Title: A Presentation by:
1PUBLIC PRIVATE PARTNERSHIPS IN THE POWER SECTOR
IN KENYA
- A Presentation by
- Laurencia K. Njagi,
- Company Secretary
- Kenya Power Lighting
- Company Ltd
- To the Law, Justice and Development Week 2012
2INTRODUCTION
- Comprehensive reforms implemented between 1993
and 2000 in accordance with the Energy Sector
Policy Framework Papers 1993-1995 and 1996-1998 . - Objectives of the reforms were to enhance
operational efficiency and attract private sector
investment in power generation. -
3INTRODUCTION
- The private sector participation would
- (i) Create competition in the generation
function - (ii) Improve operational efficiency and
- (iii) Complement GoKs investment which could be
used in other sectors not attractive to private
sector.
4SUMMARY OF IMPLEMENTED REFORMS
- Separation of commercial functions from policy
setting, and regulatory functions. - This involved transfer of power assets owned by
government and two regional development
authorities to two main public companies i.e. the
Kenya Power Lighting Company Ltd. (transmission
assets) and Kenya Power Company Ltd., now KenGen
(generation assets).
5SUMMARY OF IMPLEMENTED REFORMS
- Unbundling of generation function from
transmission and distribution functions. - KenGen undertaking generation function and KPLC
undertaking transmission and distribution
functions. - KPLC and KenGen were required to operate on a
commercial basis under a Power Purchase Agreement
which was first entered into in 1999.
6SUMMARY OF IMPLEMENTED REFORMS
- Legislative reform through the enactment of the
Electric Power Act, 1997. - Establishment of a power sector regulator in
1997 the Electricity Regulatory Board with the
mandate to set retail tariffs, approve negotiated
PPAs between KPLC and generating companies and
overall regulation of the sector.
7SUMMARY OF IMPLEMENTED REFORMS
- The Electric Power Act, 1997 was repealed in 2006
and replaced with Energy Act -to consolidate
electricity and petroleum regulation into one
regulator. - Development of power generation projects on the
basis of approved national least cost investment
plan. - Cost reflective electricity tariffs.
8PPP Projects in Energy Sector
No. Plant Capacity (MW) Type FCOD /Status Procurement Method
1. IberAfrica 106 Thermal 1997 Open competition on first 56MW, then extension in 2007
2. Tsavo Kipevu II 74 Thermal 2001 Open Competition
3. OrPower 4 100 Geothermal 2000 Open Competition for phase 1 later expansion
9PPP Projects in Energy Sector
No Plant Contracted Capacity (MW) Technology Full Commercial Operation Date/Status Procurement Method
4 Rabai 90 Thermal 2009 Open Competition
5 Mumias 25 Bagasse 2008 Co-Generation
6 Thika 87 Thermal 2013 Open Competition
7 Triumph 83 Thermal 2013 Open Competition
10PPP Projects in Energy Sector
No. Plant Contracted Capacity (MW) Technology Full Commercial Operation Date/Status Procurement Method
8 Gulf Athi River 80 Thermal 2014 Open Competition
9 Aerolus Kinangop 60 Wind 2014 Feed In Tariffs
10 AGIL Longonot 140 Geothermal 2014 Unsolicited Proposal
11PPP Projects in Energy Sector
- Other 4 mini hydro projects under feed in tariff.
12CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
- Kenya has a 20 year Least Cost Power Development
Plan for transmission and generation systems that
is updated annually. - The Government and KenGen agree on the projects
to be developed by KenGen based on its financial
and technical capacity.
13CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
- KPLC procures private investors to develop plants
not being developed by KenGen. - Most of the geothermal and hydro projects are
implemented by KenGen due to low IPP bidders
interest.
14CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
- In order to remove the risk of geothermal steam,
a fully state-owned geothermal company has been
established to carry out geothermal exploration
and development and to sell steam to private
developers and KenGen for conversion to
electricity.
15CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(ii) Bridging Capacity Gap
- In the event of delays in the implementation of a
committed project in the LCPDP, a decision is
made to procure development of a power plant of a
technology which can be implemented in a short
period by private investors to bridge the
capacity gap.
16CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(ii) Bridging Capacity Gap
- This has been the case for a number of thermal
projects.
17CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iii) Feed In Tariffs For Renewable Energy
- Kenya has a Feed In Tariff with set energy charge
rates for various renewable energy sources to
encourage their development. - Proposals from interested developers are analyzed
and approved if found adequate by a Standing
Committee under the Ministry of Energy.
18CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iii) Feed In Tariffs For Renewable Energy
- PPA negotiations are carried out between the
private investors and KPLC.
19CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iv) Unsolicited Proposals
- Some projects have been awarded for development
as PPPs following unsolicited proposals. - Mostly in technologies like geothermal and wind
which are difficult to subject to competitive
bidding without investing first to ascertain the
natural resource potential.
20LOCATION OF THE PLANT
- A decision on the siting of the project is made
based on the location of the natural resource
(hydro, geothermal and wind), the proximity to
the load centre and transmission and distribution
connection facilities.
21PROCUREMENT PROCESS AND APPROVAL
- Kenya has a Public Procurement and Disposal Act,
2006, that governs procurement by government and
state corporations. - Competitive bidding is the normal method of
procurement. - The Act provides for a review mechanism of
appeals from bidders who are dissatisfied with
the procurement/evaluation outcome.
22PROCUREMENT PROCESS AND APPROVAL
- The Public Private Partnerships Regulations made
under the Act provide specialized procedures for
procurement and approvals of PPP projects and
sets out a PPP Secretariat under the Ministry of
Finance. - A PPP Bill is before parliament as a stand alone
legislation for PPPs.
23PROCUREMENT PROCESS AND APPROVAL
- The negotiated PPAs are subject to approval by
the sector regulator, the Energy Regulatory
Commission.
24IPP PRICES
- The prices payable to IPPs in the PPAs are
derived from competitive bidding process. - For the Feed In Tariff Policy projects, the rates
are set by Feed In Tariff Policy.
25IPP PRICES
- The prices for unsolicited proposals are
negotiated i.e. project costs, cost of funding
are screened including the rate of return to be
allowed and are, where applicable, compared with
those of existing projects.
26IPP PRICES
- The rate of return is guided by ERCs Tariff
Policy which had followed a study.
27RISKS THAT KPLC AND GOK HAVE TAKEN
- KPLC has taken the market/demand risk -PPAs are
on a take or pay basis this arrangement will be
reviewed as the market becomes competitive. - The forex risk is borne by electricity consumers.
Payments are denominated in either dollars or
Euros. The variations are passed through to
customers.
28RISKS THAT KPLC AND GOK HAVE TAKEN
- Political risks are borne by GOK through a
legally binding letter of support issued to the
projects.
29PAYMENT SECURITIES PROVIDED
- The payment security provided to IPPs by KPLC has
usually been stand by letters of credit from
commercial banks in Kenya covering 3 4 months
of payments - In view of planned increased IPP participation,
KPLC requested GOK to support the sector by
providing sovereign guarantees to IPPs.
30PAYMENT SECURITIES PROVIDED
- In order to manage contingent liability, GOK
requested IDA to provide partial risk guarantee
to four projects (87MW Thika), (83MW Triumph),
80MW Gulf) and 52MW geothermal extension) thus
dispensing with sovereign guarantees.
31FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPS
IN POWER SECTOR
- An enabling environment -National Energy Policy
and Energy Act, 2006. - Both recognise need for cost reflective retail
tariffs and IPP charges that should, among
others, enable the investors to attract capital
and compensate them for the risks assumed.
32FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPS
IN POWER SECTOR
- A mature regulatory framework ERC was created
in 1997 and has been approving PPAs and setting
retail tariffs. - Capacity of KPLC to procure, negotiate, and
monitor IPPs.
33FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPs
IN POWER SECTOR
- Financial stability of KPLC as the off-taker.
- Sound governance of KPLC and energy sector
leadership. - Structured competitive procurement process of
PPPs.
34THE END THANK YOU