Title: Progress on the MICE RFCC Module
1Progress on the MICE RFCC Module
MuCool Test Area RF Workshop October 15, 2008
- Mike Zisman/Steve Virostek
- Lawrence Berkeley National Laboratory
2Progress Summary
- The MICE cavity design is heavily based on the
successful MuCool 201-MHz prototype RF cavity and
lessons learned - Fabrication and post processing
- Cavity conditioning and operation
- Engineering design of the cavity is complete
- CAD model of the cavity, tuners, support and
vacuum - Fabrication schemes and vendor identification
- RFCC module engineering design nearing completion
- Possible operation at LN temperature?
- Design accommodates LN operation, but is very
challenging
3Muon Ionization Cooling Experiment
RFCC
RFCC
Spectrometer Solenoid 1
AFC
AFC
Spectrometer Solenoid 2
Absorber and Focusing Coil (AFC)
42 RFCC Modules, 8 Cavities
5RF Cavity Summary
- Fabrication of the prototype cavity was
successful - A slight reduction in cavity diameter to raise
the frequency has been specified and analyzed - The fabrication techniques used to produce the
prototype will be used to fabricate the MICE RF
cavities - A detailed WBS schedule for the design and
fabrication of the MICE RF cavities has been
developed
6Cavity Design Parameters
- Cavity design parameters
- Frequency 201.25 MHz
- ß 0.87
- Shunt impedance (VT2/P) 22 M?/m
- Quality factor (Q0) 53,500
- Be window diameter and thickness 42-cm and
0.38-mm - Nominal parameters for MICE and cooling channels
in a neutrino factory - 8 MV/m (16 MV/m) peak accelerating field
- Peak input RF power 1 MW (4.6 MW) per cavity
- Average power dissipation per cavity 1 kW (8.4
kW) - Average power dissipation per Be window 12 watts
(100 watts)
7Recent Progress RF Cavity Design
- 3-D Microwave Studio RF parameterized model with
ports and curved Be windows - Hard to reach the design frequency by spinning
- Frequencies between cavities should be able to
achieve within ? 100 kHz - Approaches
- Modification the spinning form
- Targeting for higher frequency
- Fixed tuner to tune cavity close to design
frequency (deformation of cavity body) - Tuners are in push-in mode ? lower frequency
8Numerical Study with B Field
- Preliminary studies, in collaboration with
colleagues at SLAC using Omega-3P and Track-3P
codes - Cavity with flat windows 5 MV/m on axis 2-T
uniform external magnetic field scan of a few
points from one cavity side
Trajectories with external B 2-T field
Trajectories without external B field
E field contour
9High Power RF Tests on Prototype Cavity
- The cavity was first tested with flat copper
windows and reached 16 MV/m quickly and quietly
- The cavity then was tested with thin and curved
Be windows and again reached to 19 MV/m quickly - Cavity frequency had to be retuned
- Cavity frequency was stable during the operation,
however, we did observe frequency shift due to RF
heating on the windows - Frequency shift of 125 kHz (from 0 to 19
MV/m, 150-micro-second pulse, 10-Hz repetition
rate) in 10 minutes, well within the tuning
range (230 kHz/mm per side, ? 2-mm range) - With a few hundred Gauss stray field from Lab-G
magnet, the cavity gradient can be maintained at
19 MV/m - To test with stronger external magnetic fields
- Move the cavity closer to Lab-G magnet
- SC coupling coil for MuCool
10Tests with Stronger Magnetic Fields
- New vacuum pumping system
- Separation of the nearest curved Be window from
the face of Lab-G magnet is 10-cm (before was
110-cm) - Maximum magnetic field near the Be window 1.5
Tesla (at 5 Tesla in magnet) - Test Results
- Multipactoring was observed over the entire
magnetic field range up to 1.1-T at nearest Be
window - A strong correlation exists between cavity vacuum
and radiation levels - We have achieved 14 MV/m at 0.75-T to the
nearest curved thin Be window - Recent test results show plateau at 10 MV/m
11RF Cavity Assembly
12RF Cavity Fabrication Overview
The same fabrication techniques used to make the
prototype cavity will be used for the MICE RF
cavities
Engineering CAD Model of the RF Cavity
- Cavity half-shells to be formed by metal spinning
- Precision milling of large parts (1.2 m diameter)
- Precision turning of mid-sized parts (0.6 m dia.)
