Title: Regional and Inter-Regional Planning Update
1(No Transcript)
2Regional and Inter-Regional Planning Update
Entergy Transmission SummitJuly 29, 2008Astor
Crown PlazaNew Orleans, Louisiana
3Presentation Overview
- SERTP/RPSG Southeast Regional Transmission
Planning / Regional Planning Stakeholder Group - www.southeasternrtp.com
- SIRPP Southeast Inter-Regional Participation
Process - www.southeastirpp.com
- JCSP Joint Coordinated System Plan
4SERTP / RPSG Meetings
- 3/24/2008
- Formation of RPSG and Selection of Sensitivity
Studies for 2008 - 6/25/2008
- Preliminary 10-Year Expansion Plans of SE Region
Transmission Owners - 9/23/2008
- Preliminary Results
- November Transmission Summit
- Final Study Results
5RPSG Sensitivity Studies
1000 MW
Mobile
Atlanta
2000 MW
Entergy
GITS
1000 MW
Alabama
Florida
1000 MW
Entergy
Alabama
Santee CooperSCEG
1000 MW
GITS
6(No Transcript)
7SIRPP Activity
- April 3, 2008- Stakeholders Organizational
Meeting - June 10, 2008 Meeting
- Stakeholder Group was formed
- Economic Studies selected
- Coordinate on study assumptions
- October, 2008 Conference Call
- Review preliminary study results
- January, 2009
- Review final study results and draft report
- February, 2009- Final report issued
8SIRPP Step 1 Economic Studies for 2008
2000 MW
Entergy
GITS
2000 MW
PJMMISO
Southern
3000 MW
Southern
PJM
3000 MW
PJM (classic)
Southern
5000 MW
SPP
(JCSP)
Southern
9Joint Coordinated System Plan
- Scope of Work
- Perform Eastern Interconnect wide study
- Reliability Study 2018 model
- Economic Analysis 2024 model
- Incorporate DOE Eastern Wind Integration
Transmission Study objectives - Future Scenarios
- Reference (todays reference values)
- 20 Wind (by 2024)
10Joint Coordinated System Plan
- Timeline
- Initial Meeting November 1, 2007
- Economic Analysis March 1, 2008
- HV Transmission Overlay Development December,
2008 - Reliability Assessment August 2009
- Cost Allocation Analysis October, 2009
11Joint Coordinated System Plan
- Current Status
- Preliminary transmission plans for each future
have been completed - Beginning to test transmission plans for
robustness - Testing and consolidation of transmission plans
to be completed by December, 2008
12Steve PurdyLead Engineer, ICT Planning501-614-33
71SPurdy_at_SPP.org
Questions / Commentsspp.issuetrak.comQuick
Pick ICT Planning Base Plan
Doug BowmanLead Engineer, ICT Planning501-688-16
40DBowman_at_SPP.org