Title: New Nuclear at Darlington Environmental Assessment
1New Nuclear at Darlington Environmental
Assessment
WELCOME TO Ontario Power Generations New
Nuclear at Darlington Community Information
Session Environmental Assessment Fall 2008
2Contents
Contents
1
- Tonights presentation will cover
- The Project
- Roles, Responsibilities, Milestones
- Environmental Assessment
- Project Assumptions Layouts
- Project Environment Interactions
- Environmental Assessment (continued)
- Cumulative Effects
- Significance Criteria
- Feedback
- What We Are Hearing
- Input on Our Current Work
3Describe the ProjectPhases
The Project - Roles and Responsibilities
2
- The Project
- To construct and operate a new nuclear power
plant at the existing Darlington site to meet the
base-load electricity requirements of Ontario - Ontario Power Generation (OPG)
- Is responsible for the federal approvals - an
environmental assessment (EA) site preparation
licence - The EA and licence application are for
- Up to four nuclear units
- Up to 4,800 MW of electrical capacity
- The EA must be completed before the site
preparation licence can be issued - A federally appointed joint review panel will
review the EA and licence application
OPG will be the operator for the new nuclear
units at the Darlington site
4Describe the ProjectPhases
The Project - Roles and Responsibilities
3
- Infrastructure Ontario
- Leading a competitive process to select a nuclear
reactor vendor to construct two units and
potentially additional units - Three internationally recognized vendors
participating - Areva NP - US Evolutionary Pressurized Reactor
(1600 MW) - Atomic Energy of Canada Limited ACR1000
Advanced CANDU Reactor (1200 MW) - Westinghouse Electric Company AP1000 nuclear
power plant (1000 MW) - End of 2008 Deadline for Phase 2 Submission
- 2009 Preferred Vendor Selected
- The Vendor will
- Be responsible for construction, including
hiring, purchasing, etc. - Turn the reactors over to OPG when they are ready
to begin operations
5Upcoming Community Information Sessions
The Project Roles and Responsibilities
4
- OPG asked to begin federal approvals process for
new nuclear - Initial Site Preparation Licence submitted
Sept. 2006 - Project Description submitted April 2007
- Canadian Environmental Assessment Agency/Canadian
Nuclear Safety Commission - Determined that a Joint Review Panel will be
established to review the documents - Released for public review on September 4, 2008
- Draft Environmental Impact Statement (EIS)
Guidelines - Draft Panel Agreement and Terms of Reference
- Comments due November 19, 2008
- OPG
- Submits EIS and Site Preparation Licence
Application, once guidelines are finalized - Joint Review Panel
- Undertakes Public/Technical Review Holds Public
Hearing - Issues Report to Federal Minister of the
Environment
6Darlington New Build Project Description
Major/Indicative Milestones
5
7Elements in the Environmental Assessment
- OPG has completed baseline data collection for
most of the areas of study - ?
- We are currently looking at project environment
interactions - ?
- All of this will be documented in the
environmental assessment
6
8The Project Principle Buildings Structures
9The Project - Conceptual Plant Layouts
- Conceptual layouts developed to provide for
principle buildings and structures - All provide for
- Site access
- Switchyard Expansion
- Parking, Construction Facilities
- Soil Stockpiles, Lake fill, Land fill
- Used Fuel Nuclear Waste Storage
- Layout 1 Four reactors and once through lake
water cooling
10Conceptual Site Layouts
- Layout 2 has mechanical draft cooling towers and
two reactor units - Mechanical draft cooling towers
- Main heat transfer to atmosphere
- Structure minimally visible off-site
- Very large land area required
- ?
- ?
- Layout 3 has natural draft cooling towers and two
reactor units - Natural draft cooling towers
- Main heat transfer to atmosphere
- Structure highly visible off-site
- Large land area required
11Lake Fill
- Potential Lake Fill
- Lake Ontario shoreline along Darlington property
- From intake channel to Easterly limit of
Darlington site - EA Bounding Assumptions
- Approximately 100 metres into the lake on west
side - Approximately 450 metres on east side
- Approximately three million cubic metres,
covering 40 hectares - Provides
- Enhanced site security
- Additional lands for construction lay down
- Storage for excavated rock and soil
- Potential wildlife near shore habitat post
construction
12Project DescriptionBounding EA
Timelines/Temporal Boundaries
The dates shown are for EA study purposes.
