Title: GENERAL INSPECTOR
1GENERAL INSPECTOR
21.
The excavation of a roadside ditch in the roadway
section (part of the typical roadway cross
section) is paid for under which of the following
excavation bid items?
- Ditch excavation
- Toe trench excavation
- Borrow excavation
- General excavation
31.
The excavation of a roadside ditch in the roadway
section (part of the typical roadway cross
section) is paid for under which of the following
excavation bid items?
CORRECT!
41.
The excavation of a roadside ditch in the roadway
section (part of the typical roadway cross
section) is paid for under which of the following
excavation bid items?
- INCORRECT!
- The correct answer is D, General Excavation.
The answer can be found in Section 330.91(d), Pg
94, 2008 Standard Specifications (Volume 2).
52.
The Contractor should stop placement of
Continuously Reinforced Concrete Pavement when
the air temperature falls below ____________.
- 0F
- 32F
- 35F
- 40F
62.
The Contractor should stop placement of
Continuously Reinforced Concrete Pavement when
the air temperature falls below ____________.
35F
CORRECT!
72.
The Contractor should stop placement of
Continuously Reinforced Concrete Pavement when
the air temperature falls below ____________.
- INCORRECT!
- The correct answer is C, 35F. The answer can
be found in Section 755.40, Pg 501 of the 2008
Standard Specifications.
83.
The Contractor will obtain and pay for permits
required for crossing or encroaching upon
navigable streams.
- True
- False
93.
The Contractor will obtain and pay for permits
required for crossing or encroaching upon
navigable streams.
CORRECT!
103.
The Contractor will obtain and pay for permits
required for crossing or encroaching upon
navigable streams.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 170.03, Pg 62 of the 2008
Standard Specifications.
114.
When installing pipe materials, the Contractor
cannot vary from the established line and grade
by more than ______ , provided the variation does
not result in a level of reverse sloping invert
(flowline).
- 0 (there is no variance allowed)
- 1
- ½
- ¼
124.
When installing pipe materials, the Contractor
cannot vary from the established line and grade
by more than ______ , provided the variation does
not result in a level of reverse sloping invert
(flowline).
½
CORRECT!
134.
When installing pipe materials, the Contractor
cannot vary from the established line and grade
by more than ______ , provided the variation does
not result in a level of reverse sloping invert
(flowline).
- INCORRECT
- The correct answer is C, ½ inch. The answer can
be found in Section 445.40(b), Pg 176 of the 2008
Standard Specifications.
145.
When installing wood sign posts, the post holes
should be backfilled in layers not exceeding
________.
- 6
- 8
- 10
- half the total depth of the hole
155.
When installing wood sign posts, the post holes
should be backfilled in layers not exceeding
________.
6
CORRECT!
165.
When installing wood sign posts, the post holes
should be backfilled in layers not exceeding
________.
- INCORRECT
- The correct answer is A, 6 inches. The answer
can be found in Section 910.40, Pg 572 of the
2008 Standard Specifications.
176.
The Contractor shall furnish all facilities
necessary to permit the Engineer to have safe
access to the work to be inspected.
- True
- False
186.
The Contractor shall furnish all facilities
necessary to permit the Engineer to have safe
access to the work to be inspected.
CORRECT!
196.
The Contractor shall furnish all facilities
necessary to permit the Engineer to have safe
access to the work to be inspected.
- INCORRECT
- The correct answer is True. The answer can be
found in Section 150.20(b), Pg 36 of the 2008
Standard Specifications.
207.
When measuring painted temporary striping, the
intervals between skip lines will be included in
the measurement.
- True
- False
217.
When measuring painted temporary striping, the
intervals between skip lines will be included in
the measurement.
CORRECT!
227.
When measuring painted temporary striping, the
intervals between skip lines will be included in
the measurement.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 225.83(c), Pg 33 of the 2008
Standard Specifications.
238.
Bridge rail installation on the bridge end panels
is incidental to the Reinforced Concrete Bridge
End Panel bid item.
- True
- False
248.
Bridge rail installation on the bridge end panels
is incidental to the Reinforced Concrete Bridge
End Panel bid item.
CORRECT!
258.
