Title: Infrastructure Projects in Russia
1Infrastructure Projects in Russia
- Vladimir Liberzon, PMP
- Spider Project Team
2Introduction
- In this presentation we will discuss proven tools
and techniques that are applied to management of
large-scale infrastructure projects and programs
in Russia - The questions during the presentation are
welcomed!
3Part 1
- Large-scale Infrastructure Programs in Russia
- Overview
4Infrastructure Programs in Russia
- Russia launched many large-scale state
infrastructure projects last years. - They include
- Development of Sochi region as Recreation Area
and preparation of Winter Olympic Games 2014, - Construction of trans-Syberian highways,
- Construction of Dams and Power Plants around
Russia, - Development of Russian Pacific Area and
preparation of Asia-Pacific Summit in 2012, - Nuclear Power Plants Construction Program, etc.
5Infrastructure Programs in Russia
- These programs have multi-billion budgets,
involve many organizations and include many
inter-related projects. - Our company is involved in management of almost
all of them. We participate as consultants,
coaches and members of program management teams. - Management of such programs is very complex and
we will discuss its organization and management
approaches that proved their efficiency.
6 7Winter Olympic Games 2014
- Preparation of Winter Olympic Games 2014 Program
includes 213 construction projects. - They include
- Construction of Olympic objects like stadiums,
arenas, tramplines, ski areas, etc. - Transportation infrastructure including roads,
rail roads, airport - Utility infrastructure,
- Energy infrastructure including Power Plants,
electric lines, gas pipelines - Hospitality infrastructure including Olympic
villages, hotels, parks and recreation areas,
8Winter Olympic Games 2014
- Sochi Olympic Games will be held at two major
areas - one of them is on-shore cluster with Stadiums for
ice hockey, figure skating, curling, and similar
sports, - Mountain cluster will be host for slalom,
downhill, biathlon - These clusters will be connected by auto and rail
roads through mountains. Construction of this
roads includes six tunnels and eight bridges
9Winter Olympic Games 2014
- Development of Sochi area will also include
- gas pipeline construction,
- creating of area transport infrastructure
(widening of existing rail road, - construction of roads on the shore and in the
mountains)
10 11Trans-Syberian Highways
- Only the railway connects Russian Pacific Area
with the rest of Russia. - The program launched now will connect all parts
of Russia by modern highways. - Road construction projects are simultaneously
launched in Russian Pacific Area and in Siberia.
12Trans-Syberian Highways
- In the Pacific Area the program includes
following highway construction projects
Amur Chita - Khabarovsk 2097 km
Kolyma Yakutsk - Magadan 2021 km
M-56 Lena Never - Yakutsk 1157 km
M-60 Ussuri Khabarovsk - Vladivostok 756 km
Vostok Khabarovsk - Nakhodka 824 km
13Trans-Syberian Highways
- There are several dozens construction companies
that build these roads. - The program is managed by specially created state
owned management company.
14Boguchansk Dam
15Boguchansk Dam
- Boguchansk Dam in the middle of Siberia on Angara
river is one of the largest. - Planned capacity is 3000 Mv
- Length exceeds 2.5 km,
- Artificial lake will cover 2,326 km2
16Development of Russian Pacific Area
- Russian Pacific Area Development Program has top
priority. - Russian Government invests huge money to develop
this area that was always remote and unpopulated. - This program will create a new face for
Vladivostok, Russian Pacific Capital. - Two huge bridges over the ocean will be built.
17Development of Russian Pacific Area
- Bridge to Russkiy Island
- Total Length - 3100 m
- Central Part - 1104 m
- Width of the road - 23,8 m
- Pylon Height - 320 m
- Height over sea - 70 m
18Other Programs
- Russia plans to invest more 60bln in the
construction of new Nuclear Power Plants - Russia plans to construct high speed railway
between Moscow and St. Peterbourg - Russia invests in the development of modern
technologies (Nano technologies in particular) - Economic crisis somewhat slowed the development
but major programs did not stopped.
