Title: RADCON TECHNICIAN TRAINING
1RADCON TECHNICIAN TRAINING
- Welcome-You may click the left mouse button or
use the Enter key to advance.
2Foreign Material Exclusion
Computer Based Training
3About This Course
- You may use the P key to go to the previous
screen.
4About This Course
- This Computer Based learning activity has been
developed from the material in the lesson plan on
Foreign Material Exclusion (HPT001.113).
5Foreign Material Exclusion OBJECTIVES
- Terminal Objective
- Upon completion of this lesson the student will
demonstrate satisfactory knowledge of the TVAN
Foreign Material Control Program by scoring at
least 80 on an examination. SPP-6.5 is allowed
as reference material for the exam.
6Foreign Material Exclusion OBJECTIVES
- The examination for this CBT will be provided on
the computer. - A proctor must allow you access to the
examination. - The software will score each question as you
answer it.
7Foreign Material ExclusionOBJECTIVES
- Enabling Objectives
- 1. Define terms outlined in the FME procedure
and this course. - 2. State the purpose of Foreign Material
Exclusion. - 3. Identify responsibilities of various
personnel for work preparation through job
closure to include recovery from loss of FME
controls. - 4. Identify the most common causes of Foreign
Material Intrusion (FMI). - 5. Identify potential radiological hazards and
other concerns resulting from FMI or loss of FME
controls - 6. Identify FME requirements for special
activities and specific areas. - 7. Identify points from industry events
concerning FME, including SOER 95-1. - 8. Correlate error prevention tools used to
prevent foreign material intrusion.
8Foreign Material Exclusion REFERENCES
- A. SPP-6.5, Foreign Material Control, Revision 7,
effective date 07/11/2003. - B. HPT001.113, Foreign Material Exclusion, RADCON
Technician Training Program, Revision 0. - C. INPO SOER 95-1, Reducing Events Resulting from
Foreign Material Intrusion. - D. BFN PERs
- E. NRC Inspection Report No. 50-390/97-11
-
9Foreign Material Exclusion Training Materials
and Aids
- Access and/or print the following documents you
will need for the course by clicking on the icon - SPP 6.5, Foreign Material Control, latest
revision. - Student Notebook
10Foreign Material ExclusionIntroduction
- Foreign material introduced into plant
systems can cause equipment degradation,
inoperability of components, or even fuel damage
which may lead to higher radiation and
contamination levels.
11Foreign Material ExclusionIntroduction
- Intrusion of foreign material into primary
systems can also create activated products which
cause more radiation dose to personnel.
12TVAN has had its share of FME events. Just a few
are included here.
13Foreign Material ExclusionIntroduction - BFN
Events
- 1998 - A hose was floating in the Unit 3 spent
fuel storage pool. The hose broke and part fell
to the bottom of the pool. - 1998 - Foreign material was found in steam trap
2-TRP-073-005 at BFN and appeared to be welding
slag and grinding dust. The trap had been
replaced during U2C9 outage.
14Foreign Material ExclusionIntroduction - BFN
Events
- 1997 - Clear cellophane wrap was used to support
RADCON activities on the refuel floor. This is
contrary to FME control requirements. - 1995 - Plastic type material was wrapped around
the lower suction portion of the BFN 3A core
spray pump impeller.
15Foreign Material ExclusionIntroduction
- Significant industry events continue to occur due
to inadequate control of Foreign Material.
- INPO SOER 95-1 provides insights into the most
prevalent causes of foreign material intrusion
events and identifies some effective industry
practices for preventing foreign material
intrusion.
16Foreign Material ExclusionIntroduction
- Several other events and SOER 95-1 concerning
foreign material intrusion will be reviewed later
in this course.
17Foreign Material ExclusionIntroduction
- For these reasons, nuclear plants have a Foreign
Material Control program in place.
FME Control Program
18Foreign Material ExclusionIntroduction
- SPP 6.5, Foreign Material Controls, provides
requirements for maintaining nuclear plant
cleanliness by preventing the uncontrolled
introduction of foreign material such as
maintenance residue, dirt, debris, or tools into
open systems or components, and recovery from
intrusion of foreign material.
19Foreign Material Exclusion
- SPP-6.5, Foreign Material Control, emphasizes an
attitude of - focus on prevention .
20Foreign Material ExclusionIntroduction
- In addition to programs and procedural direction,
our work practices and habits have a great impact
on the end result of all that we do.
The success of TVANs FMI Program depends on YOU!