Bridge rail installation on the bridge end panels
is incidental to the Reinforced Concrete Bridge
End Panel bid item.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 545.90, Pg 280 and Section
587.90, Pg 344 of the 2008 Standard
Specifications.
269.
When applying asphalt tack coat, the bar height
of the asphalt distributor should be set for
double-lap coverage.
- True
- False
279.
When applying asphalt tack coat, the bar height
of the asphalt distributor should be set for
double-lap coverage.
CORRECT!
289.
When applying asphalt tack coat, the bar height
of the asphalt distributor should be set for
double-lap coverage.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 730.22, Pg 439 of the 2008
Standard Specifications.
2910.
What is the minimum overlap requirement for
geotextile used for embankment stabilization?
- 12
- 18
- 24
- 300 mm
3010.
What is the minimum overlap requirement for
geotextile used for embankment stabilization?
CORRECT!
3110.
What is the minimum overlap requirement for
geotextile used for embankment stabilization?
- INCORRECT
- The correct answer is C, 24 inches. The answer
can be found in Section 350.41(a-2), Pg 110 of
the 2008 Standard Specifications.
3211.
On a project that is Federally-funded, a
Certificate of Materials Origin (CMO) is needed
for a temporary impact attenuator.
- True
- False
3311.
On a project that is Federally-funded, a
Certificate of Materials Origin (CMO) is needed
for a temporary impact attenuator.
CORRECT!
3411.
On a project that is Federally-funded, a
Certificate of Materials Origin (CMO) is needed
for a temporary impact attenuator.
- INCORRECT
- The correct answer is False. The answer can be
found in the Non-Field Tested Materials
Acceptance Guide, Pg 2.
3512.
Moisture content at the time of compacting
moisture-density testable embankment materials
must be how close to optimum moisture content?
- 95 of optimum moisture
- 4
- 2
- minus 4 to plus 2
3612.
Moisture content at the time of compacting
moisture-density testable embankment materials
must be how close to optimum moisture content?
CORRECT!
3712.
Moisture content at the time of compacting
moisture-density testable embankment materials
must be how close to optimum moisture content?
- INCORRECT
- The correct answer is D, minus 4 to plus 2.
The answer can be found in Section 330.43(b-2-a),
Pg 88 of the 2008 Standard Specifications.
3813.
Payment for installing 8-foot guardrail posts
instead of the normal 6-foot posts will be a cost
per length bonus in addition to the regular
payment.
- True
- False
3913.
Payment for installing 8-foot guardrail posts
instead of the normal 6-foot posts will be a cost
per length bonus in addition to the regular
payment.
CORRECT!
4013.
Payment for installing 8-foot guardrail posts
instead of the normal 6-foot posts will be a cost
per length bonus in addition to the regular
payment.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 810.90, Pg 536 of the 2008
Standard Specifications.
4114.
How far above finished grade should sprinkler
heads be positioned?
- ½ to 1, measured from the top of the riser
- 1 to 1 ½, measured from the top of the riser
- ½ to 1, measured from the top of the sprinkler
- 1 to 1 ½, measured from the top of the sprinkler
4214.
How far above finished grade should sprinkler
heads be positioned?
CORRECT!
4314.
How far above finished grade should sprinkler
heads be positioned?
- INCORRECT
- The correct answer is C, ½ to 1, measured
from the top of the sprinkler. The answer can be
found in Section 1120.45(a), Pg 682 of the 2008
Standard Specifications.
4415.
What type of inlet protection involves installing
biofilter bags?
- Type 4
- Type 3
- Type 2
- Type 1
4515.
What type of inlet protection involves installing
biofilter bags?
CORRECT!
4615.
What type of inlet protection involves installing
biofilter bags?
- INCORRECT
- The correct answer is A, Type 4. The answer can
be found in Section 280.46(d), Pg 55 of the 2008
Standard Specifications.
4716.
What is the minimum number of inspections the
Agency will make jointly with the Contractor
during each plant establishment period?
- 1
- 2
- 3
- 4
4816.
What is the minimum number of inspections the
Agency will make jointly with the Contractor
during each plant establishment period?
CORRECT!
4916.
What is the minimum number of inspections the
Agency will make jointly with the Contractor
during each plant establishment period?
