City of Hope Amini Medical Center - PowerPoint PPT Presentation

About This Presentation
Title:

City of Hope Amini Medical Center

Description:

City of Hope Amini Medical Center Christopher Bratz Pennsylvania State University Architectural Engineering Mechanical Option Faculty Advisor: Dr. Jelena Srebric – PowerPoint PPT presentation

Number of Views:106
Avg rating:3.0/5.0
Slides: 44
Provided by: METAEngi
Learn more at: https://www.engr.psu.edu
Category:
Tags: amini | bratz | center | city | hope | medical

less

Transcript and Presenter's Notes

Title: City of Hope Amini Medical Center


1
City of HopeAmini Medical Center
  • Christopher Bratz
  • Pennsylvania State University
  • Architectural Engineering
  • Mechanical Option
  • Faculty Advisor
  • Dr. Jelena Srebric

2
Disclaimer
  • Due to limited information regarding the central
    plant, the Amini Center was removed from the
    central cooling plant and provided its own
    independent primary chilled water loop. This
    redesigned system serves as the baseline of
    comparison for my thesis depth redesign. For the
    remainder of this presentation, the Existing
    System refers to the Amini Centers independent
    cooling plant.

3
Building Information
  • Location Durante, California (L.A. Suburb)
  • Size 3-Stories, 59,800 sf New Construction
  • Occupancy Clinic, Lab, Office, Moderate Hazard
    Storage
  • Design-Bid-Build
  • Construction Dates 06.11.07 01.22.09

4
Building Load Profile
5
Existing Mechanical Systems
  • Primary/secondary chilled water system
  • (2) Air-Cooled Chillers on roof
  • (2) Primary Pumps in Mech. room
  • Rooftop AHUs Scattered FCUs
  • CV and VAV terminals
  • PRVs step down HPS to LPS
  • HX makes HW for building coils

6
Existing CHW System Flow Diagram
  • 185 Ton Chillers
  • 7.5 HP Primary Pumps
  • 2-way control valve
  • 296 gpm
  • 5 CHW piping
  • 42 deg. F CHWS
  • Loop Fluid Water

7
Existing Primary Loop
8
Annual Energy Consumption
9
Utility Rate
10
Annual Energy Cost
11
Primary Loop First Cost
12
Mechanical Redesign Objectives Analyses
  • Reduce annual energy cost
  • Maintain reasonable first cost
  • Reduce chiller demand load
  • Design Ice Storage System
  • Shift Load to off peak hours
  • Cheaper Utility Rates

13
Mechanical Redesign
  • Ice Storage System
  • Ice making chillers storage tanks
  • Primary Pumps
  • 25 Ethylene Glycol
  • (2) 3-way modulating valves
  • Internal melt ice-on-coil system
  • Control Sequencing
  • Full Storage
  • Load Leveling Partial Storage
  • Demand Limiting Partial Storage

14
Ice Storage Flow Diagram
15
Full Ice Storage System
  • Entire on-peak capacity shifted to off-peak hours
  • Large chillers and storage capacity

16
Full Ice Storage System
17
Full Ice Storage Sizing
18
Full Ice Storage System
  • 185 Ton Chillers
  • 5 HP Primary Pumps
  • (2) 594 Ton-hour Tanks
  • (2) 3-way modulating control valves
  • 232 gpm
  • 5 CHW piping
  • 38 deg. F CHWS
  • Loop Fluid 25 Ethylene Glycol

19
Annual Energy Consumption
20
Utility Rate
  • Utility Rate Incentives

21
Full Storage Annual Energy Cost
22
Full Storage Primary Loop First Cost
23
Load Leveling Partial Ice Storage System
  • Partial on-peak capacity shifted to non-peak
    hours
  • Design Day chiller Operates at full capacity
    24-7
  • Bldg. Load lt Chiller capacity chiller stores
    excess capacity
  • Bldg. Load gt Chiller capacity storage capacity
    discharges to supplement chiller
  • Small chillers and storage capacity

24
Load Leveling Partial Ice Storage System
25
Load Leveling Partial Ice Storage Sizing
26
Load Leveling Partial Ice Storage System
  • 125 Ton Chillers
  • 5 HP Primary Pumps
  • (1) 761 Ton-hour Tank
  • (2) 3-way modulating control valves
  • 157 gpm
  • 4 CHW piping
  • 38 deg. F CHWS
  • Loop Fluid 25 Ethylene Glycol

27
Annual Energy Consumption
28
Utility Rate
  • Utility Rate Incentives

29
Load Leveling Partial Ice Storage Annual Energy
Cost
30
Load Leveling Partial Ice Storage Primary Loop
First Cost
31
Demand Limiting Partial Ice Storage System
  • Partial on-peak capacity shifted to non-peak
    hours
  • Similar to load leveling w/ on-peak exception
  • Chiller capacity reduced to 45 during on-peak
    hours
  • Middle of road chillers and storage capacity

32
Demand Limiting Partial Ice Storage System
33
Demand Limiting Partial Ice Storage Sizing
34
Demand Limiting Partial Ice Storage System
  • 140 Ton Chillers
  • 5 HP Primary Pumps
  • (2) 476 Ton-hour Tanks
  • (2) 3-way modulating control valves
  • 176 gpm
  • 4 CHW piping
  • 38 deg. F CHWS
  • Loop Fluid 25 Ethylene Glycol

35
Annual Energy Consumption
36
Utility Rate
  • Utility Rate Incentives

37
Demand Limiting Partial Ice Storage Annual
Energy Cost
38
Demand Limiting Partial Ice Storage Primary Loop
First Cost
39
Chiller Summary
40
Energy Cost Summary
41
Ice Storage Redesign Recommendation
  • Load Leveling Scenario
  • Lowest first cost
  • Lowest Annual cost
  • Smallest Chiller and pump size
  • Smallest ice storage capacity
  • Smaller piping
  • Roof framing smaller

42
Advantages / Disadvantages
  • Advantages
  • Lowest Annual cost
  • Smaller Chiller, pump, and piping sizes
  • Slight energy savings (cleaner energy off-hours)
  • Utility Incentives
  • Lower CHWS Temp.
  • Disadvantages
  • First cost
  • Physical size and weight of storage tanks
  • Ethylene glycol need
  • Increased controls and length of piping

43
Questions?
Write a Comment
User Comments (0)
About PowerShow.com