21Foreign Material ExclusionProcedure
- SPP 6.5 requirements apply to all maintenance,
modification, operations and testing activities
which involve open systems or components.
22Foreign Material ExclusionProcedure
- The methods used to control foreign materials
within areas will depend on the configuration and
safety significance of the system, the activity
being performed, and the probability of foreign
material intrusion.
Procedure Adherence is an error prevention tool!!!
23Foreign Material ExclusionProcedure
- Several activities such as valve packing and pump
repacking are NOT considered as opening of a
component or system. - Also, some activities are exempt from the FME
requirements under certain conditions. - Review SPP 6.5, Section 2.0 for more examples of
the above.
24Foreign Material Exclusion TERMS AND DEFINITIONS
- The following definitions from SPP 6.5 are
important and are found in Section 5.0
25Foreign Material Exclusion TERMS AND DEFINITIONS
- Foreign Material Exclusion - Preventing the
inadvertent introduction of foreign material,
such as dirt, debris, maintenance residue, tools
and equipment into open plant systems or
components.
26Foreign Material Exclusion TERMS AND DEFINITIONS
- FME Area - A work area where specific controls
are implemented to prevent the introduction of
foreign material into systems or components
during the performance of maintenance,
modifications, test or inspection activities.
27Foreign Material Exclusion TERMS AND DEFINITIONS
- Maintenance Residue - Any by-product of a
maintenance activity, such as chemical deposits
from solvents, particles and filings from
cutting, grinding or lapping dust, wood chips
from scaffolding, tape adhesive, and welding or
soldering residue.
28Foreign Material Exclusion TERMS AND DEFINITIONS
- Source Term - The quantity of radioactive
materials (corrosion products and fission
products) contained in the Reactor Coolant System
(RCS).
29Foreign Material Exclusion TERMS AND DEFINITIONS
- Fail-Safe - Describes an item which is too large
to fit through the sensitive openings in systems,
components, or equipment.
30Foreign Material Exclusion TERMS AND DEFINITIONS
- Fail Safe (cont.) - Component parts of the item
must be secured to prevent loss and the item must
be easily retrieved from the system or component.
31Foreign Material Exclusion TERMS AND DEFINITIONS
- Fail Safe (cont.) - During refueling activities,
in the area of open pools of water, an item may
be considered fail-safe if the configuration of
the item makes it readily retrievable, even
though it is small enough to fit through
available system openings.
32Foreign Material Exclusion TERMS AND DEFINITIONS
- Qualified FME Monitor (FMEM) - A person who has
had training concerning FME procedures and
controls, duties of FMEM, and actions to be taken
should loss or suspected loss of FME control
occur.
33Foreign Material Exclusion TERMS AND DEFINITIONS
- The FMEM must be knowledgeable of
- FME requirements,
- use of accountability logs,
- their responsibility to remain at or near the
entrance to FME control area, - the logging in and out of items and/or personnel,
- and verification (accountability) for all items
before closure or removal of boundaries/barriers.
34Foreign Material Exclusion TERMS AND DEFINITIONS
- FME Accountability Log - A chronological listing
used to account for items and personnel that
enter and exit FMEAs.
35Foreign Material Exclusion TERMS AND DEFINITIONS
- Temporary Cover - A method to cover and protect a
system or component from the introduction of
foreign material when the system or component is
left unattended. - SPP 6.5 has several specific requirements for
temporary covers.
36Foreign Material Exclusion TERMS AND DEFINITIONS
- Lanyard - A line, rope or cord used to secure or
restrict an object from movement or loss.
Lanyards should be made of nylon or corrosion
resistant steel wire. The shortest length should
be such that it minimizes dropping distance and
limits the object from hitting and damaging
surrounding equipment. - In no case shall a personnel hazard be caused to
exist by the use of lanyards!
37Foreign Material Exclusion TERMS AND DEFINITIONS
- Non-fail-Safe - Describes an item which could be
introduced into sensitive openings of systems or
components.
38Foreign Material Exclusion TERMS AND DEFINITIONS
- Non-fail-Safe (cont.)- This introduction could
occur by the item itself falling into or part of
the item falling into the openings. - Can you think of a Non-fail-safe item where part
of the item could fall into openings???
39Foreign Material Exclusion TERMS AND DEFINITIONS
- For example a lens holder comes off a
flashlight, allowing batteries, lens and holder
to fall into an open system or component. - This type of item is considered nonfail-safe, and
shall require additional methods, such as
lanyards, taping, and bagging to prevent loss.
