Mars Exploration Rovers Spirit SOL-18 Anomaly: NASA IV - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Mars Exploration Rovers Spirit SOL-18 Anomaly: NASA IV

Description:

A system level fault had occurred on Sol 19 that put the rover in a degraded communication ... the scores for the technology being used and the maturity of ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 12
Provided by: KennethA50
Learn more at: http://klabs.org
Category:

less

Transcript and Presenter's Notes

Title: Mars Exploration Rovers Spirit SOL-18 Anomaly: NASA IV


1
Mars Exploration Rovers Spirit SOL-18
AnomalyNASA IVV InvolvementApril 2004
2
Introduction
  • Purpose
  • This is an informational presentation to discuss
    IVV involvement with the MER program as it
    relates to the memory consumption on Spirit on
    Sol-18
  • Agenda
  • Background on the system memory problem
  • Background on IVV involvement with the MER
    program
  • IVV issues related to the system memory and file
    system
  • IVV Lessons Learned
  • Summary

3
Summary of Spirit Sol-18 System Memory Consumption
  • Sol 18
  • 900 LST The planned DTE HGA communication
    session began.
  • 911 LST Event Reports were received
    indicating uplink errors were occurring. Downlink
    was spotty.
  • 916 LST The signal was lost. This was 14
    minutes earlier than expected
  • 1120 LST Commanded a 30-minute high priority
    HGA communication session. No signal was seen.
  • 1245 LST Commanded an LGA beep. The beep
    occurred as predicted (start and duration).
  • 1618 LST Odyssey UHF pass over Spirit, no
    carrier seen
  • Sol 19
  • 145 LST The MGS UHF communications session
    lasted only 2 minutes and 20 seconds. It did
    start at the correct time but only a repeating
    PsuedoNoise code was present in the data.
  • 439 LST No early morning UHF communication
    session with the Odyssey spacecraft (no signal or
    data).
  • 900 LST No morning HGA DTE communication
    session. No signal or data were detected.
  • 1100 LST Looked for 10 bps LGA DTE
    communication session initiated by a system fault
    protection response. No signal was seen.
  • 1440 LST Commanded beep at 7.8125 bps. Beep
    was seen!
  • 1524 No afternoon UHF communication session
    with the Odyssey spacecraft (no signal or data).
  • 1527 Attempted to command an LGA DTE
    communication session. No signal or data was
    received.
  • A system level fault had occurred on Sol 19 that
    put the rover in a degraded communication state
    and allowed some commanding
  • At this point JPL was able to determine that FSW
    was in a continuous delayed reset loop. The first
    reset occurred during the Sol 18 morning DTE
    session coincident with an actuator checkout
  • Both commanded and autonomous shutdowns were
    failing and the vehicle probably had not shutdown
    in a while

4
Root Cause
  • The root cause was traced to two configuration
    parameters in the VxWorks operating system
  • Configuration parameters of the dosFsLib module3
    permitted the unbounded consumption of memory
    from the system memory heap as the FLASH file
    system was populated with an increasing number of
    files
  • The configuration parameters of the memPartLib
    module4 were set so that the logic would suspend
    the execution of any task that requested memory
    when no additional memory was available
  • This had the undesirable effect of suspending a
    critical task when the memory space was exhausted
  • Other effects included memory corruption,
    inability to turn vehicle off (due to task
    deadlock), repeating system resets
  • Contributing factors included the compressed
    development schedule, unanticipated behavior of
    the FSW, incomplete development (analysis of the
    effects of the dosFsLib parameters was never
    fully completed), test program was not equivalent
    to operational use, and inadequate telemetry

5
IVV Activities for MER
  • Initial assessment of the MER project performed
    in June 2001
  • Results of assessment noted that the file system
    was a very critical portion of the FSW, however,
    the scores for the technology being used and the
    maturity of the software indicated low risk
  • Some portions were rated as high complexity
  • Overall the file system software was within the
    IVV scope though at a low level
  • Initial estimate of the IVV resources was 9-10
    FTEs
  • The MER Project had not budgeted for that level
    of IVV resources
  • Final IVV resources were 4-5 FTEs
  • Reduction in resources necessitated changes in
    the approach to IVV
  • Goal was to cover the MER FSW to a reasonable
    depth so that the IVV Team could feel
    comfortable supporting launch and operational
    readiness reviews for the project
  • Tasking was pulled up to a higher level than
    normal analysis applied at a complete FSW level
    rather than at a software component level
  • Additional issue in regards to a limited number
    of FSW requirement artifacts

6
IVV Findings Related to the System Memory
  • Requirement and test completeness
  • IVV Risk 1 on Requirements (and extended to
    include test) was remaining risk in Significant
    Concern status at time of upload
  • Chief concern was that software requirements
    discovery was not complete and that software had
    not been adequately tested at the time of the
    upload
  • Specific TIMs
  • Specific TIMs were written against the
    insufficient unit tests for portions of the file
    system using the system memory
  • Project asserted testing was complete but without
    documentation
  • These TIMs were still in Open state at the time
    of the final upload
  • Code Complexity
  • Portions of the file system using the system
    memory was consistently reported to be very
    complex
  • Modules were reported to have poor testability
    and poor maintainability
  • Code Stability
  • File system modules were being worked on until
    the last release (R8.1d, 11/20/03)
  • File Meta Engine had 10 of its total code
    changed as late as Release 8.0, and had 9 of its
    total code changed for Release 8.1
  • Note that the file system was not the cause of
    the problem, but brought the lack of memory to
    light and created the task deadlock

