Suffolk Energy-from-Waste Facility - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Suffolk Energy-from-Waste Facility

Description:

Suffolk Energy-from-Waste Facility James Dowell, Dan Smyth (RPS) and Anthony Durston, SITA UK * I A little about us We want to live in a society where there is no ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 27
Provided by: transformi3
Category:

less

Transcript and Presenter's Notes

Title: Suffolk Energy-from-Waste Facility


1
Suffolk Energy-from-Waste Facility
James Dowell, Dan Smyth (RPS) and Anthony
Durston, SITA UK
2
A little about us
  • We want to live in a society where there is no
    more waste
  • We are a recycling and resource management
    company

3
Some facts about us
  • 750 Million turnover
  • Over 5,500 staff
  • Over 40,000 private sector customers
  • Over 9 million tonnes of waste handled
  • Over 2.5million tonnes of waste recycled
  • Over 1MMwH of electricity produced
  • Part of SUEZ ENVIRONNEMENT a multinational
    water and waste management company

4
Why change is needed
  • Environmental
  • Recycling and waste as a resource Greenest
    County aspiration
  • The 4 Rs Reduce, Reuse, Recycle, Recover
  • Space in landfill is running out
  • Regulation
  • Strict landfill reduction targets
  • Landfill tax will go up to 100 per tonne by
    2013/14 (including handling and landfill tax)

24/11/2013 I
5
Suffolk and SITA UK
  • Selected as Preferred Bidder in May for a 25 year
    PFI contract to manage the residual waste
    collected by Suffolks councils.
  • Part of an integrated joint municipal waste
    management strategy
  • Working with Suffolk on Greenest County
    aspiration
  • Cabinet approval September 2010.
  • Contract signed 5 October 2010.

24/11/2013 I
6
Our proposals
  • Using the Councils former Highways Depot site in
    Great Blakenham
  • A 269,000 tonne (approx) energy from waste
    facility. Suffolk County Council is committed to
    provide 170,000 tonnes per year.
  • A visitor centre for community use
  • An onsite ash processing facility
  • Landscaped wildlife area

24/11/2013 I
7
Site location
8
Site location
9
The site plan
10
How does EfW work
  • Waste is collected mainly from households and
    there is some headroom for business waste.
  • Residual waste is burned to heat water
  • Steam is used to power a turbine to generate
    electricity
  • Flue gases are thoroughly treated
  • Bottom ash recycled for use as an aggregate
  • Fly ash removed and disposed of by a specialist
    company.
  • Recyclates recovered e.g. ferrous metals

24/11/2013 I
11
(No Transcript)
12
The benefits
  • Over 250,000 tonnes of waste diverted from
    landfill
  • Enough power for 30,000 homes equivalent to
    Lowestoft
  • Part of the overall Suffolk joint municipal
    waste management strategy
  • Visitor centre for community use
  • Financial benefits for County and council tax
    payers
  • Landscaped wildlife area
  • 43 new long-term jobs and 250 at peak of
    construction
  • Aiming for BREEAM excellence-rated building

24/11/2013 I
13
The architecture
  • Designed by Grimshaw architects

24/11/2013 I
14
Computer generated views of the facility
15
Computer generated views of the facility
16
The planning application
  • Issues raised during consultation
  • Transport
  • Air quality
  • Visual

24/11/2013 I
17
Transport
  • The facility is well located close to the
    strategic lorry network
  • Designated routes for HGVs to the site (shown in
    red)
  • Road improvements are being considered.

18
Transport
  • 216 two way HGV movements would be generated each
    day, which the road network can accommodate.
  • The EfW facility would generate less traffic
    overall than the highways depot but there would
    be a marginal increase in HGVs.
  • Transport assessment has taken into account the
    development of SnOasis.

19
Air Quality
  • Existing air quality in Great Blakenham is
    generally good.
  • Average nitrogen dioxide concentrations are well
    below the levels set out in the Air Quality
    Strategy Objective.
  • The Air Quality Assessment assumes that the
    facility operates at the maximum limits, but it
    is likely that the facility will operate well
    within these limits.
  • Even in worst case conditions, the predicted
    impact on local air quality is well below the
    Environmental Quality Standards for all
    pollutants.

20
Air Quality
21
Visual
  • Efforts taken to reduce the visual impact of the
    building through architectural design.
  • The current land use in the area is semi
    industrial with the former cement works (now
    demolished), a landfill site and the former
    transport depot.
  • Visual assessment concludes that the landscape
    and the setting of the affected locations is able
    to accommodate the new structure, taking into
    account its design, scale, the nature of existing
    development, other features such as existing
    power lines and permitted developments such as
    SnOasis.

22
Our track record
23
Visitor Centre
  • Visitor Centre Exhibits
  • The scope of the Visitor Centres message will
    be much wider than just EFW technology. Science
    Projects have designed multi-layered exhibits to
    tackle three key themes equally

Energy From Waste
Greenest County
Waste Reduction
24
SITA Trust
  • Provides funding through the Landfill Communities
    Fund. Independent from
  • SITA UK.
  • Three programmes
  • Enriching Nature England-wide funding for
    priority species and habitats.
  • Enhancing Communities community funding within
    three miles of a SITA
  • UK facility.
  • Young Persons Volunteering Fund funding for
    14-25 year old olds to
  • enhance or create facilities that can be enjoyed
    by the wider community in
  • England and Wales.

25
The engagement process
  • Designed to reach out to people across Suffolk
  • Multi-stage, multi-element engagement process
  • Initial communication focused on Great Blakenham
  • Second phase of communications in September /
    October
  • Community Liaison Group
  • Submission of planning application in December

24/11/2013 I
26
Thank you for your time
  • Any questions?

24/11/2013 I
Write a Comment
User Comments (0)
About PowerShow.com