Title: Changes and More


1
Changes and More
  • 15,16, and 17

2
Equitable Estoppel
  • The party to be estopped (PTBE) must know the
    facts
  • The injured party did not
  • The injured party relied on actions of PTBE
  • Actual injury

3
Changes
  • What can be changed?
  • Method of shipping or packaging
  • Place of delivery
  • In-scope changes to drawings designs or specs
  • Authority
  • Non Contracting Officers
  • Outside the Scope

4
In-Scope
  • What does in scope mean?
  • That which a reasonable person would have
    anticipated at the time of contract award
  • Changes in Quantity are prohibited
  • Except. . .

5
Changes
  • Duty to proceed
  • No authority
  • No clear direction
  • Untenable position
  • Effect of Failure to proceed
  • Default

6
Changes
  • Formal change order
  • Contractor proposed
  • Government originated
  • Bilateral
  • Unilateral

7
Changes
  • Constructive changes
  • Types
  • Contract interpretation
  • Interference Failure to Cooperate
  • Defective Specification
  • Nondisclosure of Vital Information
  • Acceleration

8
Delays
  • Standard clause
  • Constructive Suspension
  • Constructive Delays
  • Excusable Delays

9
Constructive Delay
  • Changes
  • Faulty Specifications
  • Furnishing Property
  • Inspection of Work

10
Excusable Delays
  • Elements Proof
  • Unforseeable
  • Beyond control
  • Without fault or negligence
  • Actual Delay
  • Unavoidable
  • Minimize effect

11
Excusable Delays (16-8)
  • Acts of God
  • Sovereign Acts Contractual Acts
  • Fires
  • Floods
  • Epidemics
  • Quarantine
  • Strikes
  • Freight Embargoes
  • Unusually severe weather
  • Subcontractor Delays

12
Equitable Adjustments
  • Computation
  • Contractor kept whole
  • Governments pricing position preserved
  • Added Work
  • Deleted Work
  • Overhead Profit

13
Proof
  • Burden of proof
  • Actual Data
  • Total Cost Method
  • Orig estimate
  • Jury Verdict Method

14
Claims
  • Preparation Costs (?)
  • Interest on Claims (Yes)
  • Interest on Borrowings (No)
  • Notice of Claims
  • 30 days for upward
  • Reasonable for downward