clarify
    if necessary
  • Determine methodology, inc. innovation,
    value-adding procedures
  • Take Clients quality evaluation criteria into
    account

79
  • ILLUSTRATION OF TOTAL COSTS
  • Golden Rule No.2 Know your costs involved

80
  • VALUE ADDED SERVICES (contd)
  • Golden Rule No. 3 Know the Clients situation
  • Able to produce and adhere to a clear and
    sufficient scope
  • Ability to fund or timeously secure funding for
    the project
  • Adequate resources to administer the contract
  • History of fees paid on time
  • Sufficient technical capability for reviews and
    approvals
  • Need for development (training, mentoring, etc)
  • Experience in using consulting engineering
    services
  • Able to responsibly evaluate award
    consulting/construction contracts
  • Finalising the Tender Price
  • Feedback from Golden Rule No 3 is to be
    considered where aspects within Clients ambit
    must be examined, for influence on level of the
    financial offer

81
  • VALUE ADDED SERVICES (contd)
  • Adjustments from Golden Rule No 3
  • Profit mark up
  • Pricing for contingencies or risk
  • Pricing work not called for but necessary (if not
    done by Client)
  • Pricing for unrealistically tight or slack
    deadlines
  • Pricing for work assumed but not required
  • Adding a margin in lieu of qualifying the tender
  • Provision for productivity delays to be expected
    in executing the work for the client
  • Price Benchmarks
  • Important to test pricing against a norm and
    indicate adequacy of price
  • Appropriate Benchmark ECSA Guideline Tariff of
    Fees
  • Percentage of Project Cost (sliding scale) x
    Factor for Stage and Type
  • Also ECSA recommended hourly rates arrive at
    Benchmark Fee
  • Adjust up or down for project concerned, with a
    Benchmark Multiplier, to get an Adjusted
    Benchmark Fee considering specific circumstances

82
VALUE ADDED SERVICES contd
  • Benchmark Multipliers
  • Specific circumstances
  • Is scope complete and clear?
  • Is Client well versed in procuring consulting
    services?
  • Does Client have adequate resources for competent
    tender evaluation?
  • Does Consulting Engineer have a successful
    project record with the Client?

Multiplier Circumstances
0.6 1.0 Favourable
1.0 Normal or Reasonable
1.0 1.6 Negative
83
VALUE ADDED SERVICES contd
  • Specific circumstances (contd)
  • Is project location advantageous for the
    Consulting Engineer?
  • Will the risks perceived be easy or difficult to
    handle?
  • Is level of complexity of the project normal or
    will it be very complex?
  • Will the risks perceived be easy or difficult to
    handle?
  • Is level of complexity of the project normal or
    will it be very complex?
  • Does the Consulting Engineer have a low order
    book and need the work?
  • Will start date and duration require price
    adjustment, if no escalation?

84
VALUE ADDED SERVICES contd
Specific circumstances Benchmark Multipliers Benchmark Multipliers Benchmark Multipliers
Favourable (0.6 1.0)/ Reasonable ( 1.0) / Negative (1.0 1.6) F R N
Is scope complete and clear? 1.0
Informed client 0.9
Previous appointments 1.2
Savings Previous experience 0.6
Project location 1.0
Staff cost, suited competent 0.8
risks perceived be easy or difficult to handle? 1.3
level of complexity of the project normal or will it be very complex? 1.0
Does the Consulting Engineer have a low order book and need the work? 0.7
AVERAGE ( this example) 0.94 0.94 0.94
85
VALUE ADDED SERVICES conclusion(1)
  • Adjusted Benchmark (Yardstick) Fee
  • Average of the sum of all the particular fees
    used
  • Still based of ECSA recommended fee scales
  • THERE IS NO SUCH THING AS A DISCOUNTED FEE

86
VALUE ADDED SERVICES conclusion(2)
87
(No Transcript)
88
  • SESSION 5
  • 5.1 Evaluation of Tenders

89
  • EVALUATION OF TENDERS 
  • References
  • CIDB Best Practice Guideline No. A4 Evaluating
    Quality in Tender Submissions (guidelines)
  • CIDB Inform Practice Note No. 9 Evaluation of
    Quality in tender Submissions (overview)
  • Evaluation of Tenders
  • Applies where Quality consideration is an
    essential part of the evaluation process which
    should apply to the vast majority of tenders for
    Consulting Engineering services
  • Procurement Method 4 generally appropriate for
    Consulting Engineering services (Quality and
    Cost-Based Selection)