19Program Management
- All large-scale programs are managed by specially
created management companies - Olimpstroy for Sochi 2014
- Far East Directorate for Pacific Development
Program, - Far East Road Construction Directorate,
- Atomenergoprom for Nuclear Power Plants Program,
- Etc.
- Management of Russian large-scale programs is
based on similar approaches that we will discuss
in this presentation.
20Part 2
- Program, Portfolio Management System Organization
21Program and Portfolio Management Requirements
- To make Programs and Portfolios manageable there
are certain requirements to all Program/Portfolio
participants and projects that include - Common methodology shall be used for scheduling,
budgeting, reporting and analyzing project data, - The same or compatible PM software shall be used,
- The same WBS templates shall be applied to all
projects in the program/portfolio, - The same resource, cost, material dictionaries
shall be used in all schedule models and reports, - The same production norms and unit costs shall be
used for contracting and estimating project
performance
22Program Management Office
- PMO is an organizational unit to centralize and
coordinate the management of projects under its
domain. This unit was created in every Program
management organization. - Main departments of PMO (by functions)
- Methodology
- Analysis
- Correspondence and Archives
- Program/Portfolio Management
23PMO Methodology Department
- Main functions of Methodology department
- Development and actualization of the Project
Management Guidelines and other Program
management standards and requirements, - Organization of Project staff training,
- Consulting, coaching, auditing Program
participants - Development and actualization of the organization
knowledge base.
24PMO Analysis Department
- PMO Analysis department
- Develops and implements Program dictionaries and
reference-books for costs, resources, materials - Develops project WBS and other templates
- Helps project planners with creating project
computer model, project scheduling and budgeting,
performance monitoring and reporting
organization, - Develops and applies standards for group work
with the Program files and data.
25PMO Analysis Department
- PMO Analysis department
- Develops and works with the Program computer
model, - Regularly collects and analyzes actual data,
- Manages Program computer models archives,
- Supplies project stakeholders with the
performance reports and other necessary
information, - Maintains PMIS and data safety.
26PMO Archive Department
- PMO Communication and Archive department
- Manages communications with program stakeholders,
- Manages program archives,
- Creates and maintains the library of past
projects archives.
27PMO Program Management Department
- PMO Program Management department functions
- Program Scheduling and Management,
- Management of project priorities,
- Management of Program Risks,
- Dealing with conflicting and competing project
requirements, - Analysis of change requests and Integrated Change
Control
28PM Information System
- Most large-scale programs in Russia are managed
using Spider Project software that is considered
as most functional, powerful and flexible system. - Spider Project usage is required from all
programs participants. It makes data
consolidation and management easier and more
reliable.
29PM Information System
- One of the reasons for selecting Spider Project
as the program management tool is based on its
ability to work with physical quantities
(volumes) of work to be done on project
activities. - It helps to implement corporate norms like unit
(physical) costs, unit material requirements,
resource productivities (units per hour), etc. - Spider Project permits to create program
(corporate) templates, dictionaries, and
databases (reference-books) that are necessary
for proper program management.
30Part 3
31Data requirements
- The requirements to the data that are used for
program planning and control may be divided into
two main groups - High level requirements based on
program/portfolio management needs, - Low level requirements that shall be applied to
creating project computer models. - High level requirements consider data
organization, - Low level requirements cover details and
instructions on creating project computer models.
32Organizing data
- The same Project, Phase, Activity, Resource,
Material, and Department coding structures are
used in all projects, - Resources that are used in all projects belong to
the program (corporate) resource pool, - Resources of the same type share the same
characteristics (like cost, production rates,
material consumption per work hour),
33Organizing data
- Program management systems have specific
requirements that are vital for successful
implementation. - It is necessary to be sure that
- WBS structures that are used in different
projects of the program are compatible, - Project costs have the same structure in all
projects (same cost components are used), - Cost accounts are the same in all projects,
34Organizing data
- Activities of the same type have the same
characteristics in all projects (like unit cost,
material requirements per work volume unit,
etc.), - Typical resource assignments have the same
characteristics in all projects (like
productivity, cost and material requirements), - Typical (repeating) processes are modeled in the
same way in all projects, - Project archives are kept and stored as required.