- INCORRECT
- The correct answer is C, 3. The answer can be
found in Section 1040.72, Pg 657 of the 2008
Standard Specifications.
5017.
Approved Unstamped Drawings take precedence over
the Standard Drawings.
- True
- False
5117.
Approved Unstamped Drawings take precedence over
the Standard Drawings.
CORRECT!
5217.
Approved Unstamped Drawings take precedence over
the Standard Drawings.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 150.10(a), Pg 34 of the 2008
Standard Specifications.
5318.
The Agency will pay the Contractor to maintain
the roadway surfacing in a detour if it is not
constructed according to the Plans.
- True
- False
5418.
The Agency will pay the Contractor to maintain
the roadway surfacing in a detour if it is not
constructed according to the Plans.
CORRECT!
5518.
The Agency will pay the Contractor to maintain
the roadway surfacing in a detour if it is not
constructed according to the Plans.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 220.60(a-1), Pg 8 of the 2008
Standard Specifications.
5619.
Which of the following statements about a Quality
Compliance Certificate is true?
- The certificate must be delivered to the
Engineers representative with the shipment of
material, or be an identification plate or mark,
decal, sticker, label or tag attached to the
container or material. - The certificate must certify that the material
meets the contract requirements and identify the
specific test methods used by number (ODOT,
AASHTO, ASTM, UL or other). - The certificate must permit positive
determination that the material delivered to the
project is the same material covered by the
certificate. - All of the above.
5719.
Which of the following statements about a Quality
Compliance Certificate is true?
CORRECT!
5819.
Which of the following statements about a Quality
Compliance Certificate is true?
- INCORRECT
- The correct answer is D, all of the above. The
answer can be found in the Non-Field Tested
Materials Acceptance Guide, Pg 1 and Section
165.35(b), Pg 50 of the 2008 Standard
Specifications.
5920.
What is the required application rate of granular
fertilizer per tree per application?
- 1/8 pound
- 1/4 pound
- 1/2 pound
- 1 pound
6020.
What is the required application rate of granular
fertilizer per tree per application?
CORRECT!
6120.
What is the required application rate of granular
fertilizer per tree per application?
- INCORRECT
- The correct answer is D, 1 pound. The answer
can be found in Section 1040.47, Pg 650 of the
2008 Standard Specifications.
6221.
During all construction activities, the Agency is
required to retain the Erosion and Sediment
Control Plan.
- True
- False
6321.
During all construction activities, the Agency is
required to retain the Erosion and Sediment
Control Plan.
CORRECT!
6421.
During all construction activities, the Agency is
required to retain the Erosion and Sediment
Control Plan.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 280.02(c), Pg 43 of the 2008
Standard Specifications.
6522.
Which of the following is NOT an approved
supplier of concrete pipe?
- Hanson Pipe and Products, Tualatin, Oregon
- Cascade Concrete Products, Scappoose, Oregon
- Central Oregon Redi-Mix, Redmond, Oregon
- Advantage Precast, Keizer, Oregon
6622.
Which of the following is NOT an approved
supplier of concrete pipe?
CORRECT!
6722.
Which of the following is NOT an approved
supplier of concrete pipe?
- INCORRECT
- The correct answer is C, Central Oregon
Redi-Mix. The answer can be found in the
Non-Field Tested Materials Acceptance Guide, Pg 6.
6823.
How many counting days after a signal footing is
poured can the Contractor erect the signal pole?
- 7 days
- 5 days
- 3 days
- 1 day
6923.
How many counting days after a signal footing is
poured can the Contractor erect the signal pole?
CORRECT!
7023.
How many counting days after a signal footing is
poured can the Contractor erect the signal pole?
- INCORRECT
- The correct answer is A, 7 days. The answer can
be found in Section 540.52, Pg 273 of the 2008
Standard Specifications, and Table 00540-1.
7124.
Conditionally Approved products from the QPL need
specific, prior approval for each project they
are used on.
- True
- False
7224.
Conditionally Approved products from the QPL need
specific, prior approval for each project they
are used on.
CORRECT!
7324.
Conditionally Approved products from the QPL need
specific, prior approval for each project they
are used on.
- INCORRECT
- The correct answer is True. The answer can be
found on the Qualified Products List Information
Page.