90
  • EVALUATION OF TENDERS 
  • Method 4 Financial Offer plus Quality plus
    Preference
  • Score Quality, rejecting all offers that fail to
    score minimum points for Quality, stated in
    Tender Data
  • Score tender evaluation points for Financial
    Offer
  • Confirm tenders eligible for preferences claimed
    and if so score tender evaluation points for
    preferencing
  • Calculate total tender points
  • Rank tenders from highest number of tender
    evaluation points to lowest
  • Recommend Tender with highest tender evaluation
    points for award, unless compelling reasons not
    to do so

91
  • EVALUATION OF TENDERS (contd)
  • Evaluation criteria
  • Essential that tender documents state evaluation
    criteria and scoring systems to be used in tender
    adjudication
  • If a criterion is stated, clarity required how
    the criterion will be adjudicated and weighted,
    relative to other criteria
  • CIDB Standard for Uniformity Sect. 4.4.3 calls
    for specific Tender Data
  • Method to be used in evaluation
  • Weighting between Financial Offer (W1), Quality
    (W2), and Preference (W3)
  • Quantified descriptions of preferences incl. how
    granted and scored
  • (Refer also to Construction Scorecard
    (Construction Sector Charter, Govt Gazette Board
    Notice 862 of 2009)
  • Details of Quality Criteria and Sub-criteria and
    manner of scoring

92
  • EVALUATION OF TENDERS (contd)
  • Recommended Approach, to be Fair, Equitable,
    Transparent, Cost-effective
  • Quality of outputs/deliverables to satisfy client
    requirements
  • Service with reasonable skill and care of
    professionals
  • Advice independent of any affiliation causing
    conflict of interest
  • Repeat/straight forward projects
    Cost-effective design important
  • Feasibilities, Complex projects experience,
    expertise important
  • Weighting, Quality / Financial Offer is less for
    repeat type projects
  • All tenders to have a minimum number of Quality
    points, to proceed
  • Ratio Quality / Financial Offer plus Preferences
    depends on project value
  • Preferential Procurement Framework Act
  • Assignments under R500k value, Ratio 8020
    mandatory
  • For higher value assignments, Ratio 9010
    mandatory
  • (Threshold as in Pref. Procurement Policy
    Framework Act Regs)
  • Refer Tables based on CIDB references with
    certain CESA adjustments, pertaining to Scoring
    against Ratings

93
  • EVALUATION OF TENDERS (contd)
  • Recommended Detail Procedure
  •  
  • Score Quality with 3 Quality reviewers, adjust if
    major scoring differences
  • Reject tenders not attaining minimum Quality
    score, inform them in writing
  • Inform tenderers of time date for opening
    Financial Offers and announce these at the
    meeting
  • Calculate Final Evaluation Scores according to
    CIDB Standards for Uniformity
  • Apply Definitions and formulae (see next slide)
  • Mutually exclusive criteria recommended, to limit
    duplication
  • Black persons are addressed in allocating
    Preferences
  • Reviewers need to be experienced. If not
    available in the Client, then specialists or
    Consulting Engineers (unconnected with the
    tender) should be retained by the Client to
    assist with evaluations
  • See recommended Tables and Examples

94
  • EVALUATION OF TENDERS (contd)
  • Definitions and formulae used
  • Nev Total evaluated score
  • Nm Score for Price
  • Nq Score for Quality
  • Np Score for Preferencing
  • W1 Weight assigned to price
  • W2 Weight assigned to quality
  • Nm W1 x Pm/P where Pm is lowest qualified
    tender price received and P is tender price under
    consideration (2 decimal places)
  • Nq W2 x S/Ms - where Ms is maximum possible
    quality score and where S is quality score for
    tender under consideration
  • Nev Nm Nq Np - Tenders ranked from highest
    to lowest Nev with
  • tender awarded to tenderer with highest Nev

