Construction Surveys - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Construction Surveys

Description:

By adding the vertical distance to a benchmark elevation and prism height: HI = elevB + hp - V Staking out with a Total Station First the instrument is oriented, ... – PowerPoint PPT presentation

Number of Views:80
Avg rating:3.0/5.0
Slides: 31
Provided by: Prefer691
Category:

less

Transcript and Presenter's Notes

Title: Construction Surveys


1
Construction Surveys
2
List of Figures
  • Readings Chapter 23
  • Figures used
  • 23-1 to 23-10.
  • Material to be considered 23-7.

3
Stages and Measurements of CS
  • Design stages topographic Surveying, and site
    maps
  • Construction stage
  • Setting-out and positioning works. 60 of
    surveying hours.
  • involves establishing lines and grades by means
    of stakes and string lines to guide the
    contractor
  • During and after construction as built drawings,
    a record and a check.
  • Measurements involved Horizontal and vertical
    angles, elevations, horizontal distances.

4
CS Equipment
  • Laser Instruments
  • to create a visible line, or plane of known
    elevation or tilt
  • The line or plane could be horizontal, vertical,
    or tilted.
  • Single beam lasers will project visible string
    lines or plumb lines
  • Rotating beam lasers a rotating single beam to
    create a plane.
  • Examples
  • Laser levels, laser theodolite and total
    stations, hand-held EDM instruments (Figures 23-1
    to 23-4)
  • Recent technology of prism-less total stations
    and EDMs, and HDS High Density Surveys.
  • Machine Guidance

5
(No Transcript)
6
(No Transcript)
7
Laser is used to guide the blade
8
HDS Surveys
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
  • Total Stations the ones designed for CS are of
    lower angular resolution(10 or 20), and shorter
    ranges(500 m)
  • Relative GPS sub-centimeter accuracy with real
    time kinematic GPS in horizontal, few cm in
    vertical. Must maintain visibility with
    satellites
  • Levels

15
Horizontal and Vertical Control
  • Before Construction new control points around
    the site must be established with high accuracy.
    Additional points inside the site are then
    established. All points must be tied out for
    repositioning. These initial points should
  • Meet certain accuracy standards
  • Be clearly marked, referenced, and recorded
  • Be far enough to be safe during construction.
  • During Construction additional control is
    extended by the contractor as needed, around or
    inside the structure. These additional points
    should be close enough to the structure so that
    workers with simple equipment can use them

16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
Staking out a Pipeline
  • Sanitary (sewage) sewers and storm sewers which
    carry storm runoffs operate under gravity. The
    grade in such pipelines is critical. City water,
    oil, and natural gas pipes are not as critical.
  • The location of the line is determined after a
    profile leveling is done.
  • The center line and an offset reference line are
    established.
  • Precise alignment and grade are guided by laser
    beams or battered boards.

20
Pipe Laying Laser system by Apache
Source laserlevels.net
21
Staking Pipeline Grades
  • A- Cut and Fill
  • The center line and an offset line are marked and
    stationed. The actual profiling and staking are
    on the offset line, not the CL.
  • Using profile leveling method, obtain ground
    elevation at each stake, compute the depth of cut
    or fill to the invert level.
  • Mark that depth on the stake side facing the
    trench, mark the station on the other side of the
    stake.
  • B- Line and grade
  • Generally done using laser equipment.

22
Staking out a Building
  • First step is to locate the building by boundary
    surveying. Stakes are placed temporarily at the
    corners as a check.
  • In a small size building, a set of batter boards
    and reference stakes are first set. The boards
    are around the building corners and nailed at a
    full number of feet above the footing base or at
    first floor elevation.
  • Nails are driven into the batter board tops so
    that a string connecting them will define an
    outside wall
  • See fig 23-7, and the example which illustrates
    staking out the building in fig 23-8.
  • In a larger building, radial methods, the one you
    used to lay out piles, are used used. Fig 23-9

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
Additional Control for Buildings
  • Elevations
  • Visible benchmark(s) should be set. Additional
    control could be done using marks on nearby
    buildings, or marks on interior structure
    elements (columns, walls).
  • Horizontal
  • temporary batter boards inside the site, marks on
    nearby buildings.
  • Plumbness
  • Essential for multistory buildings columns,
    elevator shafts, construction walls, etc.
  • Checked by a theodolite line of sight rotating in
    a vertical plane, or by lasers.
  • Two instruments, with perpendicular line of
    sights, could be used to guide the construction
    of vertical members in real time.

28
CS Using Total Stations
  • We are simply trying to define (X,Y) and maybe
    (Z) of the center of the TS. Once stored in
    memory, the TS can do further computations
    onsite.
  • Horizontal Orientation
  • By azimuth input occupied point coordinates and
    azimuth to another point.
  • By coordinates input occupied point coordinates
    and another point coordinates
  • By resection input coordinates of unoccupied
    points , at least three, output is occupied point
    coordinates.
  • Vertical Orientation if necessary, output is HI
  • By adding the instrument height to occupied point
    elevation.
  • By adding the vertical distance to a benchmark
    elevation and prism height
  • HI elevB hp - V

29
(No Transcript)
30
Staking out with a Total Station
  • First the instrument is oriented, and a file that
    contains control points and stake points
    information is downloaded into the total
    station.
  • For 2-D stakeout, the number of the desired stake
    point is entered, the instrument will display
    differences of angles and distances to orient the
    prism.
  • For 3-D works, The difference in elevation
    between the stake elevation and the required
    elevation (cut or fill) is also displayed.
Write a Comment
User Comments (0)
About PowerShow.com