Title: Grid Connections: Now and the Future
1Grid ConnectionsNow and the Future
10th November 2010
Patrick Smart Head of Commercial and Regulatory
2Agenda
- Introduction to SEL
- Overview of Grid and Grid Process
- Technical challenges
- National Grids impact on renewables
- How to manage Grid risk
- The future of grid connections
3Senergy Econnect Ltd
- Established as Econnect in 1995
- Grid connection of all renewable generation
technologies - Hagshaw Hill, North Hoyle Landmark projects for
UK Renewables - Electrical Engineering and Commercial and
Regulatory Consulting - Now part of Senergy Group, based in Newcastle
4The GB Network
5Overview of Electricity Industry
1 Transmission GB System Operator
NGETL
NGETL Scottish Power, Scottish Hydro-Electric
3 transmission owners
14 Distribution Network Operators (7 companies)
6Distribution Network Areas
7Securing Grid Capacity
- Accept a connection offer
- which generally requires a down payment (70K to
200k for commercial onshore wind) - and a commitment to progress construction
- So when do I initiate the grid process? Planning
or grid first? - Some information in the public domain DNO Long
Term Development Statements.
8DNO Connection Process
- DNOs obliged to offer terms to connect to network
- Submit competent application (likely DNO up front
fee in the near future) - Offer within 3 months
- Open for acceptance for 30 days or 3 months. Can
normally be extended but not guaranteed. - Acceptance usually requires initial down payment
to cover detailed studies and design.
9DNO Point of Connection Offers
- Non-contestable connection works only
- New Standards in effect from 1 October 2010
- Obliged to offer budget estimates within set
period (20 WDs for commercial projects) - PoC Offers - DNO liable for compensation of 150
per day late!!!! (for applications received
after 1 October 2010..) - All works offers DNOs to include 4 margin on
contestable works
10Connection Offer Process
- Offers of terms for connection open for
acceptance for 30 days or 3 months. - Can normally be extended but this is not
guaranteed. - Acceptance usually requires initial down payment
- 70K to 200k - Obligation to agree construction programme
11DNO Connection Offer Content
- Outline of connection solution
- Outline of DNO works, reinforcements and
construction program - Technical and communication requirements
- Users obligation (design to ENA standards)
- Price (often indicative until contracts placed)
- Connection cost and risk project specific
12Connection Offer Process National Grid
- Transmission System Impact
- Dash for Wind in late 2004 / 2005.
- Massive shortfall of grid capacity relative to
applications / agreements (note not necessarily
consented wind) - The GB Queue
- Much of the GB Queue connecting at distribution
voltage
13Connection Offer Process National Grid
14Connection Offer Process National Grid
- Managed through embedded bilateral agreements and
the Statement of Works process - Large generators must enter into a bilateral
agreement (BELLA or BEGA) - Small / medium generators may be referred to
National Grid for a Statement of Works. - National Grid responds with view on transmission
system impact
15Key Technical Considerations
- Three main network problems
- Thermal capacity
- Fault levels
- Voltage rise
- Further technical considerations
- Harmonics
- Voltage Flicker
- Design requirements (e.g. G59)
- If you cause technical problems, your connection
will take longer to complete and be more
expensive.
16Thermal Capacity
Safety clearance
- Overheating leads to insulation failure
- Reverse power flow capability?
17Fault Currents
Primary Substation
Distribution Feeder
Fault Current
G
Contribution of current to a fault on network can
lead to an overstressing of existing switchgear
and is a major limiting factor to the connection
of embedded generation
18Voltage Rise
Overhead line
19Voltage Rise - Mitigation
Substation
Within limits
20Connection Offer Process Key Messages
- Assess grid early (publicly available
information) - Engage with the DNO and stay in touch
- Ask about National Grid impact
- Plan submission of connection application in
light of process delays and obligation to commit
c100k - Reflect outputs from assessment and DNO liaison
in application
21Future Grid Connections
Transmission Generators
Transmission Network
Transmission Generators
Distribution Network
Consumers
22Grid Connections in the Future
- Regulatory reform RIIO (Revenue Incentives
Innovation Outputs) - Key principles
- Focus on outputs and delivery (more from assets)
- Longer term view (decarbonisation)
- Reward for higher performance
- Encourage innovation (prizes)
- 32 billion of investment required
- What does that mean for grid connections?
23Grid Connections in the Future
- Who knows.watch the RIIO space..BUT
- Opportunities for new technologies / techniques
to raise long term efficiency - Smart Grids (?) from dynamic substation control
to domestic load switching. - Electrical efficiency of connecting close to
significant points of demand. - Extend on the principle of negative GDUoS for HV
connections.
24Patrick SmartHead of Commercial
Regulatory0191 238 7344patrick.smart_at_senergywor
ld.com