7425.
What is the minimum surface temperature for
placing a 2 lift of Open Graded HMAC?
- 5C
- 40F
- 50F
- 60F
7525.
What is the minimum surface temperature for
placing a 2 lift of Open Graded HMAC?
CORRECT!
7625.
What is the minimum surface temperature for
placing a 2 lift of Open Graded HMAC?
- INCORRECT
- The correct answer is C, 50F. The answer can
be found in Section 745.40, Pg 477 of the 2008
Standard Specifications.
7726.
Which of the following documents takes precedence
if there are conflicting references or if no
reference is made in the Contract to material
specifications or test methods?
- Manual of Field Test Procedures
- Standard Specifications
- Supplemental Specifications
- Special Provisions
7826.
Which of the following documents takes precedence
if there are conflicting references or if no
reference is made in the Contract to material
specifications or test methods?
CORRECT!
7926.
Which of the following documents takes precedence
if there are conflicting references or if no
reference is made in the Contract to material
specifications or test methods?
- INCORRECT
- The correct answer is D, Special Provisions.
The answer can be found in Section 165.20, Pg 49
of the 2008 Standard Specifications.
8027.
Which of the following is an approved Traffic
Signal Loop Sealant?
- BJ Super
- Opticom Model 752
- Both A and B
- None of the above
8127.
Which of the following is an approved Traffic
Signal Loop Sealant?
CORRECT!
8227.
Which of the following is an approved Traffic
Signal Loop Sealant?
- INCORRECT
- The correct answer is A, BJ Super. The answer
can be found in the Qualified Products List, Pg
79-80.
8328.
The Project Superintendent of a project can be
designated as the Traffic Control Supervisor.
- True
- False
8428.
The Project Superintendent of a project can be
designated as the Traffic Control Supervisor.
CORRECT!
8528.
The Project Superintendent of a project can be
designated as the Traffic Control Supervisor.
- INCORRECT
- The correct answer is False. The answer can be
found in Section 225.32, Pg 19 of the 2008
Standard Specifications.
8629.
When using the count method of measuring
guardrail, the number of standard sections will
be counted and multiplied by 12.5 feet.
- True
- False
8729.
When using the count method of measuring
guardrail, the number of standard sections will
be counted and multiplied by 12.5 feet.
CORRECT!
8829.
When using the count method of measuring
guardrail, the number of standard sections will
be counted and multiplied by 12.5 feet.
- INCORRECT
- The correct answer is True. The answer can be
found in Section 810.80, Pg 535 of the 2008
Standard Specifications.
8930.
Commercial Grade Concrete must be placed within
90 minutes of batching and mixing.
- True
- False
9030.
Commercial Grade Concrete must be placed within
90 minutes of batching and mixing.
CORRECT!
9130.
Commercial Grade Concrete must be placed within
90 minutes of batching and mixing.
- INCORRECT
- The correct answer is True. The answer can be
found in Section 440.40(b), Pg 171 of the 2008
Standard Specifications.
9231.
Spot alignment control points on tangent sections
for Painted Permanent Pavement Striping shall be
every 50 feet.
- True
- False
9331.
Spot alignment control points on tangent sections
for Painted Permanent Pavement Striping shall be
every 50 feet.
CORRECT!
9431.
Spot alignment control points on tangent sections
for Painted Permanent Pavement Striping shall be
every 50 feet.
- INCORRECT
- The correct answer is True. The answer can be
found in Section 850.44, Pg 554 of the 2008
Standard Specifications.
9532.
If more than 50 tons/day of material is received
from a scale, the Contractor shall make random
check weighings at least every 10th day on which
more than 50 tons is received, or when 10,000
tons has been weighed, whichever occurs first.
- True
- False
9632.
If more than 50 tons/day of material is received
from a scale, the Contractor shall make random
check weighings at least every 10th day on which
more than 50 tons is received, or when 10,000
tons has been weighed, whichever occurs first.
CORRECT!
9732.
If more than 50 tons/day of material is received
from a scale, the Contractor shall make random
check weighings at least every 10th day on which
more than 50 tons is received, or when 10,000
tons has been weighed, whichever occurs first.
