Title: Transmission Substation 2004 Storm Season


1
Transmission Substation2004 Storm Season
2
HURRICANE CHARLEY August 13, 2004
Transmission Sections Locked Out
44 Transmission Structures Effected
.. 220 Transmission Structures
Reported Down 75 Transmission Structures
Reported Leaning 145 Transmission Phases Down
. 146 Sections Locked Out with
Trees on Line 20
3
HURRICANE CHARLEY August 13, 2004
Distribution Substations Out of Service
14 Failed Substation Transformers
.. 1 Substation Regulators Effected
... 4 Switches Effected
. 0 Arrester Failures ( of
Substations) 5 Breaker Failures
(Total) . 8 Transmission
Breakers .. 2 Distribution
Breakers . 6 Restoration ( of
Days After Storm Passes) 2
4
HURRICANE CHARLEY August 13, 2004
Arcadia-Charlotte 69 kV Section
5
HURRICANE CHARLEY August 13, 2004
Fiber Cable
Charlotte-Deepcreek 230 kV Section Peace River
Crossing
6
HURRICANE CHARLEY August 13, 2004
Arcadia-Charlotte 69 kV Section
7
HURRICANE CHARLEY August 13, 2004
Charlotte-Polo 230 kV Section
8
HURRICANE FRANCES September 3, 2004
Transmission Sections Locked Out
108 Transmission Structures Effected
.. 150 Transmission Structures
Reported Down 56 Transmission Structures
Reported Leaning 94 Transmission Phases
Down . 47 Sections Locked Out
with Trees on Line 29
9
HURRICANE FRANCES September 3, 2004
Distribution Substations Out of Service
54 Failed Substation Transformers
.. 1 Substation Regulators Effected
... 5 Switches Effected
. 2 Arrester Failures ( of
Substations) 5 Breaker Failures
(Total) . 20 Transmission
Breakers .. 1 Distribution
Breakers . 19 Restoration ( of Days
After Storm Passes) 2
10
HURRICANE FRANCES September 3, 2004
Port Mayaca-Bryant 69 kV Section
11
HURRICANE FRANCES September 3, 2004
Alva-Orange River 230 kV Section
12
HURRICANE JEANNE September 25, 2004
Transmission Sections Locked Out
80 Transmission Structures Effected
.. 129 Transmission Structures
Reported Down 48 Transmission Structures
Reported Leaning 81 Transmission Phases
Down . 88 Sections Locked Out with
Trees on Line 9
13
HURRICANE JEANNE September 25, 2004
Distribution Substations Out of Service
30 Failed Substation Transformers
.. 1 Substation Regulators Effected
... 1 Switches Effected
. 4 Arrester Failures ( of
Substations) 2 Breaker Failures
(Total) . 14 Transmission
Breakers .. 0 Distribution
Breakers . 14 Restoration ( of Days
After Storm Passes) 2
14
HURRICANE JEANNE September 25, 2004
Saint Lucie Substation