Confined Disposal Facilities and In Situ Capping - PowerPoint PPT Presentation

About This Presentation
Title:

Confined Disposal Facilities and In Situ Capping

Description:

Confined Disposal Facilities and In Situ Capping Site characterization / selection Engineering design Operational considerations Contaminant pathways and controls – PowerPoint PPT presentation

Number of Views:160
Avg rating:3.0/5.0
Slides: 51
Provided by: Prefer843
Learn more at: http://web.cecs.pdx.edu
Category:

less

Transcript and Presenter's Notes

Title: Confined Disposal Facilities and In Situ Capping


1
Confined Disposal Facilities and In Situ Capping
  • Site characterization / selection
  • Engineering design
  • Operational considerations
  • Contaminant pathways and controls
  • Long-term management
  • Monitoring
  • http//www.youtube.com/watch?vLbh9c0noR4s

2
Potential Contaminant Release Pathways for
Dredging and Upland Disposal
3
Confined Disposal Alternatives
4
Engineering Issues
  • Reduce Contaminant Pathways
  • Disposal pathways
  • Physical disturbance
  • Seepage
  • Optimize Capacity
  • Safely dispose of the greatest amount of material
    in the smallest area

5
Physical Disturbance
  • Excavation and removal of contaminated sediments
  • Erosion and Scour at the disposal site
  • Slope Stability
  • Nature of underlying materials
  • Stability of existing and future slopes
  • Intended end use of site
  • Consolidation and settling
  • Cap Properties

6
Seepage
  • Excess pore water in upland sites
  • Consolidation and compaction induced seepage
  • Groundwater-driven seepage

7
Other Considerations
  • Dredged disposal volume
  • Area of land desired
  • Habitat mitigation requirements
  • Cost comparisons

8
Local Example Ross Island
9
Ross Island Locator Map
10
Aerial Photo
11
(No Transcript)
12
History of the Ross Island Sand Gravel Site
  • July 1926 RISG acquires the islands and ownership
    is established over the area defined by the low
    water line surrounding the islands
  • October 1967 RISG issued removal permit following
    effective date of Oregons removal law
  • 1972 RISG proposed to mine entire islands away -
    denied by Oregon AG
  • 1972 RISG proposed to connect the northern ends
    of the islands forming a private pond - denied by
    COE

13
RISG History Contd
  • 1979 RISGs removal permit amended to include
    fill
  • 1980 City of Portland issued Conditional Use
    Permit specifying details of eventual reclamation
  • 1983 RISG began accepting fill materials from
    outside sources
  • 1992 first confined disposal event of Port of
    Portland dredged sediments

14
(No Transcript)
15
(No Transcript)
16
Typical Cross Section
17
Disposal Methods
18
Potential Contaminant Migration Pathways -
Disposal Processes
19
Potential Contaminant Migration Pathways -
Groundwater Transport (Present and Future)
20
Potential Contaminant Migration Pathways -
Physical Disturbance
21
Groundwater Movement through Cells
22
Potential Groundwater Transport from Containment
Cells
  • Upward groundwater flow
  • Cap design minimizes discharge via this sort of
    flow
  • Predicted discharge concentrations below
    risk-based criteria.

23
Potential Physical Disturbance of Containment
Cells
  • Natural erosion (floods).
  • Human influence (mining).
  • Geotechnical stability.

24
Slope Instability
25
Potential Physical Disturbance of Cells
  • Minimal erosion potential due to a control dike.
  • Mining controls would avoid future impacts.
  • Slopes are presently receiving fills.

26
RISG CDF Conclusion
  • Final decision not yet made about CDF and the
    future of the island as a city park or preserve
  • Engineering studies strongly suggest the CDF is
    presently secure and presents an acceptable risk

27
GREENFill Areas ConsideredYELLOWFill Areas
ProposedREDAreas to be Dredged
28
Wyckoff/Eagle Harbor
29
Wyckoff/Eagle Harbor
  • Bainbridge Island, in Central Puget Sound
  • 3,780-acre site
  • Land use in the area is predominantly
    residential, with some commercial and industrial
    uses
  • The harbor supports several fish resources, a
    wide variety of resident and migratory birds, and
    other wildlife