- Precision manufacture of smaller parts
- CMM measurements throughout the process
- To limit any annealing and maintain cavity
strength, e-beam welding will be used for all
cavity welding - cavity equator, stiffener rings, nose rings, port
annealing and port flanges - Cavity inside surfaces are finished by
electro-polishing
Prototype RF Cavity
13Recent Progress
- RFCC engineering CAD model refined
- RF and engineering design of 201-MHz RF cavity
complete - Integration and interface issues addressed
- Vendor identification and qualification near
complete
14Recent Progress (procurement fab)
- The large copper sheets used in the fabrication
of the cavity shells have been ordered and will
arrive at LBNL in mid-December - A series of vendor qualification visits has been
conducted - Applied Fusion - San Leandro, CA (e-beam welding,
machining) - Meyer Tool Mfg., Inc. - Chicago, IL (machining)
- Sciaky, Inc. - Chicago, IL (e-beam welding)
- Roark Welding Engineering - Indianapolis, IN
(e-beam welding, machining) - ACME Metal Spinning Minneapolis, MN (cavity
shell spinning) - Other vendors have been identified
- Midwest Metal Spinning, Inc. Bedford, IN (cavity
shell spinning)
15Other Module Components
- Beryllium window design is complete windows are
in the process of being ordered (8 per module
needed) - Design and analysis of the cavity frequency
tuners is complete, drawings to be done soon - A hexapod cavity suspension system has been
incorporated in the design - The RF coupler will be based on the SNS design
using the off the shelf Toshiba RF window - The vacuum system includes an annular feature
coupling the inside and the outside of the cavity
(further analysis of vacuum rupture scenarios
TBD)
16Other Module Components
Cavity Suspension
Dynamic Tuners
RF Coupler
Beryllium Window
Vacuum System
17201 MHz Beryllium Windows
- Each cavity has two Be windows
- 42-cm diameter and 0.38-mm thick
- Window is formed at high temperature and later
brazed to copper frames - Thin TiN coatings on both sides of the window
- One window curves into the cavity and one curves
out - Already tested up to 5 MW in 201-MHz cavity at
MTA, FNAL
42-cm
18Cavity Tuner Design Features
- Six tuners spaced evenly around each cavity
provide individual frequency adjustment through a
feedback loop - Layout is offset by 15º from vertical to avoid
conflict with cavity ports - Tuners touch cavity and apply loads only at the
stiffener rings - Tuners operate in push mode only (i.e.
squeezing)
19Tuner component Details
Actuator bellows assembly
Fixed arm
Pivoting arm
Forces are transmitted to the stiffener ring by
means of push loads applied to the tuner lever
arms by the actuator assembly
20Hexapod Strut Arrangement
- Analysis of a hexapod strut system is complete
- Each cavity will contain a dedicated set of 6
suspension struts arranged in a hexapod type
formation - This system spreads the gravity load of the
cavity across several struts
Example of a hexapod stage
21Hexapod Strut Cavity Mounting
- Copper mounting block will be e-beam welded
directly to the RF cavity - The cavity has very little deformation at the
mounting block location
22Vacuum System
- A NEG pump has been chosen because it will be
unaffected by the large magnetic field - A vacuum path between the inside and outside of
the cavity eliminates the risk of high pressure
differentials and the possible rupture of the
thin beryllium window
23Vacuum Vessel and Support Summary
- Engineering 3D CAD model of the vacuum vessel
mechanical design is complete - Standard machining and manufacturing methods will
be used - A plan for attaching the coupling coil and the
vacuum vessel together has been developed - Conceptual design of the support stand is
complete (analysis will need to be performed) - A method for assembling the cavities into the
vacuum vessel has been formulated - A conceptual design of the cavity water cooling
feedthrough system is finished
24Vacuum Vessel Fabrication
- Vacuum vessel material must be non-magnetic and
strong therefore 304 stainless steel will be used
throughout - The vacuum vessel will be fabricated by rolling
stainless steel sheets into cylinders - Two identical vessel halves will be fabricated
with all ports and feedthroughs
25Vacuum Vessel and Coupling Coil
26Vacuum Vessel/Coupling Coil Integration
- LBNL will weld in gussets that fit between the
coupling coil and the vacuum vessel - Sixteen special gussets are welded between the
coupling coil magnets cold mass support tubes
