ODOT Structure Project Management Seminar Bridge Preliminary Design Report

About This Presentation
Title:

ODOT Structure Project Management Seminar Bridge Preliminary Design Report

Description:

Title: BRIDGE PRELIMINARY DESIGN REPORT Author: turnbul Last modified by: smeddles Created Date: 11/11/2003 1:51:39 PM Document presentation format –

Number of Views:808
Avg rating:3.0/5.0
Slides: 11
Provided by: turn96
Category:

less

Transcript and Presenter's Notes

Title: ODOT Structure Project Management Seminar Bridge Preliminary Design Report


1
ODOT Structure Project ManagementSeminar
Bridge Preliminary Design Report
2
Project Development Process (Major) Step 8
Develop Stage 1 Design
3
Step 8 Prepare Environmental Clearance/Develop
Stage 1 Design
  • Submit CE, EA or Draft EIS for approval
  • If EIS, develop FEIS and circulate
  • Request approval (CE/FONSI/ROD)
  • Develop and submit Stage 1 detailed design
  • Establish proposed R/W limits
  • Conduct final (second) Value Engineering Study
  • Prepare 404/401 Permit applications and draft
    Mitigation plans
  • Cost Estimates/Schedule

4
Step 8- Stage 1 Detailed Design LD 1403.7
  • Design Topics
  • Survey
  • Geometric
  • Drainage
  • Right of Way
  • Traffic Control
  • Environmental
  • Structures
  • Preliminary Structure Design Report (Previously
    TSL)

Step 8
5
(No Transcript)
6
  • 202.2 BRIDGE PRELIMINARY DESIGN REPORT
    SUBMISSION REQUIREMENTS
  • A. Final Structure Site Plan Section 202.2.1
  • B. Final Maintenance of Traffic Plan Section
    202.2.2
  • C. Foundation Report Section 202.2.3
  • Supplemental Site Plan for Railway
    Crossings Section 202.2.4
  • Response to Step 7 review comments
  • Tell the story how the preferred alternative was
    decided upon
  • Compliance with all review comments
  • Update cost estimate (Provide breakdown of cost
    for aesthetic considerations, if applicable)

7
  • 202.2 BRIDGE PRELIMINARY DESIGN REPORT
    SUBMISSION REQUIREMENTS
  • Final Structure Site Plan Section 202.2.1
  • Site plan should be further developed to contain
    all the BDM requirements, finalize bridge spans
    and limits
  • Preliminary Design Checklist
  • B. Final Maintenance of Traffic Plan Section
    202.2.2
  • C. Foundation Report Section 202.2.3
  • D. Supplemental Site Plan for Railway
    Crossings Section 202.2.4

8
  • 202.2 BRIDGE PRELIMINARY DESIGN REPORT
    SUBMISSION REQUIREMENTS
  • Final Structure Site Plan Section 202.2.1
  • Final Maintenance of Traffic Plan Section 202.2.2
  • In addition to the Preliminary Maintenance of
    Traffic Plan requirements, the Final Maintenance
    of Traffic Plan should include the following
    information
  • Plan views and preliminary working drawings to
    ensure constructability
  • Temporary barrier anchorage details and
    requirements
  • Location and type of temporary shoring (See
    Section 208)
  • Location of structural members that require
    strengthening
  • Temporary structure design information (See
    Section 500)
  • Additional notes and/or details necessary
  • C. Foundation Report Section 202.2.3
  • D. Supplemental Site Plan for Railway
    Crossings Section 202.2.4

9
  • 202.2 BRIDGE PRELIMINARY DESIGN REPORT
    SUBMISSION REQUIREMENTS
  • A. Final Structure Site Plan Section 202.2.1
  • Final Maintenance of Traffic Plan Section 202.2.2
  • Foundation Report Section 202.2.3
  • Supplemental Site Plan for Railway
    Crossings Section 202.2.4

10
  • 202.2 BRIDGE PRELIMINARY DESIGN REPORT
    SUBMISSION REQUIREMENTS
  • A. Final Structure Site Plan Section 202.2.1
  • B. Final Maintenance of Traffic Plan Section
    202.2.2
  • Foundation Report Section 202.2.3
  • Supplemental Site Plan for Railway
    Crossings Section 202.2.4
  • Drainage
  • Disturbance of railroad operations fiber optic
    lines
  • Provide ample information so the Railroad Company
    can adequately locate crossing
  • Temporary shoring concerns and how it affects the
    railroad operations