Grid Connections: Now and the Future - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Grid Connections: Now and the Future

Description:

The big electricity pylons you see in GB are normally transmission network, ... through a stepdown transformer and underground cable to a load at the far end. – PowerPoint PPT presentation

Number of Views:158
Avg rating:3.0/5.0
Slides: 25
Provided by: ami49
Category:

less

Transcript and Presenter's Notes

Title: Grid Connections: Now and the Future


1
Grid ConnectionsNow and the Future
10th November 2010
Patrick Smart Head of Commercial and Regulatory
2
Agenda
  • Introduction to SEL
  • Overview of Grid and Grid Process
  • Technical challenges
  • National Grids impact on renewables
  • How to manage Grid risk
  • The future of grid connections

3
Senergy Econnect Ltd
  • Established as Econnect in 1995
  • Grid connection of all renewable generation
    technologies
  • Hagshaw Hill, North Hoyle Landmark projects for
    UK Renewables
  • Electrical Engineering and Commercial and
    Regulatory Consulting
  • Now part of Senergy Group, based in Newcastle

4
The GB Network
5
Overview of Electricity Industry

1 Transmission GB System Operator
NGETL
NGETL Scottish Power, Scottish Hydro-Electric
3 transmission owners
14 Distribution Network Operators (7 companies)
6
Distribution Network Areas
7
Securing Grid Capacity
  • Accept a connection offer
  • which generally requires a down payment (70K to
    200k for commercial onshore wind)
  • and a commitment to progress construction
  • So when do I initiate the grid process? Planning
    or grid first?
  • Some information in the public domain DNO Long
    Term Development Statements.

8
DNO Connection Process
  • DNOs obliged to offer terms to connect to network
  • Submit competent application (likely DNO up front
    fee in the near future)
  • Offer within 3 months
  • Open for acceptance for 30 days or 3 months. Can
    normally be extended but not guaranteed.
  • Acceptance usually requires initial down payment
    to cover detailed studies and design.

9
DNO Point of Connection Offers
  • Non-contestable connection works only
  • New Standards in effect from 1 October 2010
  • Obliged to offer budget estimates within set
    period (20 WDs for commercial projects)
  • PoC Offers - DNO liable for compensation of 150
    per day late!!!! (for applications received
    after 1 October 2010..)
  • All works offers DNOs to include 4 margin on
    contestable works

10
Connection Offer Process
  • Offers of terms for connection open for
    acceptance for 30 days or 3 months.
  • Can normally be extended but this is not
    guaranteed.
  • Acceptance usually requires initial down payment
    - 70K to 200k
  • Obligation to agree construction programme

11
DNO Connection Offer Content
  • Outline of connection solution
  • Outline of DNO works, reinforcements and
    construction program
  • Technical and communication requirements
  • Users obligation (design to ENA standards)
  • Price (often indicative until contracts placed)
  • Connection cost and risk project specific

12
Connection Offer Process National Grid
  • Transmission System Impact
  • Dash for Wind in late 2004 / 2005.
  • Massive shortfall of grid capacity relative to
    applications / agreements (note not necessarily
    consented wind)
  • The GB Queue
  • Much of the GB Queue connecting at distribution
    voltage

13
Connection Offer Process National Grid
14
Connection Offer Process National Grid
  • Managed through embedded bilateral agreements and
    the Statement of Works process
  • Large generators must enter into a bilateral
    agreement (BELLA or BEGA)
  • Small / medium generators may be referred to
    National Grid for a Statement of Works.
  • National Grid responds with view on transmission
    system impact

15
Key Technical Considerations
  • Three main network problems
  • Thermal capacity
  • Fault levels
  • Voltage rise
  • Further technical considerations
  • Harmonics
  • Voltage Flicker
  • Design requirements (e.g. G59)
  • If you cause technical problems, your connection
    will take longer to complete and be more
    expensive.

16
Thermal Capacity
Safety clearance
  • Overheating leads to insulation failure
  • Reverse power flow capability?

17
Fault Currents
Primary Substation
Distribution Feeder
Fault Current
G
Contribution of current to a fault on network can
lead to an overstressing of existing switchgear
and is a major limiting factor to the connection
of embedded generation
18
Voltage Rise
Overhead line
19
Voltage Rise - Mitigation
Substation
Within limits
20
Connection Offer Process Key Messages
  • Assess grid early (publicly available
    information)
  • Engage with the DNO and stay in touch
  • Ask about National Grid impact
  • Plan submission of connection application in
    light of process delays and obligation to commit
    c100k
  • Reflect outputs from assessment and DNO liaison
    in application

21
Future Grid Connections
Transmission Generators
Transmission Network
Transmission Generators
Distribution Network
Consumers
22
Grid Connections in the Future
  • Regulatory reform RIIO (Revenue Incentives
    Innovation Outputs)
  • Key principles
  • Focus on outputs and delivery (more from assets)
  • Longer term view (decarbonisation)
  • Reward for higher performance
  • Encourage innovation (prizes)
  • 32 billion of investment required
  • What does that mean for grid connections?

23
Grid Connections in the Future
  • Who knows.watch the RIIO space..BUT
  • Opportunities for new technologies / techniques
    to raise long term efficiency
  • Smart Grids (?) from dynamic substation control
    to domestic load switching.
  • Electrical efficiency of connecting close to
    significant points of demand.
  • Extend on the principle of negative GDUoS for HV
    connections.

24
Patrick SmartHead of Commercial
Regulatory0191 238 7344patrick.smart_at_senergywor
ld.com
Write a Comment
User Comments (0)
About PowerShow.com