30
Eagle Harbor
31
Wyckoff/Eagle Harbor
  • Sources of Contamination
  • Inactive 40-acre wood treating facility owned by
    Wyckoff
  • Adjacent 500-acre Eagle Harbor
  • Other upland sources of contamination (Shipyard)

32
Site History
  • Shipyard operated from 1903 to 1959 on the
    northwest shore of Eagle Harbor, resulting in
    releases of metals and organic contaminants.
  • 1905 to 1988, wood treating operations were
    conducted on the southeast shore involving
    pressure treatment with creosote and
    pentachlorophenol

33
Discovery
  • During the 1970s, efforts were made to address
    oil seepage on beaches adjacent to the Wyckoff
  • 1984 NOAA investigations of the Harbor revealed
    that sediment, fish, and shellfish from Eagle
    Harbor contained elevated levels of PAHs

34
The Response to Discovery
  • EPA required Wyckoff to conduct environmental
    investigation activities under RCRA
  • Washington State required immediate action to
    control stormwater runoff and seepage of
    contaminants

35
Response, Contd
  • September 1985 Proposed to the Superfund NPL
  • 1985Washington State Hazardous Waste Cleanup
    Program, (Ecology) Preliminary Investigation of
    sediment contamination in Eagle Harbor

36
Response, Contd
  • 1985 NOAA completed a study relating the
    presence of PAHs in sediment to the high rate of
    liver lesions in English Sole from Eagle Harbor
  • March 1987, Wyckoff Company entered into an
    Administrative Order on Consent with EPA for
    further investigation of the facility (RI/FS)

37
Historical Sources
  • Preservative chemicals were stored in tanks on
    the property.
  • Contamination of soil and ground water at wood
    treatment facility led to seepage into adjacent
    sediments.
  • Wastewater discharged into Eagle Harbor for many
    years storing treated pilings and timber in the
    water continued until the late 1940's.

38
Contaminants of Concern
  • Shipyard Levels toxic to marine life
  • Polyaromatic hydrocarbons (PAHs) and other
    organics
  • Heavy metals such as mercury, copper, lead, and
    zinc

39
Contaminants of Concern
  • Wyckoff facility, soil and groundwater are
    contaminated with
  • Creosote
  • Accompanying PAHs
  • Pentachlorophenol (PCP penta)

40
CERCLA Operating Units
  • 1991, EPA defined three operable units at the
    Wyckoff/Eagle Harbor site
  • Wyckoff (OU1)
  • East Harbor (OU2)
  • West Harbor (OU3)
  • Wyckoff Facility groundwater (OU4, 1994)

41
Selected Remedial Actions
  • Dredging, excavating dewatering intertidal
    sediment that exceeds levels of 5 mg/kg mercury
    and/or lower, moderate PAH concentrations
  • Approximately 1,000 to 7,000 cubic yards
  • Solidification/stabilization, as necessary, to
    comply with disposal rules
  • Transporting sediment, which cannot be treated to
    meet rules offsite for disposal at a
    RCRA-permitted (Subtitle C or D) landfill

42
Remedial Actions (contd)
  • Treating dewatering wastewater onsite using
    carbon adsorption before discharge into the
    harbor
  • Capping the sediment in areas of high concern
    with a 1- meter thick layer of clean sediment
  • Placing a thin layer of clean sediment in
    subtidal areas of low to moderate concern to
    enhance natural sediment recovery

43
Remedial Actions (contd)
  • Long-term environmental monitoring
  • Institutional controls to prevent exposure to
    contaminated fish and shellfish.
  • The estimated cost is up to 16,000,000
  • Most work done but site still on NPL

44
Eagle Harbor Cap Areas
45
East Harbor Capping (OU2)
  • Sept 1993-March 1994, EPA and the Corps of
    Engineers covered contaminated sediments in the
    East Harbor
  • Cap of clean sediment at water depths of 17 m and
    13 m, respectively.
  • Sediment was dredged from the Snohomish River as
    part of an annual project for ship navigation

46
Capping Methods
47
Capping Methods
  • Split Hull Fast but uneven.

48
Capping Methods
  • Hydraulic washoff

49
West Harbor CDF (OU3)
50
Final sediment cleanup actions
  • Monitoring the success of natural recovery in
    intertidal areas
  • Monitoring contaminated areas where active
    remediation cannot be implemented.
Write a Comment
User Comments (0)
About PowerShow.com