and the magnet housing - The gussets will transfer the magnetic loads
between the coupling coil and the vacuum vessel
27RFCC Attachment to Support Stand
- The vacuum vessel is bolted to a saddle made up
of small plates welded to the support stand - Stainless steel bars are welded onto the vacuum
vessel for attaching bolted gusset plates
Bolted gusset mounting bars
28RFCC Support Stand
- RFCC support stand must withstand a longitudinal
force of 50 tons transferred from the coupling
coil - Bolted gussets and cross bracing provide shear
strength in the axial direction (analysis will
confirm the stand design)
29Liquid Nitrogen Cooling Considerations
- Suspension of cavities on struts provides low
heat leak from cavity to vacuum vessel - Beryllium window FEA thermal analysis will need
to be performed with new parameters - The cavity frequency will be shifted
(approximately 600 kHz), therefore tuning system
or RF power source modifications will be needed - Insulators will need to be added to the RF
couplers - Coaxial LN feedthrough tubes will be needed to
insulate the connection outside of vacuum
MICE RF Cavity Mechanical Design and Analysis
Page 29
Allan DeMello - Lawrence Berkeley National Lab
- June 4, 2008
30Module Assembly Sequence
Beryllium windows are installed onto the cavities
Bare cavity
31Module Assembly Sequence
Assembly of the tuners onto the cavities (w/o
actuators)
Install struts onto the cavity
32Module Assembly Sequence
- Slide the inner cavity into vacuum vessel using
spacer/alignment blocks for support - Shim cavity to align tuner and coupler vacuum
feedthroughs with tuner mounts and cavity ports - After adjusting their lengths, secure the struts
to the vacuum vessel mounting blocks
33Module Assembly Sequence
Install tuner actuators
Install RF couplers
Install vacuum couplers
Install cooling water feedthroughs
34Module Assembly Sequence
Repeat the same process for the other cavities
Install vacuum valves and pumps
Two cavities are installed from each end of
vacuum vessel
35RFCC Module Shipping Configuration
Cryocoolers removed Cavities removed
Couplers removed Vacuum pumps removed
- Module short stand used for
- Initial module assembly
- Shipping to RAL
- Moving into MICE Hall
36MICE Hall Access
37Installation in MICE Hall
- Module assembled on lateral tracks
- Module aligned and shimmed to correct height
- Bellows on either end of module are pulled back
into open position and O-ring in place - Moved into position w/rails for final alignment
- Bellows are released and flanges are sealed
- Bellows are locked out using bridging bolts
- RF and utilities are connected to module
38Module Flange Connection
End flange O-ring seal
Formed bellows
Flange through holes
39Flanges and Seals
- Flanges designed to mate with AFC module
- AFC flanges are flat w/no grooves or bellows
- RFCC modules have bellows and O-ring grooves on
flanges at either end - Bellows have gt1 cm of total travel
- Bellows are locked out after installation to
provide a means of transmitting forces between
modules
40Module Mounting Provision
- Six mounting plates welded to the support base
for installation on rails - Same as spectrometer solenoid mounts
- All magnetic loads carried to the floor through
the mounting plates
41Cavity RF Feeds
- Eight RF feeds/module use standard 4 RF coax
- Cooling water for loop is required (ltlt1 lpm each)
- Adapter on end of couplers isolates ceramic RF
windows from forces during installation - Location of coax interface w.r.t. module center
TBD
RF feeds
42Schedule Overview
- RFCC design and fabrication project originally
expected to be a 3year project (10/06 to 10/09) - Coupling coil effort began in 2006 at ICST
(Harbin) - Design and fabrication of other RFCC module
components was scheduled to begin 10/07 - Start was delayed due to lack of availability of
qualified manpower - Earlier this year, mechanical engineer A. DeMello
joined MICE to work on RFCC module design (FTE) - Additional manpower required to make up schedule
43Manpower Summary
- Primary Manpower
- Allan DeMello lead ME for RFCC Module design
fab - 3D engineering CAD model, cavity analysis, design
fab - Steve Virostek engineering oversight for MICE at
LBNL - Mechanical Engineer (TBD) design/fab of
subcomponents - Cavity tuners, support structure, large
procurements - Mechanical Designer (TBD) generation of
fabrication dwgs - Other
- Derun Li cavity physics design and oversight
- Mike Green coupling coil design interface with
module
44Schedule Summary