35Organizing data
- These requirements are set on the Program level
and are mandatory for all program participants. - Templates, reference-books, coding systems etc.
are developed in the Program Management Office.
36Program Databases (Reference-Books)
- Activities, resources and resource assignments
belong to the same type if they share the same
characteristics like unit costs, material
consumptions per work volume unit, productivity,
etc. - Program Management office creates Databases or
Reference-books that contain those parameters
that shall be used for planning of all projects
of the Program.
37Program Databases (Reference-Books)
- Program Reference-books include at least
- Activity cost and material requirements per
volume unit for all activity types, - Resource assignment cost and material
requirements per volume unit for all assignment
types, - Resource assignment productivities for all
assignment types, - Resource assignment work loads for all assignment
types.
38Typical Fragment Library
- Project fragments usually describe typical
processes and technologies that are used more
than once as small projects. - Creating project computer models using the
library of typical fragments helps to avoid
inconsistencies and assures that the project
model follows Program standards. - A library of typical fragments is very important
tool for the development of common culture and
management standards.
39Program Templates
- Program management has to be based on the program
standards. These standards include not only
estimates of the typical activity and assignment
parameters process and but also project
templates. - Besides Program Management Guideline developed in
the Program Management Office describes Program
management routine (when and what reports shall
be presented, performance review meetings
schedule, etc.) and change management processes.
40Organizing data
- This slide shows WBS template for construction
projects required by Program Management Office of
Olimpstroy.
41Project Data Structure
- The main elements of any project computer model
include - project activities,
- activity dependencies,
- resources and their assignments,
- calendars,
- Costs,
- Project, Work, Resource and Cost Breakdown
Structures.
42Project Data Structure
- Now we will discuss special requirements to
project data that are necessary for most
infrastructure projects. - Some of these requirements are used in the
process of project schedules assessment.
43Activity Data
- Usually project activities are characterized by
their duration or effort. But in most cases and
especially in construction projects it is
necessary to set activitys physical volume (or
quantity) of work. - Activity volume can be measured in meters, tons,
etc., planned work hours, percents or any other
units. - Unlike activity duration, activity volume does
not depend on assigned resources. - Project performance reports always include actual
volumes that were done on project activities.
44Activity Data
- By introducing activity volumes, we will be able
to use Program/corporate databases that define - cost and material requirements per activity
volume unit for different activity types. - Resource assignment productivity or production
rate for different assignment types. - Activity duration is calculated basing on
activity volume and assigned resource
productivities. PMBOK Guide call this method as
Parametric Estimating of Activity Duration.
45Dependency Data
- Many infrastructure projects include linear
construction (roads, railroads, pipelines, etc.).
In such projects many types of work can be done
in parallel but on some distance between them.
Such logical dependency may be described as Start
to Start link with Volume Lag. - But Start to Start link shall be supported by
Finish to Finish link to prevent preceding
activity catching succeeding activity. So it is
necessary to set more than one link between
activities and to check if Start to Start links
are supported by Finish to Finish links.
46Resource Data
- Resources are divided into two classes
- renewable (human resources and mechanisms) and
- consumable (materials).
- It makes possible to assign materials to
resources defining their consumption per resource
work hour or work volume unit. - Example a car consumes gas.
47Resource Data
- Besides the individual resources there is a need
to set resource crews (we call them
multi-resources) and resource skills (roles). - Multi-resources are the settled groups of
resources working together. - Multi-resources can be assigned on activity
execution. - Assigning multi-resource project planner assigns
all resources that belong to this multi-resource.
48Resource Data
- If resources can do the same work then they
belong to the same Skill set or Resource
Assignment Pools. - Resources with the same skills are
interchangeable though they may have different
productivities performing the same activities. - One resource can belong to many Skill sets.
