Title: Northwest Natural 12


1
Northwest Natural 12 Pipeline Integrity Project
Final Design Presentation
  • Team Members
  • Jon Ziring
  • Zack Lemmon
  • Long Nguyen
  • Academic Advisor
  • Faryar Etesami
  • NWN Sponsor Advisors
  • Ross Lisle
  • Jodi Wright

2
Introduction
  • Sections of the pipeline required repair or
    modification.
  • When changes are made, the line stopper fittings
    used to isolate the section are left welded to
    the pipe.
  • Though sealed by the fitting, the enclosed
    pipeline is left with a large cut out section.

Mueller Line Stopper Unit
3
Mission Statement
  • Design a method for repairing the integrity of
    the pipeline to near its original condition.
    This method is to be cheaper, easier, and faster
    than replacing the line stopper fittings.

Hole In Pipeline Due To Fitting Installation
4
Important Design Criteria
  • Cost
  • Each unit must cost less than 300.
  • Manufacturability
  • Materials In house materials
  • Standard tools and dimensions to simplify
    production.
  • Feasibility
  • Accurate placement
  • Alignment must not rotate.
  • Clearance able to clear the minimum inner
    diameter of the access hole.
  • Precision able to accommodate for deviations in
    placement and alignment.
  • Reliability
  • The device should have a minimal probability of
    failure, as it is to remain a permanent fixture
    in the pipeline.
  • Simplicity
  • The device should require minimal training in
    order to produce, insert, and activate.
  • Obstruction
  • Minimize bore reduction, maximum 25 bored
    reduction.

5
Design Progress
6
In The Beginning
  • First Design
  • Solid piece insert
  • Simply rests on pipeline
  • Alignment from side tabs

7
Problems With Solid Piece Design
  • Access Hole Clearance

Wall Dimension Variance
8
Other Designs
  • Other Design Concepts
  • Fits Through Access Hole
  • Mechanically Activates
  • Attaches To Pipeline

9
Additional Problems
  • Too Heavy
  • Tolerances Too Tight
  • Obstructs Flow Through Pipeline

Solid Pipe Insert
10
Permanent Device
  • Problems Solved
  • Clears Access Hole
  • Loose Tolerances
  • Easily Made
  • New Problem
  • Must Be Removable

Permanent One-Way Insert
11
Removable Device
Locking Mechanism for a Removable Insert
12
Release The Insert
  • New Problem
  • Insert Must Separate Itself from the Insertion
    Tool
  • Design Adapter to Interface Between Insert and
    Insertion Tool

Insertion Tool End
13
Removable Adapter
  • Separate Adapter
  • The Adapter Stays With the Insertion Tool
  • Insert is Released from Adapter

Removable Adapter Insert
14
Final Design
  • Improvements and Optimizations
  • Cost
  • Simplicity
  • Manufacturability
  • Adaptability
  • Functionality

Final Design Concept
15
Design Simplification
Before
After
16
Existing Adapter
  • Reduce Manufacturing Costs by Using Existing
    Adapter
  • Disassemble Bypass Plug to Use as Adapter

Bypass Plug
Adapter
17
Alignment Bracket
  • Prevents Insert from Rotating when Activated
  • Allows Adapter to also be used for Removal
  • Accurate Flow Alignment

18
Over-Center Cam-Lock
  • Rotates 5 Past 90
  • Prevents Device from Vibrating Loose
  • Accommodates Variations in Pipe Lip Dimensions

19
Over-Center Lock Test
Testing Wooden Over-Center Cam-Lock Prototype
20
Pipe Locking Mechanism Test
Testing Pipe Lip Locking Mechanism Prototype
21
Assembly
22
Any Questions?