Title: Matei Purice
1Multi-tier Dispute Resolution
Mechanisms Enforcement Issues
- Matei Purice
- Associate
- Competence Competence Principle.
- Recurring Issues
- ICC YAF Conference, Bucharest
- 27 September 2010
2Multi-tier Dispute Resolution Mechanisms -
Enforcement Issues
- What is a multi-tier dispute resolution clause?
- When should such a clause be inserted in a
contract? - Are all the tiers enforceable?
- Scenario I Final tier is arbitration
- Scenario II Final tier is state court litigation
The Romanian case - Special considerations for drafting the multi
tier dispute resolution clause
3What is a multi-tier dispute resolution clause
(MTDRC)
- Contractual clause dealing with the settlement of
disputes between the contracting parties. - Provides for distinct stages and separate
procedures for solving the dispute.
4The typical ingredients of a MTDRC
- Stage 1 good faith negotiations or
consultations between the parties
for a certain period of time - Stage 2 Mediation, conciliation or other form of
alternative dispute resolution (ADR)
including binding but not final
procedures such as expert determinations /
dispute boards, etc. - Stage 3 Arbitration or state court litigation.
5Rationale of having a MTDRC in the contract
- Long term complex projects particularly in the
construction sector. - The complexity of such projects entails the
possibility of having very different issues under
dispute bearing very different monetary values. - The advantages of having a MTDRC in such
contracts - Tailor-made system of dispute resolution
encompassing appropriate methods of solving
disputes for each type of disputes that might
arise - Various mechanisms aiming at solving the disputes
as quick and cost effectively as possible.
6Examples of MTDRC in very complex projects
- The Channel Tunnel project
- 2 stages
- A panel of three independent experts who would
render a written decision within 90 days - Arbitration
- The Hong Kong Airport Core Programme
- 4 stages
- Decision of the Engineer
- Mediation
- Adjudication through a formal evidentiary
proceeding with a written decision within 42 days - Arbitration
7Examples of MTDRC in standard forms of contracts
- FIDIC Standard form of contracts (1999 edition)
- Adjudication
- Amicable Settlement
- Arbitration
- World Bank Standard Bidding Documents for the
Procurement of Works - Adjudication
- Amicable Settlement
- Arbitration
8The Subject of Inquiry
- What are the consequences if a party leapfrogs
the initial tiers going directly to arbitration
or, as the case may be, state court litigation? - Are the first tiers enforceable?
9Scenario I Arbitration as the final tier the
ICC case
- Two degrees of control may be envisaged
- Dismissal of the claim by the ICC Court under
Article 6.2 - In the few cases dealing with the issue, the
Court either found that prima facie an
arbitration agreement existed or that the issue
did not relate to the existence or validity of
the arbitration agreement and therefore referred
the matter to the arbitral tribunal. - Determination of the issue by the ICC Tribunal by
virtue of the competence-competence principle - Non fulfillment of a conciliation step
- generally depends on the wording of the clause
(mandatory vs. optional) and on the facts of the
case (conduct of the parties). - Non fulfillment of an intermediary adjudication
procedure such as expert determination / dispute
board - Inadmissibility (ICC Case No. 6238 and 6535)
- Prematurity (ICC Case No. 6276 and 6277)
- Staying of the proceedings and ordering the
parties to go and fulfill the prior procedures.
10Scenario I Arbitration as the final tier the
ICC case
- ICC Case No. 9977 (Final Award of 22 June 1999)
prior amicable settlement procedure at senior
management level for 14 days - A prior process like the one set forth in the
Agreement, rather implies a an attitude and
behavior of the parties inspired in a true and
honest purpose of reaching an agreement - ICC Case No. 4840/1986 Clause 67 of the FIDIC
Conditions of Contract (second Edition)
mandatory prior recourse to an engineer - Such submission of claims in the first place
to the Consultant for settlement is required
under Clause 67 and is a condition precedent to
filing arbitration with the I.C.C., and that it
appears, therefore, that the Plaintiffs claims
for Phase II were prematurely and unduly referred
to arbitration, and consequently this Tribunal
does not have jurisdiction thereover.
