Extraordinary General Assembly

1 / 17
About This Presentation
Title:

Extraordinary General Assembly

Description:

derrick under completion. 4 1. 5 1. Why Thule Drilling is actively supporting the revised completion date: ... Over 1,000 CTRs (Cost Time Resources document) ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 18
Provided by: plro3

less

Transcript and Presenter's Notes

Title: Extraordinary General Assembly


1
Extraordinary General Assembly March 16 2007
2
Thule Power at QGM- Expected delivery May
07 Rebuilt 250 ft Jack-up 30.000 feet
drilling depth Quarters up to 108 people
Automatic pipe handling Varco Drilling package
3
Thule PowerCantilever with drill floor and
derrick under completion
4
(No Transcript)
5
Why Thule Drilling is actively supporting the
revised completion date
  • Major changes in the QGM project organization
    implemented early December 2006
  • Experienced personnel from Davie Shipyard engaged
    by QGM on management as well as supervisory
    levels from end December 2006
  • Experienced Commissioning Manager employed from
    Keppel Fels, Singapore
  • Increased Owner site team personnel
  • Integration of KCA Deutag operating personnel
    into day to day construction activity
    (supervision commissioning)
  • Adequate labour resources allocated (540 present
    increasing to about 580 at peak) on TP
  • Optimal manning at all work fronts
  • Increased manning on night shift to near dayshift
    level
  • Involvement in planning by all managers and
    supervisors 3 weeks to complete the plan
  • Over 1,000 CTRs (Cost Time Resources document)
    issued as basis for the new plan

6
Thule Power Saudi Aramco Contract
  • 4 year fixed contract, with one year option
  • Commencement May 2007
  • Penalties starts accruing at USD 73,500/day
    from 1 March 2007
  • Contract Value USD 215 mill incl. mob
  • EBITDA contribution over the fixed contract
    to Thule USD 123 mill
  • Manager and Contractor KCA Deutag

7
JU New buildings at QGM
  • Friede Goldman Super M2 Design
  • Proven design 30 units built (L780)
  • 300 ft water depth w/fixation
  • 30 000 ft drilling depth capacity
  • Accommodation 100 people
  • 3 000 ton variable load
  • 57 ft cantilever reach
  • Ideally suited for the Middle East area
  • Delivery
  • 1st unit 1st quarter 2008
  • 2nd unit 2nd quarter 2008
  • Both units are on schedule for these
  • adjusted deliveries.

8
NEWBUILDINGSAssembly site at QGMs main yard at
Hamriyah, UAE (Jan 2007)
Thule Energy Thule Force
9
Thule Drilling marketing strategy newbuildings
  • Thule Energy Thule Force
  • Objective Long term contract for one of the
    rigs in place within 3Q 2007
  • Market target Middle East South East Asia,
    where rigs are best suited
  • Joint market approach with KCA Deutag to
    present to the customers a fully integrated
    Contractor
  • Several bids submitted and rigs have been
    pre-qualified by several oil companies

10
QGM Financial status today
  • QGM is still short of funding to complete all
    three projects unless other work can be secured
    or additional funds are made available
  • QGM and Thule Drilling are cooperating to find
    alternative sources for this funding
  • Alternative sources being pursued
  • Financial investors
  • Industrial investors
  • Thule Drilling already made USD 22 mill
    available
  • All alternatives will probably entail change of
    control or substantial ownership transfer of
    shares in QGM
  • Value of QGM is more than funding required and
    debt to Thule

11
Financing May 2007
Bond Issue
  • Amount USD 40 mill
  • Duration 18 months
  • Interest 13.75 semi annually
  • Redemption USD 20 mill when 1 pri. bank
    facility is established
  • Call structure 103 first 6 months, 102 next 6
    months, 101 last 6 months
  • Security priority after the USD 130 mill bond
    loan

Equity issue
  • Amount NOK 220 mill (aboutt USD 35 mill)
  • Guaranteed by a group of existing shareholders
  • Share price NOK 13.06
  • Total number of shares 36.95 million 16.85
    million 53.8 million

12
Reason for Additional funding Required
All numbers in USD million
  • Penalty Thule Power re Saudi Aramco contract 7
  • Postponed income due to delay Thule Power 8
  • Locked in Escrow (operational, KCA Deutag) 5
  • Additional cost / change orders Thule Power 4
  • Assumed no exercise of Warrants 18
  • Phoenix upgrade for sale 1
  • Remaining (fees, potential yard finance,
    reserve) 41
  • TOTAL 84
  • Financed Through
  • Equity 35
  • Bond placed today 40
  • Bond Feb Thule Phoenix 9
  • Total 84

13
Rig Mortgage overview after bond issue
  • Market value of units less pledged USD 144 mill
  • Market values as is

14
Rig mortgage overview after delivery of Thule
Power
  • Market value of units less pledged USD 176 mill
  • Market values as is for Thule Energy and Thule
    Force

15
Rig mortgage overview end of Q3 2008 all rigs
delivered
  • Market value of units less pledged USD 375 mill
  • Market values as completed Jack-ups

16
Total asset (book) value and interest bearing debt
17
Thule Drilling continues to be an attractive
investment case
  • Thule Power is a profitable project
  • Cost is still low compared with new-buildings
  • Attractive contract with payback well within
    the contract term
  • Two new jack-ups under construction at attractive
    prices
  • Two Jack-ups delivered at the right time in an
    expected promising market
  • QGM a lesson learnt Thule has better control
    of their operation
  • QGMs infrastructure and yard facilities nearly
    fully upgraded (USD 20 mill invested)
  • Thule Drilling favorable balance sheet with
    around 45 equity (on proforma balance)
Write a Comment
User Comments (0)