Current Situation - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Current Situation

Description:

Project Description HVDC Light Technology Location and Routing Installation and Construction AC and DC transmission cables. – PowerPoint PPT presentation

Number of Views:206
Avg rating:3.0/5.0
Slides: 29
Provided by: TonyDu8
Category:

less

Transcript and Presenter's Notes

Title: Current Situation


1

Juan de Fuca Cable
Presented by Sea Breeze Pacific Juan de Fuca
Cable, LP
2
Presentation Overview
  1. Introduction
  2. Need for Project
  3. Project Description
  4. Environmental Considerations
  5. Permitting

3
Introduction
  • Sea Breeze Pacific Juan de Fuca Cable, LP (Sea
    Breeze Pacific) is proposing to construct and
    have operated a 550 MW High Voltage Direct
    Current (HVDC) Light transmission line between
    Port Angeles, Washington State, and the Greater
    Victoria Area, B.C.

4
Project Proponent and Team
  • Sea Breeze Pacific Juan de Fuca Cable, LP is a
    joint venture between Sea Breeze Power Corp., and
    Boundless Energy, LLC.

5
  • Sea Breeze Power Corp Vancouver-based renewable
    energy company building both wind and
    run-of-river hydro electric projects.
  • Boundless Energy LLC Transmission and utility
    engineering company based in York Harbor, Maine.
    Originators of the Neptune Regional Transmission
    System HVDC concept and plan.
  • ABB, Inc. One of three companies in the world
    involved in large scale HVDC engineering.
  • Design, manufacturing, and installation company,
    has completed major projects on every continent.
  • Currently seven operating HVDC LightTM lines in
    the world.
  • A 110 km line was just approved to link Finland
    with Estonia.

6
Need for the Project
  • Opportunities to strengthen B.C. and Washington
    transmission grids and improve voltage stability
  • Consideration of short-term and long-term power
    generation, supply and load demand conditions
  • Open Season, in which utilities will
    competitively bid to use the line, will
    ultimately demonstrate need

7
Power Situation in the Pacific Northwest
  • BC has high generation potential
  • Many opportunities for electricity interchange
  • Potential energy for transmission
  • More than 7000 MW in coastal B.C.
  • 2000 MW in northern Alberta

8
Project Description
  1. HVDC Light Technology
  2. Location and Routing
  3. Installation and Construction

9
HVDC Light Technology
  • A proven, state-of-the-art technology with low
    environmental impact and no fluctuating
    electro-magnetic field (EMF)
  • Relatively low operating temperature, and
    non-liquid insulation

AC and DC transmission cables. Two cables at far
right are HVDC LightTM. Photo courtesy of ABB.
10
  • Approximate diametre of cable bundle
  • 16 cm on land
  • 25 cm at sea
  • Approximate temperature
  • 70C in core
  • 60C on cable surface.
  • Heat is equivalent to one 20 Watt light bulb per
    metre, or one 60 Watt light bulb every 3 metres.
    Rate of heat dissipation will depend on substrate.

Gotland HVDC Light cables. Photo courtesy of ABB.
All cables would be buried no overhead lines
11
Location Routing
Would connect converter stations near existing
substations in the Greater Victoria Area, B.C.
and Port Angeles, Washington. Proposed
terrestrial and underwater cable routes will be
subject to Federal and Municipal regulations.
Approximate lengths of cable Greater Victoria to
Port Angeles 46 km Proposed length on B.C.
side 10 km Proposed length on WA side 3
km Length at sea 33 km
12
Proposed marine corridor approx. 500m wide
13
Project planning and studies will take into
account consultation with interested and affected
parties, and will consider
  • Environmental factors
  • Fisheries
  • Transportation
  • First Nations interests
  • Aesthetic factors
  • Commercial use
  • Recreational use

14
Installation Construction
Installation Offshore/Marine
A ship-towed machine would create trenches, into
which the HVDC cable system would be buried. The
cable comes from the factory as one continuous
length.
The trenches would be deep enough to prevent
disturbance by ship anchors, etc. Anticipated
depth of burial is approximately 1 to 1.5 metres.
15
Artistic rendering of marine cable installation
16
Overview of cable installation foreshore and
offshore
17
Installation Marine to Terrestrial Transition
  • Horizontal directional drilling (HDD) would be
    used to avoid adverse environmental effects.
  • A versatile technology that uses a
    precision-guided directional system to bore a
    hole through soil or rock.
  • Disturbance to marine foreshore areas is
    minimized by drilling underneath them.