95
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
  • Table 7-1 Nature of Projects (5 types are
    defined)
  • Feasibility Studies and Investigations (require
    specialised skills deliverable a report)
  • Innovative Projects (require innovation,
    creativity, expertise and skills specialist
    advice needed is often identified in the project)
  • Complex Projects (require high level of technical
    skills and resources may require skills other
    than normal engineering)
  • Straightforward Projects (comprise straight
    forward tasks with standard technologies may
    need strong capacity and resources if project is
    large)
  • Repeat Projects (Straightforward tasks with
    routine/periodic activities, eg maintenance to
    maintain Clients assets
  • The Descriptions of each type show that the
    tenderers experience and
  • capability are key, particularly in types 1 to 4

96
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
    (contd)
  • Table 7-2 Quality Criteria and Points Scale for
    small projects
  • Quality plus Financial Offer/Preference ratio
    8020 (i.e.. 20 points for BBBEE)
  • Maximum points shown for 5 Project Types from
    Table 7-1 for BBBEE, Quality and Financial Offer,
    Financial Offer and Quality
  • Higher points used for Quality in more complex
    projects and lower points for Financial Offer
  • 9 Quality Criteria listed, from Adequacy of work
    plan to Demonstrable managerial ability
  • Quality maximum points from (2) allocated to 9
    Quality criteria allocation to 5 of the 9
    Quality Criteria should suffice

97
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
    (contd)
  • Table 7-3 Quality Criteria and Points Scale for
    large projects
  • Quality plus Financial Offer/Preference ratio
    9010 (i.e.. 10 points for BBBEE)
  • Maximum points shown for 5 Project Types from
    Table 7-1 for BBBEE, Quality and Financial Offer,
    Financial Offer and Quality
  • Higher points used for Quality in more complex
    projects and lower points for Financial Offer
  • 9 Quality Criteria listed, from Adequacy of work
    plan to Demonstrable managerial ability
  • Quality maximum points from (2) allocated to 9
    Quality criteria allocation to 5 of the 9
    Quality Criteria should suffice
  • Operation similar to Table 7-2

98
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
    (contd)
  • Table 7-4 Indicators to be used when scoring
    tenderers on Quality Criteria
  • Ratings, very good/good/satisfactory/poor
    (100/70/50/0) with descriptors, listed for 9 x
    Quality Criteria
  • Note poor scores zero criteria are
    unacceptable for Consulting Engineering services
    (see descriptors)
  • Ratings for 9x Quality Criteria are common to all
    Project types

99
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
    (contd)
  • Table 7-5 refers to Qualification and Competence
    of Key Staff
  • To be completed by Client when issuing tenders
  • Shows 6 x typical staff posts Project Leader,
    Design Engineer, Materials Engineer, Contracts
    Engineer, Resident Engineer and Assistant
    Resident Engineer
  • Shows 5 x Project types (Table 7-1) for each post
  • Lists 6 x attributes for each post
    (qualification, experience thereafter ,
    registration, experience thereafter, involvement
    on comparable projects (past 10 years), project
    values (past 6 years)
  • Client able to list preferred and minimum
    attributes, Tenderer fills in the Offer column
  • Although Titles of Job posts state Engineer,
    Client may choose to use Registered Engineering
    Technologist or Registered Engineering
    Technician, depending on nature of project

100
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
    (contd)
  • Table 7-6 Assessment example
  • Shows a worked example for a complex project in
    the 9010 points system range with 5 of 9 x
    Quality Criteria addressed
  • Weight assigned to each Quality Criterion
    addressed. Total maximum points for Quality
  • Rating indicators from Table 7-4 applied to each
    Quality Criterion by 3 reviewers to give
    Reviewers scores and average scores
  • Weights applied to average scores to give points
    for Quality, with total Points for Quality for
    tender under consideration
  • Table shows 2 x sets of points for Quality
    results 1st set 2 outliers, 2nd set no
    outliers, after a repeat review by the reviewers