- Example excavators of different types that may
be used on earth moving works.
49Assignment Data
- Resource Assignments have their own
characteristics including - Resource productivity on assignment,
- Assignment cost (may be fixed, per unit of work
volume, or per hour), - Assignment material consumption (fixed, per unit
of volume, or per hour), - Resource workload ( or resource work time that
is required on concrete assignment)
50Assignment Data
- Assigning resources to activities implies the
notion of a team - a group of resources working
on an activity together. The team can include
individual resources, multi-resources and skills. - If resources belong to different teams then they
can work independently of each other at different
time. This is the way to simulate working in
different shifts on the same activities.
51Assignment Data
- Resources can consume materials in the process of
their work. Besides, materials can be assigned to
activities or resource assignments directly. In
some projects it is necessary to simulate not
only material consumption but also production or
supply of resources and materials on activities
and assignments.
52Calendars
- Separate calendars can be set for all activities,
resources and time lags. - Availability of all these calendars is important
for the proper project performance simulation.
53Cost Data
- Usually it is not enough just to define activity
and resource costs. It is necessary to know
project expenses and revenues, what will be spent
on wages, on machinery and equipment, on taxes,
etc. Sometimes it is necessary to allow for
multiple currencies. So there is a need to define
and assign cost components. - Cost Structure shall be the same in all projects
belonging to the Program and is defined on the
Program level.
54Material, Resource and Cost Centers
- There is a need to get different reports on the
groups of cost components, materials and
resources. That is why it is necessary to define
Cost, Material and Resource Centers - Material center can include any group of
materials. - Resource center can include any group of
resources. - Cost center includes selected cost components.
- Using material, resource, cost centers permits to
get group reports (all pipes, all workforce) and
to manage parallel budgets (actual expenses,
contract costs, etc.).
55Multiple WBS
- It is also very useful to have an opportunity to
get project reports that aggregate project data
different ways. Usually we use at least three
Work Breakdown Structures in our projects based
on project deliverables, project processes and
responsibilities. - At least one WBS is mandatory and required by
Program Management Office. Others may be selected
by project management teams.
56Contract Breakdown Structure
- Contract Breakdown Structure is the powerful tool
for management of contract relationships. The
same organizations are involved in multiple
projects and in different programs. - Contract Breakdown Structures are used to get
reports on the contract performance and contract
cash flows.
57Cost Breakdown Structure
- Cost Breakdown Structure for contract costs is
defined by Program Management Office. - Contractors can add cost components and create
Cost centers for planning and tracking real
expenses. - We manage not only expenses but also financing.
- Program managers control program, project and
contract cash flows.
58Project Archives
- The planners should be able to store project
versions and to analyze the progress in project
execution, comparing current project and
portfolio schedules not only with the baseline
but also with any previous version. It enables to
assess the progress in project execution for the
last week, last month, last year, compared to the
baseline, etc.
59Typical Fragment Library
- Project fragments usually describe typical
processes and technologies that are used more
than once as small projects. - Creating project computer models using the
library of typical fragments helps to avoid
inconsistencies and assures that the project
model follows corporate standards. - A library of typical fragments is very important
tool for the development of common culture and
management standards.
60Part 4
- Program/Project Scheduling
61Scheduling Tasks
- Program/Project scheduling without the resource
limitations taken into the consideration, - Program/Project resource constrained scheduling
(resource leveling), - Determination of feasible time floats for
Program/Project activities and those activities
that are critical, - Determination of the Program/Project cost,
material and resource requirements for any time
period,
62Scheduling Tasks
- Determination of renewable resources utilization
in time, - Risk analysis and development of the
Program/Project schedule and other parameters
allowing for the risks, - Program/Project performance measuring,
- Program/Project performance analysis and
forecasting main project parameters.
63Tasks to solve
- The problem of project schedule development
without allowing for resource constraints has a
correct mathematical solution (Critical Path
Method), which would be the same for all PM
packages, provided that initial data are
identical. All other problems are solved using
different approaches and yielding different
results.
