Title: Technical Committee on Environet J.L.Goswami-BARC-India
1Technical Committee on Environet
J.L.Goswami-BARC-India
2Indian nuclear power programme
- For sustainable energy security, recycling of
fissile /fertile element in spent fuel and
capitalisation (utilisation) of vast thorium
reserves is must - Three stage strategy involving closed fuel cycle
- Ist stage utilisation of nat.uranium in PHWRs
and production of Pu - 2nd stage use of Pu in fast breeder reactors and
utilisation of thorium - 3rd stage utilisation of U-233 and Pu in AHWRs
3Indian Nuclear Power Programme
15 PHWRs 2 BWRs (4120 MWe) FBTR (40 MWth) KAMINI (30 kWth)
Under Construction 3 PHWRs 2 LWRs (2660 MWe) Under Construction PFBR (500 MWe) Under Planing AHWR (300 MWe)
4 Indian perspective on Decommissioning and
Environmental Remediation
- Indian nuclear facilities have not yet reached
the stage of final retirement - The emphasis is on ageing management and life
extension of facility by refurbishing,
modifications and equipment replacements. - These practices have been successfully deployed
for Research Reactors , NPPs and Radiochemical
plants - Research Reactor CIRCUS
- Tarapur Atomic Power Station
- Reprocessing Plant Kalpakkam
- Presently following facilities are under
planning for decommissioning - Waste Immobilisation Plant Tarapur
- Advance Vitrification Facility Tarapur
-
-
- Some nuclear facilities have also been
decommissioned for putting up advanced plants- - Thoria reprocessing plant at Trombay
- Research Reactor Zerlina
- Research reactor Purnima
5Refurbishing of Research Reactor CIRUS
- Refurbishing undertaken during 1997-2002 after 30
years of operation - Assessment review was carried out during1992-97
for structures, systems and components in
respect of seismic requirement , stored energy in
graphite reflectors ,safety analysis etc - Total cost of refurbishing was 10 of a new
replacement reactor and life extended for 20
years - Refurbishing Plan and Preparatory Work included
Development of Procedures Special Tools and
Regulatory Review
6Refurbishing of Research Reactor CIRUS
- Remote repairs for in-accessible areas
- Cover gas pipe flange joints replacement
- Leak rectification of aluminium thermal shield
coolant pipe - Primary coolant pipes replacement
- Ball tank leak repairs
- Extensive external corrosion protection measures
- Remote tools like remote sealing clamp tool ,
gouging tool and tightening tool were developed
and mock trials taken
7Partial Decommissioning of Fuel Reprocessing
Plant at Kalpakkam
- The plant remained shut down since Aug 2004 for
revamping and modifications. - Modifications have been carried out to improve
plant performance and to address safety related
issues encountered during previous campaigns. - The radiation fields inside hot cells were around
1-5 R/hr .The total man-Rem consumed was 760 Rem - Total Solid waste generated Cat-I 2400 m3,
Cat-II 17 m3, Cat-III 10 m3 , Cat-IV 12 m3
8Decommissioning of Fuel Reprocessing Plant
Trombay
- Partial decommissioning was taken up in 1974 to
increase the capacity and life of the plant. - Removal /emptying of recoverable nuclear material
from the system/waste streams - Detailed radiation survey of areas/equipment and
piping - Indirect decontamination of process equipment and
piping using chemicals such as nitric acid, sod
hydroxide etc to remove bulk of radioactivity - Further decontamination to external surfaces by
water jet and subsequent radiation mapping - Dismantling of equipment and piping employing
remote gadgets and for difficult positions
manually by contact dismantling - Installing the new equipment and piping
- Segregation of radioactive solid waste
- Management of the liquid waste
- The experience gained was valuable in identifying
the design improvements such as Plant layout for
removal of components, provisions for radiation
survey preparedness in waste handling
9Decommissioning of Reprocessing Plant, Trombay
- Six out of the eight process cells were
decontaminated, decommissioned, and
reconditioned, reducing the radiation level to
the minimum possible extent and also made all the
surfaces of the process cells free of
contamination to facilitate the erection of
equipment and piping for the new plant, without
undue exposure to the plant personnel.
10Decommissioning of a Thorium Processing Facility
at Trombay
- Plant started in 1955 to process natural thorium
and due to ageing and excessive corrosion was
decommissioned in 2000 - Initial Radiation field around 5-300 mR/hr
-
- The steps undertaken were decontamination and
removal of tanks equipments from the plant with
subsequent dismantling of civil structures - Segregation and disposal of radioactive waste .
- Radioactive solid waste quantity of 2150 m3
consisting mainly of 70 concrete and 30 as
metallic waste was disposed in NSDF
11Tank Remediation by Ion Exchange
- A trailer mounted mobile IX unit for treatment
of alkaline ILW consisting of - Shielded IX Columns
- Piping and instrumentation
- Shielded enclosure
- Ventilation for enclosure
- Radiation monitoring
- Remotisation
12Decommissioning Robot Remote forklift
13Research and development efforts on Environmental
Remediation
- Analytical techniques for measurement
(monitoring) of residual activity - Treatment schemes for tailings from uranium
extraction (mining/milling) - Modelling studies on activity migration and
treatment schemes /processes for soil
decontamination
14 Challenges ahead
- Development of remote cutting devices for steel
plates, pipes, concrete etc - Development of underwater tools for
decontamination and dismantling - In the wake of changed policy involving
multinational participation some facilities may
be decommissioned to the green field stage
including environmental remediation - Management and disposal of Radioactive Waste and
final repository site selection and construction
15Thank You