101
  • RECOMMENDED TABLES FOR EVALUATION OF TENDERS
  • CESA recommended changes to CIDB Tables
  • (in using Tables 7-1 to 7-6)
  • Table 7-4 Ratings, very good/good/satisfactory/poo
    r CIDB uses 100/90/70/40. CESA recommend
    100/70/50/0 because
  • Descriptors for Poor (0) confirm unsatisfactory,
    i.e. unacceptable
  • Good/Satisfactory mean nearly the same decrease
    Good to 70 to compare with Very Good (100)
    decrease Satisfactory 70 to 50.
  • Actual application of weightings, Quality /
    Financial Offer depends on relative value of the
    two criteria, e.g. Quality scoring 80 to 85 and
    Financial scoring 50 to 100, Financial scoring
    can outweigh Quality scoring

102
(No Transcript)
103
  • SESSION 6
  • 6.1 Performance Monitoring Consulting
  • Services

104
  • PERFORMANCE MONITORING
  • This presentation
  • Performance Quality Assurance
  • Evaluation of CEs Performance process
  • Pillars of PM
  • Consultant performance evaluation scorecard
  • Points to Note

105
  • PERFORMANCE MONITORING
  • Introduction
  • Performance Evaluation of CEs is crucial in
    upholding advancing the standards of service
    from Consultants
  • Benefits of performance evaluation.
  • The client will know the level of service being
    delivered or delivered
  • The client will get an indication as to whether
    his choice for consultant was correct
  • Ensures integrity of the QCBS process
  • Assist in the pre-selection and bid evaluation
  • raise the standard of consulting engineering
    industry

106
  • PERFORMANCE MONITORING
  • Introduction
  • Other uses (by Client, CIDB, ECSA, NT, CESA, etc)
  • Disciplinary action warning
  • Suspension of firm(s) registration
  • Cancellation of registration
  • Black listing the firm
  • Black listing the professional

107
  • PERFORMANCE MONITORING
  • Performance Quality Assurance
  • CE have a Quality Management System ISO 9001
    2008 QMS or of similar levels ( a condition of
    CESA membership)
  • ISO requires firms to conduct Client Satisfaction
    surveys, analyse to show trends and confirm
    improvement.
  • Enable flaws to be detected, thus avoiding more
    costly deviation corrections
  • CE have adopted the principles of a Business
    Integrity Management System, ( Part of CESA
    members Code of conduct)

108
  • PERFORMANCE MONITORING (contd)
  • Evaluation of CEs Performance process
  • NT assigns PM to CFO suggest done with Project
    Manager or Town Engineer
  • The process must commence from the time of
    appointment and must continue until final
    completion of the project.
  • Points to note during the initial briefing of
    the consultant
  • The briefing must set a standard for performance
    and discuss the evaluation process, as well as
    describing the method of reporting required.
  • Client should provide feedback, so that the
    consultant could improve if necessary

109
  • PERFORMANCE MONITORING (contd)
  • Pillars of performance monitoring
  • Criteria must relevant
  • Criteria clearly defined to allow consistent
    application confidential, rigorous and objective
    manner
  • Conducted according to the Pillars of procurement
    and CIDBs Code of Conduct

110
  • PERFORMANCE MONITORING (contd)
  • Consultant performance evaluation scorecard
  • CESA is proposing a comprehensive set of
    evaluation criteria for gauging the performance
    of CE.

111
  • PERFORMANCE MONITORING EVALUATION SCORECARD

112
  • PERFORMANCE MONITORING (contd)
  • Points to Note
  • Attributes choosing engineering consultants
  • Technical competence
  • Managerial ability
  • Experience on similar projects
  • Dedicated personnel available for the projects
    duration
  • PROVEN PERFORMANE
  • Local and/or local knowledge
  • Professional independence integrity
  • Conclusion - Turn to page 44

113
(No Transcript)
114
  • CLOSING REMARKS
  • This technical briefing has been presented in the
    interests of a more efficient construction
    industry, enhanced through the use of more
    effective and uniform procurement
  • would like to thank
  • Consulting Engineers and their Clients for
    attending, and we wish you a safe onward journey

This technical briefing has been presented in the
interests of a more efficient construction
industry, enhanced through the use of more
effective and uniform procurement
Write a Comment
User Comments (0)
About PowerShow.com