As a result, the intertidal zone would be
undisturbed by cable installation.
18
Installation Terrestrial
  • Beyond the transition zone, buried HVDC cables
    would connect to a converter station.
  • Proposed path is within a public road right-of-way

Diagram of cable installation beneath road
right-of-way
19
Converter Stations
A converter station would be needed to convert DC
to AC and vice versa.
Converter stations can be designed to fit into
their surroundings.
20
Environmental Considerations
  1. Choice of Technology
  2. Choice of Installation Techniques
  3. Noise and Traffic Considerations
  4. Environmental Studies and Consultation

21
HVDC LightTM Technology Environmental aspects
  • No fluctuating electromagnetic field
  • ? expected to have minimal to no effect on the
    sensory organs of marine mammals and fish.
  • Cables are not liquid-cooled
  • ? do not pose any danger of coolant leaks or
    spills.
  • Relatively low operating temperature
  • ? expected to have low impact on the local
    heat regime
  • No adverse impact anticipated to fisheries
    resources during operation.

22
Choice of Installation Techniques
Environmental aspects
  • Buried submarine and terrestrial cable
  • Disruption to marine floor is expected to be
    local and short-term
  • Directional drilling avoids damage to natural and
    cultural features by drilling deep underneath
    them.

23
Noise Traffic Considerations
Installation
  • Noise and visual impacts related to the cable
    would be temporary and limited to construction
  • ? similar to the installation of a buried
    telephone cable.
  • Once cable is installed, maintenance activity
    would be minimal.

Converter stations
  • Design could include features to minimize noise
  • Outer structure could be designed by architects
    to minimize visual impact

24
Environmental Studies and Consultation
Proposed Marine Studies
Proposed Terrestrial Studies
  • Physical
  • Bathymetry
  • Geotechnical
  • Terrain and obstacles
  • Archaeology
  • - Offshore core sampling
  • Biological
  • Mammals
  • Fisheries
  • Birds
  • Nearshore ecosystem
  • Socio-economic studies
  • - Traditional use and knowledge
  • Physical
  • Geotechnical
  • Hydrology
  • Archaeology
  • Noise
  • Biological
  • Wildlife and avifauna
  • Vegetation
  • Socio-economic studies
  • - Traditional use and knowledge

Sea Breeze is committed to a high standard of
consultation with any individuals or groups who
may be affected by the Project.
25
Expected Timeline
  • 1. Terrestrial field studies - Start June 2005
    completion anticipated July 2005
  • Marine field studies Start June 2005 completion
    anticipated August 2005
  • 3. Permitting Start September 2004 completion
    anticipated March 2006
  • 4. Operational The physical construction phase
    is expected to begin November 2006 and be
    completed by November 2007.

26
Permitting
  • Final National Energy Board application is
    expected to be filed October 2005 and will
    include information to meet Canadian
    Environmental Assessment Act requirements.
  • No Provincial permits required.
  • Municipal permits will follow federal permit
    approvals.

27
Past Experience
The Neptune Regional Transmission System,
designed by Sea Breeze Pacific partners, has been
fully permitted through all environmental
processes. The system will start in New Jersey
and, through micro-tunneling, bring one end of
the 660 MW HVDC cable up into Long Island
underneath Jones Beach, a popular local
park. This line in the very populated New York
area has had no public opposition.
28
Thank you
Write a Comment
User Comments (0)
About PowerShow.com