40Foreign Material ExclusionWork Steps
Work Planning
Work Preparation
Work Performance
41Work Planning
42Foreign Material Exclusion Work Planning
- A FME evaluation for controls should be performed
whenever a system or component is to be opened.
This evaluation is typically performed by the
work planner. - For standard, recurrent activities in which FME
is required, a mandatory FME list and standing
instructions concerning FME controls
(requirements) should be developed. - An example is SPP 6.5, Appendix F, BFN Spent Fuel
Pool, Vessel Cavity, and Equipment Pit - Level 3 - Appendices B - G contain other BFN requirements.
43Foreign Material Exclusion Work Planning
- More stringent FME requirements may be mandated
for any work activity than is listed in the
Appendices of the SPP. - Especially important for work on valves which
have stellite hard-facings and where particles
could come in contact with reactor coolant.
44Foreign Material Exclusion Work Planning
- Less stringent controls must be approved by the
FME Program Coordinator or designee.
45Work Preparation
46Foreign Material Exclusion Work Preparation
- Work Supervisor Responsibilities
- Brief the work crew(s)
- Assign qualified FME monitor
- Define FME area boundaries to be established
- Worker Responsibilities
- Establish boundaries and markers
- Remove nonessential material from the
FMEA/adjacent areas - Clean the FMEA (including overhead and
components) of dirt and debris - Erect a clean enclosure or barrier around the
FMEA - Make all items fail-safe
- Remove unsecured personal items (jewelry, wallet,
coins, etc.)
47Foreign Material Exclusion Work Preparation
- FME areas must be bounded and marked.
48Foreign Material Exclusion Work Preparation
FOREIGN MATERIAL EXCLUSION AREA AUTHORIZED
PERSONNEL ONLY
- The STOP sign and these FMEA boundary postings
(or similar ones) are used.
FOREIGN MATERIAL EXCLUSION AREA AUTHORIZED
PERSONNEL ONLY FME MONITOR APPROVAL REQUIRED BEFOR
E ENTRY
49Foreign Material Exclusion Work Preparation
- FME Monitor Responsibilities
- Perform and document an initial inventory of all
non-permanent items that are not fail-safe within
the FMEA using an approved FME Accountability
Log. - Concurrence must be obtained from the job
supervisor.
50Work Performance
51Foreign Material Exclusion Work Performance
- Work Supervisor Responsibilities
- Ensure work preparation steps are complete
- Authorize system or component opening
- Monitor work area
- Ensure logs are reconciled and approved
- Ensure FMEA cleanliness
- Designate an individual to witness closure of the
system
52Foreign Material Exclusion Work Performance
- FME Monitor Responsibilities
- Maintain required access controls to FMEA and
records for material accountability - Ensure personnel understand requirements and
comply with FME controls - SPP 6.5, Sections 3.3.5, and 3.3.6, contain many
more specific requirements for both the above
responsibilities.
53Foreign Material Exclusion Work Performance
- Some examples are
- Log all missing items or parts from tools and
equipment entering the FMEA. Video taping or
photographing items is an option. - Log all tools, equipment, and material that enter
and exit the FMEA - Inspect tools, etc., exiting the FMEA for missing
parts that might have been lost in the FMEA.
54Foreign Material Exclusion Work Performance
- Control of Materials Entering FMEAs
- Tape shall be placed over all pocket openings
containing items/material. - Pens and pencils shall be attached to a lanyard.
55Foreign Material Exclusion Work Performance
- Control of Materials Entering FMEAs (cont.)
- Loose objects such as badges and dosimetry shall
be worn under protective clothing or placed in a
pocket and taped, even if attached to a lanyard. - Electronic dosimeters are considered secured if
placed inside the pocket with the retaining clip
over the pocket and taped.
56Foreign Material Exclusion Work Performance
- Control of Materials Entering FMEAs (cont.)
- Items of jewelry, such as earrings, wrist
watches, rings and necklaces shall be removed or
placed in taped pockets. However, rings which
cannot be removed, and rings and watches covered
by gloves shall be considered fail-safe. - Eyeglasses shall be fastened to the wearer with
tape, nylon cord, or eyeglass retainer straps
57Foreign Material Exclusion Work Performance
- Worker Responsibilities
- Examine all items before entry and before removal
to identify and correct any loose or missing
parts - Use good work practices to minimize maintenance
residue generated during the activity. - Ensure parts/particles, especially valve stellite
hard-facing, are removed before closure.