Actual start and in service dates have yet to be
determined
13Site Preparation
- Timeline
- Approximately two years
- Workforce
- Up to 400 (100 on-site 300 off-site)
- Activities Include
- Mobilization
- Vegetation Removal/Earthmoving
- Soil/Rock Management
- up to 12 million cubic metres
- Infrastructure installation
14Construction
- Workforce
- Up to 3,500 peak workforce for two units
- On-site parking
- Off-site parking may be used within five km of
Darlington site, bus shuttles to transport
workers - Activities Include
- Installation
- Reactor block, turbine generator, cooling system
- Construction Waste Management
- Marine/Road/Rail Considerations
- Concrete Supply
- Timeline
- Approximately six to eight years for two units
15Operations
- Workforce Procurement
- Up to 1,400 per year for each set of two units
- Mid-Life Replacement or Refurbishment - peak
workforce approximately 2,000 - Procurement patterns similar to current
Darlington - Activities Include
- Reactor Commissioning
- Safe plant operations
- Waste/Used Fuel transfer
- Mid-life major component replacement and/or
refurbishment
- Timeline
- Approximately 60 operating years for each set of
reactors (2016-2100)
16Project Environment Interactions Matrix
Component Potential Interaction Potential Interaction Potential Interaction Potential Interaction
Component Site Preparation Construction Operation Decom- missioning
Aboriginal Interests
Aquatic Biota, Surface Water
Atmosphere
Geology, Hydrogeology, Seismicity
Human Health
Hydrology Surface Water
Land Use and Transportation
Physical Cultural Heritage
Radiation and Radioactivity
Socio-economic Conditions
Terrestrial
17Potential Environment Effects Atmospheric
Environment
- Atmospheric Environment
- Air quality noise
- Examples of Potential Effects
- During site preparation construction phases
- Off-site dust and vehicle exhaust emission
- Increased noise from traffic and equipment
- Dust and noise levels return to low levels during
plant operation - Localized fogging and icing from mechanical draft
cooling towers (if used)
18Potential Mitigation Measures Atmospheric
Environment
- Potential Mitigation Measures
- Dust management plan for site preparation and
construction phases, assumed to include - Watering for dust control
- Paved versus unpaved roads
- Different aggregate grades for road construction
- Slope stabilization (e.g. hydro seeding)
- Noise
- Ensure construction equipment is well maintained
- Proactive communication with community
- Vehicle operating restrictions
- Off-site dust / vehicle exhaust/ noise effects
- Routine monitoring and notification
19Potential Environmental Effects Socio-Economic
Conditions
- Socio-economic environment
- Community character, economic studies,
recreational users, municipal finance, etcetera - Examples of Potential Effects
- Nuisance effects to adjacent neighbours
- Disruption of some on-site recreational
facilities - Increased demand for municipal services and
housing - Creation of direct, indirect and induced
employment opportunities - Increased municipal revenue
20Potential Mitigation Measures Socio-Economic
Conditions
-
- Potential Mitigation Measures
- Monitor neighbouring properties for nuisance
effects - Replace or offset loss of recreational uses on
and off the Darlington site - Support construction and trades recruitment and
training initiatives - Enhanced apprenticeship programs
21Projects to Consider in Cumulative Effects
Projects to Consider in Cumulative Effects
Cumulative Effects Assessment
20
22Cumulative Effects Assessment
- Projects
- 407 East Extension
- Region of Durham Energy from Waste Facility
- Development within Clarington Energy Park
- Oshawa Ethanol plant
- St. Marys Alternative Fuels Project
- Pickering Airport
- Refurbishment of existing Darlington Nuclear
Generating Station - Future 401 widening
- Studies and Plans
- Durham Region Water and Wastewater Master
Servicing Strategy
23Significance of Residual Environmental Effects
- Criteria typically include
- Magnitude of effect
- Geographical extent of the effect
- Timing, duration, and frequency of the effect
- Degree to which effects are reversible or
- mitigable
- Ecological and social/cultural context
- Probability of occurrence
- Existing regulatory and industry standards are
used as points of reference. - Professional expertise and judgment are also
applied.
24Feedback Weve Received
- Community Information Sessions
- 600 visitors to date
- Most Important Environmental Features are
- Drinking and lake water quality
- Atmospheric environment, air quality
- Human health considerations
- Nuclear emergency infrastructure and preparedness
- Transportation system safety and road traffic
volumes safety
25Feedback Weve Received
- Community Kiosk
- 500 visitors
- Benefits the project will bring to the area
- How to secure employment
- Importance/Value of the Kiosk
- Timing of Key Events
- When will construction, operations start?
- When will decisions be made?
- Community Events/Displays
- 5,000 visitors
- 50 of the comments
- Nature of the EA studies, Strong project support
- 50 beyond OPGs responsibility
- Vendor selection, Ontarios electricity system,
etcetera
26Upcoming Community Information Sessions
Thank you for participating!
25
- Were here to answer your questions.
- We want your input on
- Mitigation measures to address potential effects
of the project - Project to consider for the cumulative effects
assessment - Criteria to assess significance of effects
- Comment and evaluation forms are available
please take a minute to fill them out before you
leave!
27Contact Us
Contact Us
26
www.opg.com/newbuild 1-866-487-6006