64Resource constrained scheduling
- Resource constrained schedules produced by
different PM software are different. The software
that calculates shorter resource constrained
schedules may save a fortune to its users. - That is why we pay most attention to
resource-constrained schedule optimization.
65Resource constrained scheduling
- The schedule stability is no less important,
especially at the project execution phase. - That is why our project management software
Spider Project features an additional option -
the support of the earlier project version
schedule (keeping the order of activity execution
the same as in selected earlier project schedule).
66Sample Project before leveling
- Traditional notion of Critical Path works only in
case of unlimited resources availability. - Let us consider a simple project consisting of
five activities, presented at the next slide. - Activities 2 and 5 are performed by the same
resource.
67Sample Project after leveling
- Please pay attention to activities that became
critical. Now delaying each of the activities 1,
2 and 5 will delay the project finish date. We
call these activities Resource Critical and their
sequence comprises Resource Critical Path.
68Resource Critical Path
- In many projects it is necessary to simulate
financing and production, and calculate project
schedules taking into account all limitations
(including availability of renewable resources,
material supply and financing schedules). True
critical path should account for all schedule
constraints including resource and financial
limitations.
69Resource Critical Path
- We call it Resource Critical Path (RCP) to
distinguish it from the traditional
interpretation of the critical path definition. - The calculation of RCP is similar to the
calculation of the traditional critical path with
the exception that both early and late dates (and
corresponding activity floats) are calculated
during forward and backward resource (and
material, and cost) leveling.
70Resource Constrained Floats
- This technique permits to obtain resource
constrained floats. - Activity resource constrained float shows the
period for which activity execution may be
postponed within the current schedule with the
set of resources available in this project.
71RCP and Critical Chain
- It appears that by adding financial and supply
constraints to the Critical Chain definition as
well as the way of the Critical Chain
calculation, we will obtain something very
similar to RCP.
72Part 4
73Project Success Criteria
- If project success criteria are set as finishing
project in time and under budget then proper
decision making will be complicated. - Project managers will not be able to estimate the
effect of their decisions to spend more money but
to finish the project earlier. - If some project is business oriented then this
project has to have business criteria of its
success or failure.
74Project Success Criteria
- One of potential options to set the profit that
should be achieved at some point in time basing
on the forecast of the revenues that will be
obtained after the project will deliver its
results. - Such success criterion will permit to weight time
and money making managerial decisions.
75Project Success Criteria
- At the next slide you may see the project
schedule that is calculated without allowing for
project financing and supply restrictions. There
are periods when project has no money to proceed
and necessary materials (wall frames) are absent.
76Project Success Criteria
- But if project manager will find enough money and
materials then project total profit to some
imposed date will be close to 219,000.
77Project Success Criteria
- If to calculate project resource, financing and
supply constrained schedule than total profit
will become more than 25,000 less.
78Project Success Criteria
- Maybe it is reasonable to borrow money or to find
some other solution? - To be able to weight options and to choose the
best it is necessary to simulate not only
expenses. This approach is especially important
for portfolio management.
79Part 5
- Risk Analysis
- Success Driven
- Project Management
80Why risk analysis
- Our experience of project planning shows that the
probability of successful implementation of
deterministic project schedules and budgets is
very low. Therefore project and portfolio
planning technology should always include risk
simulation to produce reliable results.
81Risk Simulation
- Risk simulation may be based on Monte Carlo
simulation or use three scenarios approach that
will be described further.
82Risk Simulation three scenarios approach
- A project planner obtains three estimates
(optimistic, most probable and pessimistic) for
all initial project data (duration, volumes,
productivity, calendars, costs, etc.). - Risk events are selected and ranked using the
usual approach to risk qualitative analysis.
Usually we recommend to include risk events with
the probability exceeding 90 in the optimistic
scenario, exceeding 50 in the most probable
scenario, and all selected risks in the
pessimistic scenario.