7
IVV Concerns over Requirements Test
  • Upload Readiness Review (11/25/03)
  • Plans were to upload final FSW on 12/2/05 review
    was to determine readiness
  • IVV recommended further testing before upload,
    delaying upload past Dec 2
  • Operational Readiness Review (12/5/03)
  • Aggregate of requirement and test issues
    represent a risk being tracked in IVV Risks
  • Final Requirements Risk status was Significant
    Concern (middle of three possible levels)
  • IVV Concern There remains an IVV concern
    about the possibility of requirements-related
    surprises during operations. IVV has a less
    optimistic view of the requirements discovery
    than does the project.
  • Potential Consequence for Surface ops Possible
    loss of science return (Possible loss of
    science return means the situation we are
    currently seeing significant time to detect,
    understand, and correct problems on the surface)
  • Reiteration of 11/25/03 IVV recommendation for
    further testing before upload (which by 12/5/03
    had already occurred, the project having
    proceeded with planned upload on 12/2/03)
  • Recommendation to Continue testing to the extent
    possible
  • Recommendation to Ensure test results are
    adequately reviewed
  • Project emphasis on test as you fly (vs. formal
    unit and requirements-based tests) didnt find
    the problem

8
IVV Lessons Learned
  • Resources
  • The low level of resources being applied to such
    a large and complex project was not sufficient
  • The goal of analyzing the software at a depth
    that would allow the IVV Team to feel confident
    when supporting project readiness reviews had to
    be maintained
  • Forced a shift from a software component approach
    to a more whole system approach
  • Resources for IVV should be such that a software
    component approach can be maintained throughout a
    project SDLC
  • Lack of Artifacts
  • Current IVV Facility processes are very
    requirements driven
  • The lack of FSW requirements artifacts on the MER
    Project affected the IVV work being performed
    and also helped to move the approach away from a
    component level analysis
  • And given that projects are not generally
    required to follow a standardized software
    development life cycle
  • The IVV Facility needs to examine its
    requirements driven approach and generate some
    alternative approaches to performing IVV on
    projects lacking software artifacts

9
IVV Lessons Learned
  • Pursuing Risks
  • Early on the IVV Team documented the
    requirements risk
  • Project would only address specific problems that
    were realization of the risk not the risk itself
    with the IVV Team
  • Otherwise, the planned testing program mitigated
    the risk in the projects eyes
  • The IVV Team was still concerned, but the lack
    of FSW requirements made it difficult to fully
    examine the consequences and likelihood of the
    risk
  • The IVV Team eventually accepted the test
    program as a mitigation to the risk
  • However as milestone reviews neared, the testing
    in some cases had not been completed
  • The project continued testing up to the last
    minute
  • Additionally, the lack of requirements artifacts
    placed the MER Project into the position of
    testing with incomplete requirements
  • Testing was driven more by scenarios generated by
    system engineers such that they felt that the
    system was fully exercised IVV had no insight
    into how the scenarios were developed
  • The IVV Team needs to be more proactive in
    assessing mitigation efforts early in the SDLC so
    as to more effectively support projects
  • Additionally projects should enforce and follow
    good software engineering practices that includes
    good requirements development to support a mature
    test program

10
IVV Contributing Factors
  • The IVV Team needs to be more intimately
    involved with the development team
  • The MER projects compressed schedule created a
    schedule risk from outside parties
  • The IVV team was not able to work directly with
    the developer
  • Additionally there was no access to the
    development issue database or the low level
    testing artifacts that would allow IVV to
    perform a more in-depth analysis
  • Projects need to integrate the IVV process into
    the development process in order to gain maximum
    advantage of the resources being offered
  • More specific attention to COTS products
  • The root cause in this case was the incorrect use
    of a COTS product
  • The IVV team usually analyzes the use of and
    interfaces between COTS and developed code since
    the content of most COTS products is not visible
  • The IVV team was not able to perform that level
    of analysis on this mission due to resource
    constraints

11
Summary
  • The anomaly consumed the available system memory
    and created a deadlock between tasks
  • The IVV approach was modified based on various
    project specific factors that caused the analysis
    approach to be elevated to a full system approach
    rather than the normal software component
    approach
  • Even at the full system approach, the IVV team
    identified potential troubling areas involving
    the system memory usage risk tracking, issue
    tracking, code analysis, requirements analysis,
    test analysis, code complexity, and code
    stability
  • However, the lack of complete requirements
    documents and testing documentation, both
    identified by IVV as project deficiencies,
    hindered finding the specific problem prior to
    upload
  • The IVV Facility is examining the lessons
    learned to determine what actions to take to
    ensure better service on other IVV projects