11Scenario I Arbitration as the final tier the
ICC case
- Particular circumstances
- The ICC ADR Model Clause 4 - Obligation to submit
dispute to ADR, followed by ICC arbitration as
required - The ICC Dispute Board Model Clause
12Scenario I Arbitration as the final tier - a
CCIR case
- The arbitral clause in the contract provided for
a mandatory conciliation procedure prior to
commencing arbitration. - Respondent objected to Claimants request for
arbitration arguing that such is premature given
the non-fulfillment by Claimant of the prior
negotiation procedures. The arbitral tribunal
held - By contrast to the mandatory conciliation
procedure envisaged by Article 7201 of the Civil
Procedure Code applicable in commercial disputes
under the jurisdiction of the state courts, in
arbitral matters the failure to fulfill the prior
conciliation step, provided by the parties, does
not entail a rejection of the claim as premature
or, as certain state courts have held, as
inadmissible but rather imposes, by virtue of the
mandatory force of the contract, that such
deficiency is remedied by ordering the claimant
to first carry on the conciliation procedure. - (CCIR Case no. 201/2007 Interlocutory award of
November 1, 2007)
13Scenario II State court litigation as the final
tier
- Romania - MTDRC providing for conciliation
followed by state court litigation - The issue Enforceability of the conciliation
step - Differences between the provisions of Article
7201 of the Civil Procedure Code (mandatory
conciliation procedure applicable in commercial
cases) and conventional agreements for
conciliation - Article 7201 is the minimum requirement under the
law - The parties may provide for a more detailed
conciliation procedure but have to follow at
least the requirements of Article 7201 - The court may decide that the claim is
- Inadmissible
- Premature
14Scenario II State court litigation as the final
tier
- Romania - MTDRC providing for mediation followed
by state court litigation - The issue Enforceability of the mediation stage
- Possible approaches
- May the judge stay the court proceedings?
- Law No. 192/2006 on mediation
- Article 6 provides that the judicial and
arbitral authorities as well as other entities
having judicial attributions inform the parties
of the possibility and advantages of recurring to
mediation and guides them to follow such means in
order to settle their dispute. - Article 62 provides that (in civil matters!) the
judge will stay the proceedings in order to allow
the pursuance of the mediation procedure - The New Civil Procedure Code (Not yet in force)
Article 21 The judge will recommend the parties
the amiable resolution of the case through
mediation, in accordance with the special laws.
15Scenario II State court litigation as the final
tier
- Romania - MTDRC providing for expert
determination / dispute board followed by state
court litigation - Poor case-law and doctrine on the matter.
- Possible approaches
- The court has no express legal grounds to dismiss
the case either as inadmissible or premature - The court has no express grounds to order the
staying of the proceedings - The parties agreement will be considered a
contractual arrangement with no effects on the
state courts jurisdiction - The court may consider awarding damages for
breach of contract - It may be advisable to include a monetary
evaluation of the prejudice for breach of the
MTDRC in the contract
16Concluding Remarks
- Special care when drafting the MTDRC
- Mandatory vs. optional stages may vs.
shall - Clear and objective criteria for moving from one
stage to the next - Possibility to provide for damages in case of
breach of the MTDRC - Choosing the final tier arbitration vs. state
court litigation. - Special care when following the MTDRC
- Supporting documents attesting that efforts to
negotiate in good faith have been undertaken by
Claimant - Observe the time limits set up in the MTDRC.
17Competence Competence Principle. Recurring
IssuesICC YAF Conference, 27 September 2010,
Bucharest, Romania
- Matei PURICE
- Associate
- E-mail matei.purice_at_tuca.roÂ
- Tel (40-21) 204 88 90
- Web www.tuca.ro