- INCORRECT
- The correct answer is True. The answer can be
found in Section 190.20(f-1), Pg 101 of the 2008
Standard Specifications.
9833.
What is the minimum cover from finished surfaces
for Rigid Nonmetallic conduit placed on roadways
and shoulders?
- 24
- 18
- 12
- 30
9933.
What is the minimum cover from finished surfaces
for Rigid Nonmetallic conduit placed on roadways
and shoulders?
CORRECT!
10033.
What is the minimum cover from finished surfaces
for Rigid Nonmetallic conduit placed on roadways
and shoulders?
- INCORRECT
- The correct answer is D, 30 inches. The answer
can be found in Section 960.41(c), Pg 588 of the
2008 Standard Specifications.
10134.
Which of the following should a Contractor do
when an abandoned pipe is encountered?
- Place a watertight cap over the outlet end
- Place free draining cover material around the
inlet end - Remove ends of remaining pipe to at least 2 feet
below subgrade - All of the above
10234.
Which of the following should a Contractor do
when an abandoned pipe is encountered?
CORRECT!
10334.
Which of the following should a Contractor do
when an abandoned pipe is encountered?
- INCORRECT
- The correct answer is C, remove ends of
remaining pipe to at least 2 feet below subgrade.
The answer can be found in Section 330.41(a-7),
Pg 82 of the 2008 Standard Specifications.
10435.
When 5 of the original contract amount is earned
from other contract items, not including advances
on materials, the contractor should be paid which
of the following for mobilization?
- 1 of the mobilization amount or 1 of the
original contract amount, whichever is smaller - 50 of the mobilization amount or 5 of the
original contract amount, whichever is smaller - 10 of the mobilization amount or 10 of the
original contract amount, whichever is smaller - There is no payment due at this time.
10535.
When 5 of the original contract amount is earned
from other contract items, not including advances
on materials, the contractor should be paid which
of the following for mobilization?
CORRECT!
10635.
When 5 of the original contract amount is earned
from other contract items, not including advances
on materials, the contractor should be paid which
of the following for mobilization?
- INCORRECT
- The correct answer is B. The answer can be
found in Section 219.90, Pg 4 of the 2008
Standard Specifications.
10736.
HMAC vibratory rollers (not used for finish
rolling) shall be
- Capable of at least 2000 vibrations a minute
- Have a gross static weight of at least 6 tons
- Be tandem or multiple axle, multiple wheel type
- Both A and B
10836.
HMAC vibratory rollers (not used for finish
rolling) shall be
CORRECT!
10936.
HMAC vibratory rollers (not used for finish
rolling) shall be
- INCORRECT
- The correct answer is A, capable of at least
2000 vibrations a minute. The answer can be found
in Section 745.24(b), Pg 476 of the 2008 Standard
Specifications.
11037.
Where can a list of approved manufacturers of
steel reinforcement for concrete can be found?
- The ODOT Construction Manual
- Section 02510 of the ODOT Standard Specifications
- The Non-Field Tested Materials Acceptance Guide
(NFTMAG) - The Qualified Products List (QPL)
11137.
Where can a list of approved manufacturers of
steel reinforcement for concrete can be found?
CORRECT!
11237.
Where can a list of approved manufacturers of
steel reinforcement for concrete can be found?
- INCORRECT
- The correct answer is D, the QPL. The answer
can be found in the Qualified Products List, Pg
55-56.
11338.
Which of the following are requirements when the
contractor is using a Portable Changeable Message
Sign (PCMS)?
- Entire message is displayed within 7.5 seconds
- Using no more than two (2) displays within any
message cycle - Messages shall not scroll horizontally or
vertically across the sign face - Both A and C
- All of the above
11438.
Which of the following are requirements when the
contractor is using a Portable Changeable Message
Sign (PCMS)?
CORRECT!
11538.
Which of the following are requirements when the
contractor is using a Portable Changeable Message
Sign (PCMS)?
- INCORRECT
- The correct answer is D, both A and C. The
answer can be found in Section 225.46(b), Pg 28
of the 2008 Standard Specifications.
11639.
What type of fertilizer is required when it is
used near water?
- Inorganic fertilizer 22-16-8
- Inorganic fertilizer 22-10-5
- Low-phosphorus fertilizer 22-2-11
- None of the above
11739.