58Foreign Material Exclusion Work Performance
- Examples of Good Work Practices
- Ensure that the external surface of the component
to be worked is free of foreign material that
could enter the system when opened. - Inspect and clean the work area if required
before starting work including the area above the
work area and ensure no loose items exist which
could fall in the system while open. Remove or
secure items that could fall in the system. - Clean any new components or parts of protective
coating or dirt before installation. - Use only approved chemicals.
- Ensure all tools or components entering the FMEA
that have loose or missing parts are identified
on the accountability log.
59Foreign Material Exclusion Work Performance
- Examples of Good Work Practices (cont.)
- Visually inspect system internals for foreign
material immediately after opening. If foreign
material is found, notify job supervisor and FMEM
if applicable. - As work progresses, inspect system internals that
will be inaccessible after further assembly. - Ensure system cleanliness before final closure.
- Be responsible for items taken into FME areas,
ensuring items being carried in are logged in and
out on exit when required. - Clean up as work progresses, rather than rely on
large clean-up when the work is completed.
60Foreign Material Exclusion Work Performance
- FME areas are classified as
- Level 1 - FME General Housekeeping
- Level 2 - Systems/Components in which the opening
is small, or all areas can be visually inspected
and foreign material removed. - Level 3 - Systems/Components in which all areas
cannot be visually inspected and foreign material
removed.
61Foreign Material Exclusion Work Performance
- SPP 6.5, Appendices contain requirements for
specific activities for Levels 1, 2, and 3 and
are listed by system for BFN and PWRs. - Appendix G gives guidance for BFN Refuel Floor
FME controls. - Appendix H gives requirements for BFN Torus and
Drywell activities.
62Foreign Material Exclusion Work Performance
- Appendix I gives guidance at PWRs, Reactor
Equipment Pit with Head in Place. - Appendix J gives guidance at PWRs, around Spent
Fuel Pit, Cask Loading Area, Transfer Canal and
Refueling Cavities when flooded. - Appendix K gives guidance at PWRs, Control of
Loose Debris in Ice Condenser, Modes 5, 6 and No
Mode.
63Foreign Material Exclusion Suspension of the Job
- Often plant conditions change which requires work
within a FMEA to be suspended. If work in a FMEA
is stopped during a shift, between shifts, or for
a period of time certain actions are required.
64Foreign Material Exclusion Suspension of the Job
- If work on a job will be interrupted for normal
breaks, meals, shift turnovers, or work related
activities, the Lead Work Performer or Job
Supervisor shall ensure the following conditions
are met - Work location must be secured with appropriate
temporary covers, plugs, or other barriers. - To extent practical, unneeded tools, equipment,
supplies, material, and debris are removed and
general housekeeping requirements are met.
65Foreign Material Exclusion Suspension of the Job
- The Job Supervisor may relax the FME requirements
when work is interrupted for longer than one
shift, provided the following conditions are met
66Foreign Material Exclusion Suspension of the Job
- Ensure all personnel are out of the area.
- A Stop sign should be posted at the entrance to
require all individuals who enter the area to
contact the job supervisor before entering the
area. FME boundaries may be removed if Stop
signs are placed on the temporary covers. - When FME boundaries remain ensure temporary signs
are maintained to clearly identify the FME area
and the responsible supervisor to be contacted
for entry into the area.
67Foreign Material Exclusion Suspension of the Job
- Temporary plugs, covers or seals should be
substantial and compatible with the application.
Examples - metal or plastic disks.
- pipe plugs,
- blind flanges,
- heavy gasket material
- herculite
- Covers should be fire resistant or fire retardant
to the extent possible.
68Foreign Material Exclusion Suspension of the Job
- Paper products or rags inserted into openings are
unacceptable for use as temporary plugs or covers.
69Foreign Material ExclusionRecovering from Loss
of FME Controls - Worker Responsibilities
- If a known or suspected instance of entry of
foreign material into an open system or component
should occur, the worker(s) shall immediately
take action.
70Foreign Material ExclusionRecovering from Loss
of FME Controls - Worker Responsibilities
71Foreign Material ExclusionRecovering from Loss
of FME Controls - Worker Responsibilities
- If an item can not be accounted for on the
inventory log, the worker shall notify his job
supervisor.
72Foreign Material ExclusionRecovering from Loss
of FME Controls - Worker Responsibilities
- If the material can be easily retrieved (without
further disassembly of the system or component)
then the retrieval may be performed and
documented on existing work initiating document.
Caution Radioactive Material
73Foreign Material ExclusionRecovering from Loss
of FME Controls
- Caution Radioactive Material!
