Title: Wide Area Networking (WAN) with Wireless Technologies
1Wide Area Networking (WAN)with Wireless
Technologies
- Graham Robinson
- Senior Wireless Architect
2Agenda
Technology OverviewSolution DesignLong Range
Site Survey Simply Wireless Case Studies
3Wireless WAN Technology Options
- Class Licensed Spectrum
- 2.4 GHz and 5 GHz
- Licensed Spectrum
- Cellular, 3G, Microwave
- Free Space Optics (Laser)
4Wireless WAN Overview
- Purpose
- To connect multiple sites, offices, buildings or
houses with network connectivity. - Attributes
- High Bandwidth (1Mbps to 54Mbps)
- Long Distance (10m to 15km)
- Single (Initial) Investment
- Quick to Implement
- Comparatively High ROI
- Limitations
- Require Line of Sight
- May require Development Approval (DA)
5Wireless WAN Flavours
Point-Point
Point-Multipoint
Up to 54Mbps
Up to 54Mbps
Speeds
Frequency Band
2.4 GHz and 5 GHz
2.4 GHz and 5 GHz
Worldwide
Worldwide
Availability
Duplex
Half/Full Duplex
Half Duplex Only
5km
15km
Distance
6Australias 2.4 GHz Band
2.4 GHz Band
2.402
2.478
AUS (ACA) 11 Channels
11 Channels
Band 1 1W (30dBm) Radio 6dBi Antenna EIRP
(max) 4W
Band 1 Indoor or Outdoor (Wireless LAN and WAN)
7Australias 5 GHz Band
5 GHz Band
5.15
5.35
5.470
5.725
5.825
AUS (ACA) 12 Channels
4 Channels
8 Channels
Band 1 50mW(17dBm) Radio 6dBi Antenna EIRP
(max) 200mW
Band 2 1W(30dBm) Radio 6dBi Antenna EIRP
(max) 4W
Band 1 Indoor Use Only (Wireless LAN) Band 2
Outdoor Bridging Only (Wireless WAN)
8Agenda
Technology OverviewSolution DesignLong Range
Site Survey Simply Wireless Case Studies
9Solution Design
- Site Selection
- Physical Access Approval
- Technical Requirements
- Environmental Analysis
10Site Selection
- Business Requirements
- Number of Sites
- Location of Links
- Visibility / Line of Sight
11Physical Access Approval
- Building Ownership
- Rooftop Access
- RF collocation
- Strata Approval
- Council Approval (DA)
12Technical Requirements
- Reqd Bandwidth
- Network Topology
- Management
- Application Usage
- Voice vs. VoIP
- Monitoring
13Environmental Analysis
- EM Radiation
- Weather Conditions
14Agenda
Technology OverviewSolution DesignLong Range
Site Survey Simply Wireless Case Studies
15Understanding Your Environment
- Line of Sight (LOS)
- Expected Changes
- Existing Bridges (collocation)
- Development Approval
16Radio Planning
- Multi-path Degradation
- RF Interference
- Legacy System Cohesion
- Channel Plan
- Optimal Spectrum Usage
17Survey Documentation
- Signal Strengths
- Signal Quality
- Fade Margin
- Network Baseline
- Estimated Availability
- Troubleshooting
18Agenda
Technology OverviewSolution DesignLong Range
Site Survey Case Studies
19XYZ Pty. Ltd.
- Case Study 1 XYZ Pty. Ltd. (Under NDA)
- Requirements
- Reliable network connectivity (point-point)
between multiple buildings separated by a large
roadway. - Conventional Ideology Limitations
- Fibre cabling costs were to exceed 500,000 AUD.
- The project required extensive planning due to
the requirement to trench under the roadway. - Any alterations to the roadway required a lengthy
approval process. - The estimated lead time to implementation was
6-18 months. - The Simply Wireless Solution
- Simply Wireless provided an appropriate
point-point solution for less than 60,000 AUD. - The wireless solution had a three (3) week
implementation lead time. - Wireless Bridge Benefits
- Large cost savings.
- No development approval required.
- Very low lead time to implementation.
20XYZ Pty. Ltd.
- Case Study 2 XYZ Pty. Ltd. (Under NDA)
- Requirements
- Reliable and scalable network (point-multipoint)
connectivity between multiple buildings separated
by open space, other buildings and grassed areas. - Conventional Ideology Limitations
- Fibre, cabling, switches and integration costs
were to exceed 100,000 AUD. - The fibre solution could not be easily
re-designed. - Additional building were to cost approximately
20,000 each. - The project required extensive planning due to
some trenching requirement. - The estimated lead time to implementation was 2-6
months. - The Simply Wireless Solution
- Simply Wireless provided a point-multipoint
solution for less than 40,000 AUD. - Additional buildings could be brought on for less
than 10,000 each. - The wireless solution had a three (3) week
implementation lead time. - Wireless Bridge Benefits
- Large cost savings.
21Questions?