83Risk Simulation three scenarios approach
- The most probable and pessimistic project
scenarios may contain additional activities and
costs due to corresponding risk events and may
employ additional resources and different
calendars than the optimistic project scenario.
As the result project planner obtains three
expected finish dates, costs and material
consumptions for all major milestones.
84Desired Parameters
- They are used to rebuild probability curves for
the dates, costs and material requirements. - Defining desired probabilities of meeting project
targets a project planner obtains desired finish
dates, costs and material requirements for any
project deliverable.
85Success Probabilities
- If the targets were approved then it is necessary
to calculate the probabilities of meeting
required project targets. If they are reasonable
then they may be accepted. - Probabilities to meet approved project targets we
call Success Probabilities. These targets may
include all project parameters that will be
controlled (profit, expenses, duration, material
consumption).
86Baseline
- Target dates do not belong to any schedule.
Usually they are between most probable and
pessimistic dates. A set of target dates and
costs (analogue of milestone schedule) is the
real project baseline. - But baseline schedule does not exist!
87Buffers
- We recommend to use optimistic schedule for
setting tasks for project implementers and manage
project reserves. - Project planner obtains not only the set of
target dates but also a critical schedule a
project schedule calculated backward from target
dates. The difference between current and
critical dates shows current schedule contingency
reserves (buffers).
88Sample Critical Schedule
- There are time, cost and material buffers that
show contingency reserves not only for a project
as a whole (analogue of Critical Chain project
buffer) but also for any activity in the
optimistic project schedule.
89Success Probability Trends
- The best way to measure project performance is to
estimate what is going on with the project
success probabilities. If they raise it means
that contingency reserves are spent slower than
expected, if they drop it means that project
performance is not as good as it was planned and
corrective actions are needed.
90Success Probability Trends
- Success probabilities may change due to
- Performance results
- Scope changes
- Cost changes
- Risk changes
- Resource changes
91Success Probability Trends
- Thus success probability trends reflect not only
project performance results but also what is
going on around the project. - We consider success probability trends as the
really integrated project performance measurement
tool.
92Success Probability Trends
- Success probability trends may be used as the
only information about project performance at the
top management level because this information is
sufficient for performance estimation and
decision making.
93Success Driven Project Management
- We call the described methodology Success Driven
Project Management.
94Success Driven Project Management
- If project performance is estimated by success
probability trends then project managers are
encouraged to resolve uncertainties ASAP. This
can increase success probabilities even with
activity finish delays cost overruns. - Postponing problem activities leads to negative
trends in success probabilities.
95Success Driven Project Management
- This attribute of success probability trends is
especially useful in new product development
project management. - On the corporate level it is very useful to know
trends and current probabilities of meeting
targets for all portfolio projects.
96Part 6
97Corporate PM Tools and Techniques
- Organizing data in a way that supports proper
resource work simulation and application of
corporate norms and standards. - Creating a set of reference-books and the fragnet
libraries that are obligatory for creating
project computer models.
98Corporate PM Tools and Techniques
- Calculating Resource Critical Path and resource
constrained floats for every project and project
portfolio. - Risk assessment and simulation.
- Defining project success and failure criteria
that reflect achieving project business goals.
99Corporate PM Tools and Techniques
- Defining project targets (and corresponding
contingency reserves) that may be achieved with
reasonable probabilities. - Regularly recalculating the current probabilities
of meeting project targets during execution and
analyzing success probability trends. Negative
success probability trends require corrective
actions.
100Success Driven Project Management Flowchart
REFERENCE-BOOKS Resources Materials Cost
Components Cost Breakdown Structure Resource
Breakdown Structure Calendars Resource
Productivities Unit Costs Material Requirements
per Volume Unit Skills Multi-Resources
Code Structures
Typical Fragnet Library
Project Schedule
WBS Templates
Project Budget
Project Portfolio
Risk Analysis
Risk Register
Issue Register
Success and Failure Criteria
Performance Reports
Success and Failure Probabilities
Corrective Actions
-
Success Probability Trends
Work Authorization