- Do not remove foreign material without first
having the material surveyed by RADCON! - Unplanned radiation dose events have occurred
because workers handled foreign material that was
highly radioactive.
74Foreign Material ExclusionRecovering from Loss
of FME Controls - Work Supervisor Responsibilities
- If the missing items cannot be accounted for, the
job supervisor shall determine if work should be
stopped and the item retrieved or if the search
and retrieval will be performed just before
closure.
75Foreign Material ExclusionRecovering from Loss
of FME Controls - Supervisor Responsibilities
- A PER will be initiated for items which cannot be
retrieved immediately. - Safety and technical evaluations will be
performed as appropriate.
76Foreign Material ExclusionCompleting Job Closeout
- Before a system opening is closed
- All PERs identifying FME must be evaluated
- The system determined acceptable for closure
- Closeout inspection performed and documented
- Any FME concerns resolved, documented on PER
- Workers remove all materials, debris, tools, and
equipment. - Initiate corrective actions for inadequate FME
controls - Provide feedback to work planner on problems or
good practices
77Foreign Material ExclusionTraining Requirements
- General and specific training shall be conducted
for - All personnel with access to plant work areas for
a general knowledge of FME. - Engineers, supervisors, technicians, operators,
planners. - FME monitors, foremen, craftsmen, contractors.
- A list of qualified FME monitors will be
maintained by Site Training.
78Foreign Material ExclusionPeriodic Assessment
- The Site FME Coordinator should periodically
perform an assessment of how well the FME program
is working.
- This would involve review of such items as work
documents and PERs concerning loss of/or
suspected loss of FME controls.
79Foreign Material ExclusionPeriodic Assessment
- Trends will be reviewed and any corrective
measures should be implemented.
80Foreign Material ExclusionCommon Causes of FMI
Identified by INPO
- Insufficiently established and communicated
management expectations for the implementation of
FME controls. - Limited supervisory emphasis on FME
considerations and practices during pre-job
briefings and monitoring of work. - Insufficient training for workers in basic FME
practices and a lack of specific training for
work activities involving specialized activities
of key plant systems.
81Foreign Material ExclusionINPO Recommendations
- Provide clearly established management
expectations for foreign material exclusion
controls and practices. - Verify the work control process reinforces FME
controls. - Ensure initial, continuing and job-specific
training programs provide the knowledge and
skills needed to implement effective FME
practices.
82Foreign Material ExclusionSOER 95-01
- On August 29, 1994, at Pilgrim, a main generator
fault caused a load rejection that resulted in a
reactor scram from 100 power. The fault
resulted from overheating of stator bar
insulation. The overheating has been attributed
to foreign material restricting flow of the
stator cooling water outlet header. Imprints in
one piece of the gasket material indicate that
the material may have covered as much as 80 of
the outlet flow area from the most severely
damaged stator bar. - The unit was shutdown for 14 weeks.
83Foreign Material ExclusionSOER 95-01
- At Biblis A, 1994, during preparations for plant
restart following a refueling outage, a fire
occurred in the motor of a reactor coolant pump
as a result of a short circuit in the motor
windings. When the motor was inspected, a
chisel, left in the motor during a previous motor
inspection, was found to have caused the short
circuit. - Plant restart was delayed for approximately one
month.
84Foreign Material ExclusionSOER 95-01
- Robinson 2
- On October 10, 1992, parts from a refueling tool
came loose and lodged in the control rod guide
tube of a fuel bundle. The next day, contractors
who performed the work noticed parts were
missing, but they did not report this to their
supervisor or to station personnel. 18 hours
later, the contract personnel informed their
supervisor that the missing parts were at the
bottom of the spent fuel pool. Their supervisor
thought this was of limited significance and did
not report it to station personnel. One hour
later, a control rod would not fully insert into
a fuel bundle, station personnel were informed
that missing tool parts might be the cause.
Visual inspection of the control rod revealed one
of the missing parts stuck to the end of the
control rod. The other parts remained in the
guide tube of the affected fuel bundle.
85Foreign Material ExclusionSOER 95-01
- Milhama 1, 1993 - A turbine overspeed trip test
was performed on the main turbine. During this
test which followed a refueling outage, bearing
lube oil pressure was 14 psig instead of the
normal 24 psig at rated turbine speed. The
reactor was shut down and investigation revealed
that the bearing oil pump ejector nozzle was
found clogged with paper towels that had been
used to wipe the main oil pump flanges. - The plant was off-line for an additional 6 days.