What type of fertilizer is required when it is
used near water?
CORRECT!
11839.
What type of fertilizer is required when it is
used near water?
- INCORRECT
- The correct answer is C, low-phosphorus
fertilizer 22-2-11. The answer can be found in
Section 1030.14(b-3), Pg 626 of the 2008 Standard
Specifications.
11940.
What is the required material to use when
backfilling a signal conduit trench in an
existing roadway area?
- Selected granular backfill
- HMAC
- Control low strength material
- Both A and B
12040.
What is the required material to use when
backfilling a signal conduit trench in an
existing roadway area?
CORRECT!
12140.
What is the required material to use when
backfilling a signal conduit trench in an
existing roadway area?
- INCORRECT
- The correct answer is C, controlled low
strength material. The answer can be found in
Section 960.41(g-1-c-2), Pg 589 of the 2008
Standard Specifications.
12241.
Which of the following Quality Compliance
Documents are required for precast Concrete
Barrier if supplied by an approved supplier?
- Quality Compliance Certificate
- Test Result Certificate
- Field Inspection Report
- Manufacturers Warranty
- All of the above
12341.
Which of the following Quality Compliance
Documents are required for precast Concrete
Barrier if supplied by an approved supplier?
CORRECT!
12441.
Which of the following Quality Compliance
Documents are required for precast Concrete
Barrier if supplied by an approved supplier?
- INCORRECT
- The correct answer is C, Field Inspection
Report. The answer can be found in the Non-Field
Tested Materials Acceptance Guide, Pg 21.
12542.
What is the required post spacing for supported
sediment fence?
- 4 feet
- 6 feet
- 8 feet
- 2 feet
12642.
What is the required post spacing for supported
sediment fence?
CORRECT!
12742.
What is the required post spacing for supported
sediment fence?
- INCORRECT
- The correct answer is A, 4 feet. The answer can
be found in the Standard Drawings RD-1040.
12843.
Which of the following sheets shows the locations
of Bid Item 860?
- Standard Drawing RD100
- Sheet 4
- Sheet 3
- Sheet 5
12943.
Which of the following sheets shows the locations
of Bid Item 860?
CORRECT!
13043.
Which of the following sheets shows the locations
of Bid Item 860?
- INCORRECT
- The correct answer is D, Sheet 5.
13144.
The 12 pipe extension on Sheet 4B is NOT
required to have watertight joints.
- True
- False
13244.
The 12 pipe extension on Sheet 4B is NOT
required to have watertight joints.
CORRECT!
13344.
The 12 pipe extension on Sheet 4B is NOT
required to have watertight joints.
- INCORRECT
- The correct answer is True. The answer can be
found on Sheet 2C.
13445.
The required Erosion and Sediment Control
Emergency Measures for the Project are
- 100 biofilter bags and 300 of straw wattles
- 12 check dams, 2 inlet protection and 1000 of
sediment fence, supported - 1 tire wash facility, 2000 of plastic sheeting
and 0.75 acre of matting - 12 check dams, 2 inlet protection and 1000 of
sediment fence, unsupported
13545.
The required Erosion and Sediment Control
Emergency Measures for the Project are
CORRECT!
13645.
The required Erosion and Sediment Control
Emergency Measures for the Project are
- INCORRECT
- The correct answer is D. The answer can be
found in the Section 280.48, Pg 15-16 of the
Special Provisions.
13746.
Items such as strain poles, terminal cabinets,
pedestrian and vehicle signals become the
property of the contractor upon removal.
- True
- False
13846.
Items such as strain poles, terminal cabinets,
pedestrian and vehicle signals become the
property of the contractor upon removal.
CORRECT!
13946.
Items such as strain poles, terminal cabinets,
pedestrian and vehicle signals become the
property of the contractor upon removal.
- INCORRECT
- The correct answer is False. The answer can be
found in the Section 950.42, Pg 50 of the Special
Provisions.
14047.
The minimum required thickness of aggregate base
material is 6 inches for sidewalk ramps and
pedestrian landings.
- True
- False
14147.
The minimum required thickness of aggregate base
material is 6 inches for sidewalk ramps and
pedestrian landings.
CORRECT!
14247.
