BCRA Poster - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

BCRA Poster

Description:

Subgrade Soil Support and Stabilization O HARE Airport Modernization Research Project Research Progress and Future Tasks Sept. 21, 2006 Co-PIs: Erol Tutumluer ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 29
Provided by: InTa6
Category:

less

Transcript and Presenter's Notes

Title: BCRA Poster


1
Subgrade Soil Support and Stabilization
OHARE Airport Modernization Research Project
Research Progress and Future Tasks Sept. 21,
2006
Co-PIs Erol Tutumluer
Marshall R. Thompson RA
Deb Mishra
2
Introduction
  • The strength and performance of an airport
    pavement related to the structural design and the
    subgrade soil characteristics
  • This project provides testing and analysis to
    establish subgrade support and stabilization
    requirements for OHare airport pavements

3
Research Objectives
  • Consider/Establish subgrade support and
    stabilization requirements with respect to
  • Need for subgrade stabilization
  • Selection of lime and other suitable admixture
    stabilization considerations
  • Stabilization depth
  • Estimate subgrade support for various
    combinations of subgrade stabilization treatments
    and prepared subgrade conditions

4
Progress Made In 2005-06
  • A project research paper was presented at the
    2006 ASCE Airfield and Highway Pavement Specialty
    Conference, Atlanta, GA, April 30 May 3, 2006
  • Published in the Proceedings book Airfield and
    Highway Pavements, edited by I.L. Al-Qadi
  • Characterizing Subgrade Soils and Establishing
    Treatment Needs for a New Runway at the Chicagos
    OHare Airport
  • by H.S. Brar, E. Tutumluer, M.R. Thompson,
    L. Gosain, and R. Anderson

5
Progress Made In 2005-06
  • On April 5th, 2006, the Co-PIs joined a TEL-CON
    meeting with the OMP concerning the project
    findings on subgrade stabilization and additional
    frost action effects. It was recommended that Dr.
    Dempsey (a participant in the TEL-CON) conduct a
    climatic-modelling study of the 9-27 RW.
  • Both North Runway 9L-27R and South Airfield
    subgrade soil support and stabilization needs
    were discussed
  • effectiveness of lime stabilization on primarily
    silty soils with low clay contents (less than
    20),
  • adequate strength gain requirements,
  • poor workmanship and inadequate construction
    quality control,
  • construction cut off dates for lime treatment
    effectiveness,
  • frost penetration effects, and
  • Cement treatment as an option to include in the
    construction specifications (and use in certain
    project locations in case lime treatment becomes
    unsatisfactory for the primarily silty, low clay
    contents soils to be encountered during subgrade
    preparation)

6
Progress Made In 2005-06
  • Marshall Thompson traveled to the OMP office on
    April 11th and participated in a conference at
    ORD with OMP staff concerning soil stabilization
    (lime/cement, frost action effects, and use of
    fly ash as a stabilization admixture)
  • Erol Tutumluer gave a progress update on July
    20th at the OMP office and found out that fly ash
    was now used for modification of the North Runway
    soils
  • Marshall Thompson traveled to the OMP office on
    July 28 and participated in a conference with OMP
    staff and 9-27 Design Staff concerning
    treatment options for unstable subgrades. He
    participated in the subsequent development of
    recommendations.

7
Progress Made In 2005-06
  • Professor Barry Dempsey, a UIUC expert on
    climatic effects has completed a study of frost
    penetration and freeze-thaw cycle activity for
    the various 9-27 pavement configurations. The
    study considered ORD climatic data for the period
    1996 2006. The report has been published as
    CEAT TN 26.

8
TECHNICAL NOTES
  • Technical Notes have been prepared and submitted
    to the OMP throughout the project duration to
  • Establish the Best Demonstrated Available
    Technology (BDAT) for subgrade soil evaluation
    and stabilization
  • Communicate specific findings and
    recommendations to OMP
  • engineers
  • TN5 K-150 Considerations for RW 9-27
  • TN6 Subgrade Strength/Stiffness Evaluation
  • TN7 Working Platform Requirements for
    Pavement Construction
  • TN8 Subgrade Stability Manual (IDOT)
  • TN13 Moisture Limitations for Lime
    Stabilization
  • TN14 Admixture Stabilization (Lime Treatment of
    Subgrades)
  • TN19 Progress Report on Laboratory Soil Test
    Results

  • (March 2006)

9
DEMPSEY STUDY FINDINGS
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
TOTAL PVT THICKNESS 40 INCHES
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
9-27 PAVEMENT
FROST LINE 46 INCHES
19
DATE FROST DEPTH (INCHES) DATE FROST DEPTH (INCHES)
2-97 46 1-02 30
1-98 28 2-03 40
1-99 43 2-04 46
2-00 37 1-05 36
1-01 47 12-05 36
AVERAGE 39 INS
9-27 PAVEMENT SECTION
20
FY 07 Year 3 Project Tasks
21
FY 07 Year 3 Project Tasks
  • Task 1
  • Cooperate with OMP in the reviewing (and
    modifying if appropriate) Section P-152
    (Excavation and Embankment) and Section P-159
    (Lime Modified Soils) or Fly Ash Modified Soil
    Specs?
  • Experiences (problems/successes) from the current
    9-27 contract should be considered
  • The modified versions should be included in
    future contracts

22
FY 07 Year 3 Project Tasks
  • Task 2
  • Cooperate with OMP in the reviewing and
    modifying Section P-158 (Lime Stabilized
    Subgrade) for inclusion in the upcoming paving
    contract
  • Current version cites latest edition of IDOT
    Specs. Should reference the IDOT 2002 version
  • Modify Spec. (as needed) to include cement as a
    possible admixture
  • Incorporate frost action and freeze-thaw
    potentials from Dempseys study (TN 26) as
    guidelines
  • Will construction be permitted outside the
    current April 15 Sept 15 window?
  • Other issues??

23
FY 07 Year 3 Project Tasks
  • Task 3
  • Evaluate the 9L-27R runway/taxiway soil lime
    stabilization and (fly ash) modification for
    meeting the subgrade support (k-value)
    requirements
  • The research team will support the activities of
    OMP in
  • Characterizing soils _at_ finish grade
    elevation for stabilization admixture
    selection.
  • Evaluating completed modification/stabiliz
    ation effort.
  • Field Validation of completed pavement
    structure.

24
FY 07 Year 3 Project Tasks
  • Task 4
  • Evaluate currently available geotechnical/subgrad
    e data for the South Airfield of the OHare
    Airport with particular emphasis on the
    stockpiled soils
  • Summarize technology and experiences from North
    Runway (9-27) and apply to the South Airfield
  • Advise on the soil sampling needs and if
    considered essential, develop recommendations for
    additional soil exploration/sampling activities
  • Develop/conduct a laboratory testing program for
    soil treatment and subgrade support for the South
    Airfield

25
Project Schedule Deliverables
  • Technical Notes will be prepared and submitted to
    the OMP throughout the duration of this project
    to communicate specific findings and
    recommendations to OMP engineers as needed
  • Several of the Project Tasks are already pursued
    simultaneously, and the specific delivery of
    results will be contingent upon availability of
    OMP data and other factors that depend on
    coordination with OMP
  • Continue to work with OMP on current and future
    subgrade soil support and stabilization needs for
    all OHare runways/taxiways. This will be in the
    form of sustained support for working with OMP on
    subgrade soil support issues

26
Any Questions?
27
(No Transcript)
28
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com