86Foreign Material ExclusionSOER 95-01
- Perry 1, 1992/93 - During a refueling outage
debris was found on the suppression pool floor
and on the suction strainers for 2 RHR pumps.
The strainers were replaced in a future outage
due to deformation from excessive differential
pressure caused by debris on the strainers. - Additionally, filter media for 3 large air
filters in the drywell air coolers, used to
provide filtered air in the drywell during plant
outages, was determined to be the source of
fibrous material found coating the suction
strainer during another outage.
87Foreign Material ExclusionSOER 95-01
- Dresden 3, 1993 - A reactor scram occurred due to
flow restriction in the high-pressure section of
the main turbine. A bolt, slugging wrench, and
key stack that fit together to form a tool had
been left in the main steam piping during a
previous outage. - These parts caused extensive damage to the
first-stage turbine rotor and stationary
diaphragm blades. The blading deformation
partially blocked the steam flow. - A two-month forced outage was required to repair
the HP turbine.
88Foreign Material ExclusionSOER 95-01
- Hatch 2, 1992 - Fuel sipping identified failed
fuel bundles. Inspection revealed debris in 102
of the bundles. Some of the bundles were damaged
from ferrous metal chips from machining
activities performed on primary system piping
during the previous refueling outage.
89Foreign Material ExclusionSOER 95-01
- Point Beach 2, 1992 - A foam rubber plug was
found blocking a containment spray pump. The
plug had been installed in the piping for
cleanliness control during modification work that
installed full flow test lines in the containment
spray, RHR, and safety injection systems during a
previous outage.
90Foreign Material ExclusionSOER 95-1
- Many of these events caused delays in restart of
a unit, or forced outages to repair damage to the
plant.
91Foreign Material ExclusionWBN Event NRC
Inspection Report No. 50-390/97-11
- On September 20-21, 1997, with the reactor
defueled, a rad-worker noted four, small foreign
objects lying on the reactor vessel flange.
Because of his concern for FME (Error Precursor
Can-do attitude), the rad-worker placed three
pieces of the material in a plastic bag without
having the appropriate radiation survey conducted
and subsequently removed the bag from the reactor
vessel cavity area.
92Foreign Material ExclusionWBN Event NRC
Inspection Report No. 50-390/97-11 (contd)
- One piece of foreign material was later
determined to have a contact reading of 56
Rem/hour. - Calculations indicate that the worker received
3.645 Rem to his hand or about 7 of the NRC
annual extremity limit of 50 Rem.
93Foreign Material ExclusionOE 9543
- While preparing to install a new Low Pressure
Stop Valve on the 2B Reactor Feed Pump, workers
disassembled a NEW valve to inspect for foreign
material and found a handfull of metal shavings
and grease inside the valve near the plug and
seat area. - This foreign material was not visible prior to
disassembly of the valve. The workers removed
all foreign material from the valve and then
installed the valve successfully. - If the workers had not removed this foreign
material, it could have been introduced into
primary plant systems resulting in possible fuel
and component damage.
94Foreign Material Exclusion OE 9543
- The root cause of this incident is
- Less than adequate foreign material intrusion
controls by the equipment supplier. - The equipment supplier has since instituted final
inspection requirements to prevent a future
incident of this type.
95SUMMARY
- During past years, foreign material intrusion
events have occurred with an increasing frequency
resulting in the following - nuclear fuel cladding damage
- major equipment damage
- heat transfer capability degradation
- increased radiation levels
- increased presence of discrete radioactive
particles - increased radwaste generation
- system flow characteristics degradation
- unscheduled plant outages and outage extensions
96Summary
- All employees must maintain an awareness of
Foreign Material Exclusion during maintenance
activities and especially during an outage.
97 - Examination Instructions-
- Your examination must be proctored.
- You may review the course as much as you wish
before taking the test.
98 Exam Ground Rules
- No communication, except between student and
proctor. - No reference material other than SPP-6.5 is
permitted during testing. - All answers given are to be your own, and you are
not to receive assistance on the exam, nor are
you to provide assistance to another student on
the exam. - Violations of exam integrity will result in
disciplinary action. - By entering the exam and requesting a proctor
code, you are attesting that you understand and
will comply with the exam rules.
99FOREIGN MATERIAL EXCLUSION
- We need your feedback on this course. Please
obtain a feedback form, complete, and mail it to
Brian Fike, BFT 2A, BFN. - Thank you!
100FOREIGN MATERIAL EXCLUSION You may press escape
to go back to the main menu to take the test.