The minimum required thickness of aggregate base
material is 6 inches for sidewalk ramps and
pedestrian landings.
- INCORRECT
- The correct answer is False. The answer can be
found on Sheet 2B-5, Section A-A.
14348.
At station CL 2875 Lt., what is to be
constructed?
- Construction approach
- PCC monolithic curb and sidewalk
- Road connection
- This is a No Work zone
14448.
At station CL 2875 Lt., what is to be
constructed?
CORRECT!
14548.
At station CL 2875 Lt., what is to be
constructed?
- INCORRECT
- The correct answer is C, road connection. The
answer can be found on Sheet 4.
14649.
At station CL 2800, the second lift of HMAC base
course shall be what thickness?
- 2 inches
- 3 inches
- 4 inches
- There is only one lift of HMAC base course at
this station
14749.
At station CL 2800, the second lift of HMAC base
course shall be what thickness?
CORRECT!
14849.
At station CL 2800, the second lift of HMAC base
course shall be what thickness?
- INCORRECT
- The correct answer is B, 3 inches. The answer
can be found on Sheet 2A-2.
14950.
At station CN 9190, what is the thickness and
type of wearing course needed?
- 3, ¾ open graded
- 2, Level 3 ¾ open graded
- 2, ¾ open graded
- 2, ¾ dense graded
15050.
At station CN 9190, what is the thickness and
type of wearing course needed?
CORRECT!
15150.
At station CN 9190, what is the thickness and
type of wearing course needed?
- INCORRECT
- The correct answer is B, 2 inches, Level 3 ¾
inch open graded The answer can be found on Sheet
2A-3.
15251.
How is sign 57 mounted?
- Clamped to signal pole
- Mounted overhead on mast-arm
- Re-installed with existing hardware
- None of the above
15351.
How is sign 57 mounted?
CORRECT!
15451.
How is sign 57 mounted?
- INCORRECT
- The correct answer is A, clamped to signal
pole. The answer can be found on Sheet S-7894.
15552.
Which of the following is NOT correct for a
construction entrance?
- 50 foot minimum for 2.3 acres of exposed soil
- 25 foot minimum radius
- 20 foot width over an existing 18 foot wide
approach - None of the above
15652.
Which of the following is NOT correct for a
construction entrance?
CORRECT!
15752.
Which of the following is NOT correct for a
construction entrance?
- INCORRECT
- The correct answer is A, 50 foot minimum for
2.3 acres of exposed soil. The answer can be
found in the Standard Drawings RD-1000.
15853.
The Agency Archaeologist for this project is
Patrick OGrady.
- True
- False
15953.
The Agency Archaeologist for this project is
Patrick OGrady.
CORRECT!
16053.
The Agency Archaeologist for this project is
Patrick OGrady.
- INCORRECT
- The correct answer is True. The answer can be
found in the Section 290.51, Pg 20 of the Special
Provisions.
16154.
According to Contract 13127, a steel-wheeled
roller that is used for finish rolling of a Level
3 HMAC mix shall have a minimum static weight of
_______.
- 6 tons
- 8 tons
- 10 tons
- 12 tons
16254.
According to Contract 13127, a steel-wheeled
roller that is used for finish rolling of a Level
3 HMAC mix shall have a minimum static weight of
_______.
8 tons
CORRECT!
16354.
According to Contract 13127, a steel-wheeled
roller that is used for finish rolling of a Level
3 HMAC mix shall have a minimum static weight of
_______.
- INCORRECT
- The correct answer is B, 8 tons. The answer can
be found in the Section 745.24(a), Pg 45 of the
Special Provisions.
16455.
The placement tolerance for the thickness of
lines for pavement markings are which of the
following?
- 1/3 of specified thickness
- 1/3 of manufacturers recommendations
- 1/3 or 1/10 of specified thickness
- None of the above
16555.
The placement tolerance for the thickness of
lines for pavement markings are which of the
following?
CORRECT!
16655.
The placement tolerance for the thickness of
lines for pavement markings are which of the
following?
- INCORRECT
- The correct answer is C, 1/3 or -1/10 of
specified thickness. The answer can be found in
the Section 850.46, Pg 47 of the Special
Provisions.
167(No Transcript)